NPS pressured about Susquehanna-Roseland EIS
July 21st, 2011
First, the bad news – the Commonwealth Court of Pennsylvania has affirmed the Order of the Pennsylvania Public Utilities Commission approving the Susquehanna-Roseland transmission project:
Commonwealth Court of Pennsylvania – Affirms Pennsylvania’s S-R Order
And now, on to the pressure… The National Park Service is working to do it’s job as steward of our national park land, in this case, the federally declared Wild and Scenic Delaware River and the Delaware Water Gap.
Seems that some don’t think they should be allowed to do that job, and are pressuring them to “hurry up” so the Susquehanna-Roseland transmission line can steamroll on through. Well, BACK OFF!
Today the pressure on NPS was overt in two venues. First, U.S. Rep. Charlie Dent (R-PA) amends a bill to push the NPS to complete its environmental review one year ahead of schedule. Say what?!?!?!
Then in my inbox a sour grapes press release from FERC Commissioner Phillip Moeller whining because the newly adopted rule won’t do what he wants, it won’t address “problems” like NPS doing its proper review of transmission projects:
Here’s the Susquehanna-Roseland specific part:
“While I offer substantial praise for today’s final rule, the Commission should have taken a different approach to several important issues. We must recognize that all of the nation’s difficulties in building needed transmission will not be resolved by this rule. Rather, this rule largely addresses planning for long-distance transmission lines, which is only a subset of the critical issues that are inhibiting needed investment.
This rule cannot address issues like the delays caused by other federal agencies in the siting of important projects, as this Commission lacks the legal authority to require other federal agencies to act. For example, see the comments of PJM in this proceeding at p. 17, which state that:
[t]he PJM Board approved the Susquehanna-Roseland 500 kV line in 2007. The Susquehanna-Roseland line was approved by the state regulatory commissions in Pennsylvania and New Jersey for 2012. The line is currently delayed by the National Parks Service [sic] and is not expected to be in service until 2014 at the earliest.
Ohhhhhhhh, isn’t it too bad. He’s just one Commissioner, and he’s got to put his dissent out there as an extensive and extended rulemaking proceeding closes… Why is he pushing, why does he care, and why does his care rise to the level that he sends out a dissenting press release? Lighten up, the National Park Service has a job to do. As the testimony in the Susquehanna-Roseland proceeding before the New Jersey Board of Public Utilities reflects, we are NOT going to freeze in the dark in an incubator without a job…
And here’s Pre. Charlie Dent’s whine:
Charlie Dent pushes expedited federal review of Susquehanna-Roseland power line proposal
Published: Thursday, July 21, 2011, 4:30 AM
By Tom Rowan Jr. | The Express-TimesAnd the New Jersey Sierra Club wants Dent, R-Lehigh Valley, to back off.
If it passes through the House, it would be referred to the Senate.
Confirmed: Bulk power transfer to New York
July 1st, 2011
DUH! We all know what the point of the Susquehanna-Roseland transmission is, PSEG! Back during the Susquehanna Roseland hearing, I introduced a FERC filing reflecting the 660MW transfer across the river to New York, that was what, a year and a half ago now?
So how is this Firm Transmission Withdrawal Rights for 685MW and 330 MW is news? The NJ BPU was NOT in the dark about this…
Now where’s that other 670MW… Exhibit 96… it’s in here somewhere… here’s a post from November, 2009:
How far down does electrical demand have to go…
Here’s yesterday’s piece from the New Jersey Spotlight:
Federal Agency OK’s Power Transfer from New Jersey to New York
Deer, moose v. transmission lines
July 1st, 2011
Here’s the recent “eagle drops fawn on transmission line” incident:
Close, but not quite a moose:
Xcel had 9,083 peak in June?
June 29th, 2011

(Yes, that’s Summer grrrrrrrrrrl.)
Remember how hot it was back a couple of weeks ago? Xcel’s Tim Carlsgaard was again bragging about Xcel’s peak:
9,083 MW
There’s plenty of time this summer to ramp it up higher, but so far, 9,083.
Here’s Xcel’s peak demand for the last decade, taken from their 10-Ks filed with the SEC:
Carlsgaard’s number came from an informal calculation or two, interruptible service was part of it, and I think it was deducted, but you never can be sure with a PR shill!!! Anyway, 9,083MW is nothing to write home about. If you remember, Capx 2020 was based on a 2.4% increase ANNUALLY. If we’d done that, starting from 2005, we’d be at:
10,620 MW
So we’re down about 1,600MW from their projections, and from what CapX was based on…
Their projections of a 2.4% increase annually add up quickly:
2005 – 9,212
2006 – 9,433
2007 – 9,659
2008 – 9,891
2009 – 10,128
2010 – 10,371
2011 – 10,620
In 2006 they jumped ahead of projections by a couple of years, but since then have dropped further and further behind, now with a peak trailing behind the peak of 2005…
So one way of looking at it is that they’ve pushed the “need” for additional power out for years.
Another way of looking at it is that they’re about three 500MW coal plants shy of what they projected.
Another way of looking at it is that they 1,600MW short is about Prairie Island’s and Monticello’s three nuclear reactors short.
Another way if looking at it is that it’s 1,00MW of cheap generation for wholesale and there’s plenty of room on 2,050-2,211 MVA (4,100-4,422 MVA double circuited) CapX 2020 transmission to ship that over to points east… (see MCEA, ME3, Waltons Schedin IR3)
So Tim, do tell, where am I off here??? p.s. Always check my math, I’m an attorney, not a vet, because my brain has grey sponge in the math department.
ILSR’s Farrell on Fed Transmission Scam
June 29th, 2011
ILSR’s John Farrell is halfway there – he recognizes the federal part of the transmission equation, but the state part is missing, for example, Minnesota’s special eminent domain exemptions for “Public Service Corporations” (particularly where the transmission is for private profit, NOT public service), rate recovery for “Construction Work in Progress” and state regulators refusal to examine the interstate nature of transmission proposals. And the third part of that unholy trinity — in the Midwest, bulk power transmission would not be being built but for the Settlement Agreement – ME3(Fresh Energy), Izaak Walton League (and Walton’s program Wind on the Wires), Minnesota Center for Environmental Advocacy, and North American Water Office. This glut of transmission is their legacy. It takes all three to build transmission.
From Grist, today:
Feds running a high-voltage gravy train for power transmission
by John Farrell
28 Jun 2011 6:00 AM
Even as distributed generation shows economical and political advantages over centralized renewable energy, the Federal Energy Regulatory Commission (FERC) is running a high voltage gravy train in support of expanded transmission. FERC’s lavish program is expanding large transmission infrastructure at the expense of ratepayers instead of looking at more economical alternatives.Since 2007, FERC has had 45 requests for bonus incentives for transmission development — authorized under the 2005 Energy Policy Act — and has provided all or most of the requested incentives in more than 80 percent of the cases. With the bonuses, the average return on equity for utilities for their new transmission investments is nearly 13 percent. This high rate of return is a full 2.5 percentage points higher than the median utility return on equity [PDF], a value considered just and reasonable by state public service commissions in ordinary times. However, these rewards came during a time when unemployment doubled, the stock market tumbled, and most corporations were lucky to have any profit.The ratepayer impact of these bonuses is significant. In a November 2010 criticism of FERC transmission awards, Commissioner John Norris noted that the 2 percent bonus FERC provided to the PATH high-voltage project on the Eastern seaboard would “cost [Maryland] ratepayers in PJM at least $18 million per year.” The bonus payments were also given in concert with other incentives that reduced risk, including rate recovery during construction and guarantee of payment if the facilities were abandoned for reasons outside utility control.





