A modest success — the FULL Public Utilities Commission will take up the Environmental Review Scoping Decision issued June 9, 2026, a Consent Order. The FULL Commission is taking it up on July 9!

An Objection must be filed within 10 days for full Commission review:

Staff Briefing Papers will come out some time before the meeting, we’ll see how quickly they’ll dismiss our concerns.

Here’s the Objection filed by North Route Group and NO765MN, under Minn. State. 216A.03, Subd. 8(b) and Minn. R. 7849.1400 with many substantive specifics:

Again, not a big deal, but I hope it will get them to discuss on the record and vote on adequacy of this Scoping Decision for the first 765 kV transmission line to go through Minnesota.