Some Info Requests from 25-117
November 15th, 2026
Spending the weekend organizing, and there are some delightful responses to Information Requests from parties in the PUC’s PowerOn Midwest docket. They’re not in the record yet, so if you want to use them (PLEASE DO) you can cite to the document’s legalectric.org link and ATTACH THE DOCUMENT TO YOUR COMMENT! If folks do this, it’ll be harder to ignore this important info.
First the laundry list, and below, links to the documents:
- DOC 5 – Long Term Costs – see also W. Ben Johnson’s “dissertation” chart comparing long terms costs of AC and DC
- DOC 7 – more on costs
- DOC 8 – MISO Variance Analysis
- DOC 11 – Federal $$$
- DOC 12 & 13 – Cost change
- DOC 14(a), (b) – 64% increase in cost of Tranche 2.1 (do the math and be astounded)
- DOC 16 – Allocated share to us – 18-24% (do the math based on that 64% increase and be astounded)
- DOC 17 – MISO’s role developing Tranche 2.1
- DOC 18 – Land Impacts
- MISO 2 – Transmission alternatives – planning
- MISO 4 – Proxy route
- MISO 5 – Cost Benefit Update? NOPE!
- MISO 7 – Cost Benefit
- MISO 8 – Independent Market Monitor
++++++++++++++++
Though not in an Information Request, you should know that MISO filed Complaint to FERC (FERC Docket EL-25-80-000) to limit authority of its Independent Market Monitor, and, well, FERC explained in technicolor what they though of that move – this is public info on the FERC docket. If you use it, cite to the FERC docket with link (https://elibrary.ferc.gov/eLibrary/docketsheet?docket=el25-80-000) :
Once more with feeling:
FERC Docket EL-25-80-000
Some articles from the PoM Public Hearings
November 14th, 2026
It was a long week, 258 miles between all the locations, plus the to and fro miles. There’s ONE hearing left, in Kasson on Monday, plus a virtual hearing that evening:
There was some good media coverage:
Pipestone: Objections heard during transmission line public hearing
Slayton: PUBLIC HEARING REGARDING POWERON MIDWEST PROPOSED LINES HELD IN SLAYTON
Worthington: PowerOn Midwest scrutinized by public comments
Windom: (none?)
(And before hearings: Fairmont Sentinel: PowerOn Project getting its necessity tested)
And waiting for others to show up!
At several of the meetings a man was handing out a packet of info from Arthur Firstenberg — much of it may have been from Firstenberg’s “The Invisible Rainbow: A History of Electricity and Life.” His handout:
UPDATE: County & Township filings – PowerOn Midwest
November 12th, 2026

UPDATED: October 20, 21, 23, 29, and November 6, 12, 2026! Keep those resolutions coming!
Here are the Resolutions filed thus far by Counties and Townships affected by PowerOn Midwest 765kV transmission (PUC Docket CN-25-117) through their communities. Some are forms, fill in the blank even, and I’m hoping that there will be more individual ones filed — individually drafted filings have greater weight, greater impact.
Cities:
Counties:
Townships:
DOT Exhibits just filed – PowerOn Midwest
November 12th, 2026
Just filed, exhibits proposed to enter with MN Department of Transportation testimony, under subpoena, in the PowerOn Midwest hearing. It’s about DOT coordination with the Applicants, per Minn. Stat. 161.45 to use highway corridors for routing transmission (not “just” interstates, there are many highways in southern Minnesota), and most importantly, what the DOT is looking at regarding Direct Current underground.
Broken down into pieces:
DNR Data Practices Request
November 11th, 2026
Quite a while ago I’d sent in a Data Practices Act request to the Minnesota Department of Natural Resources because I hadn’t seen DNR comments on either of these 765kV transmission projects (Gopher to Badger and PowerOn Midwest).
Info arrived today!!
And btw, in this bunch of pdfs is proof positive that Kyle Johnson and Charlie Wray are ON THIS! But what’s also clear is that the DNR is not actively digging into this project. So there’s more work to do.
In no particular order:
I also sent another DPA Request when I learned that “one option” is to run that line on the other side of the lake from Myre-Big Island State Park.
I’m attached to that park, had a few meetings with Association of Freeborn County Landowners there, and of course, camp hosting in September, 2019. When I saw that map above, I had a chat with folks at the park, who hadn’t heard about it!

No response yet.