Comment on Cannon Falls Data Center AUAR
June 26th, 2025
Here ’tis, just filed, sent to Cannon Falls City Administrator, and copied Randolph Township, the EQB Environmental Review Team, and the Environmental Quality Board:
Tract Data Center in Cannon Falls
June 24th, 2025
Yes, there it is. This is the site plan proposed by Tract for its data center in Cannon Falls. I’ve just come from a file review, and am posting the docs little by little here.
The Alternative Urban Areawide Review (AUAR) is based on a ruse that the data center is “one option” for the site, but the site plans, schedule, and other documentation show that it’s a data center and nothing else.
Here are photos of a bunch of 11×17 docs that didn’t fit in the scanner:
And here are the larger plans, also photos as they are LARGE:
And there’s more to load…
Archer Data Centers Faribault Campus
June 23rd, 2025
Too late I learn about this — deadline for comments was June 20. Note this is an Environmental Assessment Worksheet, not an Alternative Urban Area Review (AUAR).
The official Minnesota Environmental Quality Board notice and published document can be found here. The City of Faribault also posted the document here.
https://www.ci.faribault.mn.us/DocumentCenter/View/11706/Archer-Datacenters-Faribault-Site—Draft-EAW—05-08-2025
This is billed as a 120MW project on 84.3 acres.
Looks like a lot of roofs for solar!
THESE THINGS ARE ALWAYS TOO BIG TO UPLOAD OR PASS AROUND VIA EMAIL.
ALJ Recommendation- PINGP Dry Casks
June 23rd, 2025
Here it is, the ALJ Recommendation about additional casks for nuclear waste at Prairie Island Nuclear Generating Plant:
Short version – Xcel Energy gets what they want:








