PowerOn Midwest Direct Testimony
August 14th, 2026
Downloading all, here ya go, Tranche 2.1 moving forward:
Applicants – PowerOn Midwest
MISO
Commerce-DER
LIUNA
Lots of PowerOn Midwest open houses
August 14th, 2026
Let’s see, PowerOn Midwest, MISO’s Tranche 2.1 on parade. Albert Lea 10am, then Austin on Wednesday (gotta admit, I fell asleep when charging my phone!); then Zumbrota at 10am, back home then off to Kasson yesterday evening. ZZZZZZZZZZZZZZZ. Handed out at close to 400 of these. Lots of time and not much done other than yack and yack. Lots of good questions, lots of the same questions, and lots of pointed “If you’re seriously concerned, GET ON eDockets!! NO EXCUSES!” That was the message of the day… days.
The crowds were… shall I say these were highly attended? 160+ in Albert Lea, 150+ in Austin, ? in Zumbrota, and 100+ in Kasson (weird place, in the middle of the County Fairgrounds).
I did learn something at the Albert Lea open house — I’ve not been tracking routing much as it’s Certificate of Need that’s ongoing now. What I learned is that is that there’s a proposed route, though in the narrower purple line, that is right below Myre-Big Island State Park! THIS IS MY PARK!!! We camp-hosted there, and spent so much time at Big Island, meetings with Doreen Hansen and Association of Freeborn County Landowners, hearings at the college:
You’d think they’d avoid a State Park? It’s also going through the Freeborn Wind project area, the landowners there getting hit again.
And speaking of viewsheds, here’s the poop… The blob of land where the “38” is, that’s Big Island, the campground is up against the water. I went to the park after the open house, killing time on the way to Austin…
From Google, here’s the Island, showing the campground.
Sites 1-5 are on that upper loop, along the road next to the lake. the furthest site, at that crossover is site, the camp host site. Sites 1-4 have the best internet on the island, have officed there many times, particularly during the Freeborn Wind fiasco (WS-17-410).
And at Site 1 way back when, before meeting Doreen Hansen, Association of Freeborn County Landowners:
Here’s what I found at Big Island. Standing at the lake by the bench across from Site 1 yesterday, though I had my directions off, and due south is a bit to the left. There was a loon just off the shore! And those lattice towers would be how far above that treeline? Impact on State Park viewshed, anyone?
Also, look at those protected areas south of the lake — I can’t imagine they’d really route it through this area, but knowing how this works, I’ll be taking a close look at the other route on the north side of Albert Lea, and on the lookout on other route issues proposed for this long route.
We’ll see how this goes. It’s not really time to look at routing, I’ve been working on rustling up participation in this Certificate of Need docket, and routing, that’s not a job for North Route Group and NO765MN, but it sure got my attention!!
Order &Draft Permit for Pine Island data center xmsn
August 14th, 2026
Here it is. Stay tuned for date(s) of public hearings — need to make solid comments, and lots of them!
In order to make a coherent comment, it’s important to read the application AND the draft permit just released. Plan on having NOT MUCH time, so be concise, AND if you have reports, studies, credible newspaper articles, hand them in as exhibits, quickly explaining what they are.
We’re ON it = time to get to work!
DOJ “monitoring” voting in Minnesota!
August 13th, 2026
Really… here’s the link. There’s also a youtube of 2 of them being confronted by a head election judge, can’t find it now:
www.justice.gov/opa/pr/justice-department-conduct-election-monitoring-minnesota-primary-election
Minnesota Secretary of State Steve Simon addresses DOJ monitoring of polling sites
Minnesota officials advise voters as Justice Department sends seven teams to monitor primary
Hermantown Data Ctr AUAR Redo
August 11th, 2026
Today published in the EQB Monitor is news that the redone AUAR for the Hermantown Data Center has been released:
EQB Hermantown Data Center page
And the AUAR? It’s here:
Updated Hermantown Industrial AUAR project link provided by RGU
There’s a meeting scheduled, in person and virtual:
| Tuesday, September 8, 2026 | 6:30 p.m. | 5105 Maple Grove Road Hermantown, MN 55811 |
Virtual link: https://hermantownmn.com/community/calendar/
The EQB Monitor blurb says “End of objection period (for state agencies and Met Council only): August 25, 2026″
Is that reasonable? You might want to let the “Responsible Governmental Unit” know what you think of that limitation.
Responsible governmental unit and contact: City of Hermantown, Eric Johnson, 218-729-3600
What would I do? Oh, I wouldn’t let that stop me — I’d not look for permission. I’d send in comments anyway, to “City of Hermantown, Eric Johnson” and copy the EQB env.review@state.mn.us for their files, oh, and MCEA’s Abigail Hencheck and Jay Eidsness because they signed the Hermantown Complaint: ahencheck@mncenter.org and jeidsness@mncenter.org