Today is the Xcel Energy “stakeholder” meeting for “stakeholders” at the PUC.  For the IRP docket, CLICK HERE and search for PUC Docket 15-21.

20150210_093508

Here are their scenarios:

20150210_103218[1]

Regulatory process and timeline.  January 2 filing, 900 pages, and today between that filing and March 16, 2015 filing.  That March 16 filing will be next piece and will complete filing of plan to Commission, then forward with Information Requests and stakeholder meetings, and then PUC decision within next year or so, depending on what’s happening in stakeholder process.  Three components:

1) CAPCON Order (capacity acquisition process)

  • Aurora Solar
  • Calpine combine cycle expension
  • Black Dog 6 Natural gas

2) Increase small solar forecast

3) Sherco Retirement Scenario

  • Sherco 1 & 2 retirement in 2020
  • Sherco 1 retirement in 2020, Sherco 2 retirement in 2023 (based on capacity acquisition process, retirement, etc. scheduling)

For questions about the IRP, contact Jim Alders  james.r.alders@xcelenergy.com

This is on the heels of last night’s meeting of “Citizens League Electric Energy” group.  From the Citizens League site:

And notes from committee meetings:

The January 26 meeting isn’t posted, but I scanned them in and will post later.  They had a charge of the “committee” in the Phase 2 Report to support Xcel Energy’s “e21 Initiative” below:

Charge-to-Electrical-Energy-Phase-3

That charge contained this specific direction:

CitizenLeagueChargeReally, this is what it says:

… the Citizens League Study Committee will be asked to draft both a statement and legislation to direct the Public Utilities [Commission] to convene this public dialogue with the support of external stakeholder efforts.

So we shouldn’t have been surprised…  That charge was pretty much fulfilled and presented to the group last night, BUT the good news is that in addition to Alan and my objections to that endorsement of the “e21 Initiative,” there were several long-time Citizens League members who objected to the way that this was done and the endorsement of the e21 Initiative.  (I’ll insert the draft when I get back)

Short version, the Draft was soundly rejected.  WHEW!

And for those concerned about this e21 Initiative, Intervene!!! Yes, Citizen’s League, that’s something YOU can do!

Just filed Petition for Intervention in Xcel’s e21 Docket

February 4th, 2015

e21

Yes, I’ve filed this under “Energy” “Disaster” because it’s a train wreck of a proposal, and I cannot believe people would buy into this… or sell out into this.  What, you say?  e21!

102115_e21_Initiative_Phase_I_Report_2014

In December, Xcel filed this, and I swear, this was the heading:

REQUEST FOR PLANNING MEETING AND DIALOGUE
ROADMAP FOR SUPPORTING THE e21 INITIATIVE

“Roadmap for SUPPORTING?”  Really…

So what is it?  It’s a lot of whining about how hard it is to be a utility and that things are changing.  Ummmmm… yeah.  As if Xcel didn’t know that?

It feels to me like it’s another whack at “restructuring,” a/k/a deregulation, and a “we’re too big to fail” argument.  And as before with “restructuring,” everyone’s getting in line, jumping on the bandwagon.

Listen to this recommendation:

(J)1. Encourage the use of, and give additional weight to, settlement agreements among parties, as long as the Commission determines that the agreements are in the public interest.

Really…

And now that we’ve permitted and built all this excess transmission capacity, they’re whining about under-utilization… can you believe it?  Check this recommendation:

(N) Identify and develop opportunities to reduce customer costs by improving overall grid efficiency.  In Minnesota, the total electric system utilization is approximately 55 percent (average demand divided by peak demand), thus providing an opportunity to reduce system costs by better utilizing existing system assets (e.g., generation, wires, etc.).

This sounds like the best opening to get into the CapX and MVP dockets and get them revoked.  Give me a break…

So I just filed this, we’re gonna do what we can:

Legalectric and Muller – Petition for Intervention

Why file for intervention?  Well, this thing is all about stakeholders, and argues that, hey, look, all the stakeholders agree so just do it.  Ummmm… right… and just who are the stakeholders?  Those who have made those agreements with them in the past that got us right where we are today, DOH! What a fine mess you’ve gotten us into… let’s not do it yet again!

finemess

 

Yes, electrical infrastructure, substation, transmission — that’s Michelle Robinson’s work — check it out:

Land_invite_MR

PublicUtilitiesCommission

Today we were before the Minnesota Public Utilities Commission, moi and my clients, Residents of Getty and Raymond Townships, asking that the Commission reconsider its permit amendment for the Black Oak and Getty wind projects:

Residents of Getty and Raymond Twps_Motion for Reconsideration

Given Staff’s position, well:

Reconsideration_Staff Briefing Papers

So yeah, that was a unanimous refusal to reconsider, and then a unanimous vote to deny.  But there was a ray of sunshine this morning!  Chair Heydinger did indeed recuse herself.

Imagine living on the farm right there in the middle of this in Section 18?  And it’s not “just” people who live there, but bald eagles too.  We’ll see what US Fish & Wildlife has had to say, my FOIA request to them is slowly-at-a-snail’s-pace moving forward:

BlackOakLayout

GettyLayout

DOE_Logo

Interesting letter arrived today:

GNTL_Invitation to Consult

It says that “DOE is contacting you because you submitted comment(s) related to cultural resources during the open NEPA public scoping period for the proposed GNTL project.”

RRANT Scoping Comment

???

So what does that mean? What’s involved?  Sending info to them?  Sending more Comments?  Attending meetings? A free trip to D.C?  A self-funded trip to International Falls in February?

“Consultation” is a term of art in federal permitting, and is required with all Indian tribes, of which there are several in the area of the project.  In this case, they also specify “the State Historic Preservation Officer” and “the Advisory Council on Historic Preservation,” and also “certain individuals and organizations…”

Here’s the  National Historic Preservation Act of 1966 (NHPA)

Working with Section 106

Energy Development, Transmission and Historic Preservation

Are “historical resources” all that they’re concerned about, is there a special category for “cultural resources?”  Or are different people invited to consult on different categories?

And if this is something I want to do, and it is, I have to “include information about your demonstrated legal or economic relation to the undertaking” … (odd word, that)… ” or to properties potentially affected by the proposed GNTL project…”

UntitledGuess I’d better figure out what I said in those comments first!