Yesterday, we filed Motions for Reconsideration of the Minnesota Public Utilities Commission Order regarding the AWA Goodhue (a/k/a T. Boone Pickens) Wind Project:
What’s really weird about it is that not only is there a PUC Order where the ALJ’s Findings of Fact, Conclusions of Law and Recommendation is adopted, with a few amendments and deletions, but there’s an “EFP” Order too, with the Energy Facilities Permitting writing their own separate overlapping “Findings.” Ummmmm…. who the hell is EFP to be writing Findings? When do intervenors get a chance to comment on them??? This is a very bizarre morphing that is not addressed anywhere in the rules. I can see EFP briefing papers, but Findings… and Findings that aren’t even cited? WTF?
Anyway, here’s what’s been filed, starting with my client, Goodhue Wind Truth:
GWT – Reconsideration – Site Permit
There are a lot of others, will post later, this is painfully slow…