Note it’s Minnesota, the Lakefield-E Adair, IA isn’t shown

Oh, lordy, a handful, or more, of prior non-transmission clients affected by this — got notice from two recently, they learned from postcards in the mail. No, that’s not campaign pre-caucus blurbs! Very glad they didn’t throw them away. Also heard of another person down in the Iowa section today! So many are affected by this MISO Tranche 2.1.

Now, on to the “Power on Midwest” projects that dropped today:

These were FOUR Certificate of Need dockets, CN-25-117, CN-25-118, CN-25-119, and CN-25-120. They’ve been consolidated into ONE. Here’s the rough breakdown from the application (linked below, p. 4-5):

Here’s the application, all across southwest and south central Minnesota, and heading north to the “North Rochester” substation north of Pine Island and on to Hampton:

A little light reading so you’ll be ready for the round of scoping & early comment meetings in a week or two…