Exhibit List – PowerOn Midwest
November 24th, 2026
Here’s the Master Exhibit List with working links so you can check out what’s in the record for this PowerOn Midwest hearing (PUC Docket CN-25-117).
Links should all work:
PPSA Annual Hearing December 9
November 24th, 2026
It’s that time of year again, the time we get to tell the PUC how its routing and siting of utility infrastructure is working and not working. Mickey Mouse is a more appropriate PPSA Annual Hearing than ever.
What’s the “Power Plant Siting Act Annual Hearing?” Good question, because the Power Plant Siting Act was repealed, now it’s “Energy Infrastructure Permitting:
All the rules but THREE were repealed, and only two could apply to transmission lines.
Arguable the most important of those three is standards and criteria for siting:
Great, it’s preserved. So let’s take a look at 216E.03:
Well, that’s reassuring… So what does 216E.04 have to say?
Oh, OK…
Years back, we’d spent YEARS working on updating the 7849 and 7850 rules, but in 2022:
Minn. R. ch 7849 & 7850 Rulemaking? DEAD!
When I saw there were no longer routing and siting rules, I’d filed a rulemaking petition, as the new 216I says, the Commission “may” adopt rules:
Anyway, the PUC tossed out the Rulemaking Petition — Rulemaking? Who needs rules!
And then a bizarre notice, just five days ahead of time, given the panelist link, and then DISINVITED! Funny how that works.
Last minute notice (and disinvited!) – PUC “Planning Meeting” June 18th, 2026
Implementation of MN’s 216I?!?!?! June 26th, 2026
Methinks there will be plenty to say at this year’s hearing, as always.
As for prior hearings:
2024 Summary Report_– Docket 24-18
And going way, way back (I don’t have record of the earlier ones, but we had some tremendous pot lucks way way back!):
2006 Report to PUC – Docket 06-1733
2007 Report to PUC – Docket 07-1579
2008 Report to PUC – Docket 08-1426
2009 Report to PUC – Docket 09-1351
2010 Report to PUC – Docket 10-222
2011 Report to PUC – Docket 11-324
2012 Report to PUC – Docket 12-360
2013 Report to PUC – Docket 13-965
2014 Summary Report– Docket 14-887
2015 Summary Report – Docket 15-785
2017 Summary Report – Docket 17-18
2018 Summary Report – Docket 18-18
2019 Summary Report_Docket 19-18
2020 Summary Report – Docket 20-18
2021 Summary Report – Docket 21-18
2022-Summary-Report_Docket 22-18
It’s a busy time in SE Minnesota!
November 23rd, 2026
Last night, a very well attended meeting in Viola Town Hall, just east of Rochester. This project is at issue because after a very detailed ALJ’s Recommendation, the Public Utilities Commission did a complete 180, and the behavior displayed on the dais was just plain ugly.
LISTEN TO THIS MEETING – STARTS AT 33:44 – October 22 Public Utilities Commission Meeting: (won’t let me embed)
Olmsted County residents worry about losing farmland due to Lemon Hill Solar Project
(FYI, it’s about a lot more than farmland!)
And now on to transmission — this is North Route Group and NO765MN challenging the “Gopher to Badger Link” 765kV transmission project, a meeting in Mazeppa a week ago:
‘David and Goliath’: Rural residents fight proposed transmission line in SE Minnesota
… and…
Mazeppa flower farmer says proposed 765-kV line would put her out of business
The Public Utilities Commission is regulatory capture personified. Lots of work to do!
Gopher-Badger “Complete” and Intervention filed
November 20th, 2026
Earlier today, the Public Utilities Commission posted in eDockets that the Route Application for Gopher-Badger Link (TL-26-156) is “complete” by their standards:
So on that happy note, I filed the Intervention Petition:
Some Info Requests from 25-117
November 15th, 2026
Spending the weekend organizing, and there are some delightful responses to Information Requests from parties in the PUC’s PowerOn Midwest docket. They’re not in the record yet, so if you want to use them (PLEASE DO) you can cite to the document’s legalectric.org link and ATTACH THE DOCUMENT TO YOUR COMMENT! If folks do this, it’ll be harder to ignore this important info.
First the laundry list, and below, links to the documents:
- DOC 5 – Long Term Costs – see also W. Ben Johnson’s “dissertation” chart comparing long terms costs of AC and DC
- DOC 7 – more on costs
- DOC 8 – MISO Variance Analysis
- DOC 11 – Federal $$$
- DOC 12 & 13 – Cost change
- DOC 14(a), (b) – 64% increase in cost of Tranche 2.1 (do the math and be astounded)
- DOC 16 – Allocated share to us – 18-24% (do the math based on that 64% increase and be astounded)
- DOC 17 – MISO’s role developing Tranche 2.1
- DOC 18 – Land Impacts
- MISO 2 – Transmission alternatives – planning
- MISO 4 – Proxy route
- MISO 5 – Cost Benefit Update? NOPE!
- MISO 7 – Cost Benefit
- MISO 8 – Independent Market Monitor
++++++++++++++++
Though not in an Information Request, you should know that MISO filed Complaint to FERC (FERC Docket EL-25-80-000) to limit authority of its Independent Market Monitor, and, well, FERC explained in technicolor what they though of that move – this is public info on the FERC docket. If you use it, cite to the FERC docket with link (https://elibrary.ferc.gov/eLibrary/docketsheet?docket=el25-80-000) :
Once more with feeling:











