PUC & DoC’s Response to North Dakota, et al.’s FERC Complaint
September 9th, 2025
The Minnesota Public Utilities Commission has filed a Comment in the North Dakota, et al. v. MISO docket, FERC Docket EL25-109-000.
To look at filings in docket, go HERE: https://elibrary.ferc.gov/eLibrary/search and at the “Enter Docket Number” box, fill it in: EL-25-109 Note that everyone in the world has intervened!!!
Here’s the original filing from the North Dakota, Montana, Arkansas, Mississippi, and Louisiana Commissions:
Here’s the Minnesota Public Utilities Commission and Department of Commerce’s pretty sparse Comments:
And the Briefing Papers for this Comment (it was approved unanimously):
Data Centers should pay more for electricity
September 9th, 2025
DOH! Data Centers should pay more for electricity!
There’s quite a few data centers proposed for Minnesota, specifically:
- Rosemount – 4 active projects: Dakota East, Rich Valley East, Rosemount Industrial, and U-More
- Farmington – Farmington West and Farmington Tech Park
- Becker – Xcel – WITHDRAWN
- Chaska – no documentation yet
- Cannon Falls Industrial (the one I’m most familiar with)
- North Mankato – subject of MCEA lawsuit
- Hampton Industrial – Tech Park
- Lakeville Industrial – also subject of MCEA lawsuit
- Apple Valley – Tech Campus? Rockport Data Center?
- Eagan – thompson Reuters – ?? add to existing small one?
- Northfield – old and ? inactive
- Pine Island – Skyway
- Hermantown
- Faribault – Archer Data Center – Not AUAR – EAW?
- Monticello Tech/Monticello Industrial Park
- Monticello – Scannell Technology Park
- Others I’m missing? Let me know in comments!!
What we’re hearing, with little substantive info, is that data centers will use a LOT of electricity. Folks are going on and on with zero information about how much they’ll use, how that will affect rates, and the trend of electricity demand, which is flat. WE NEED SPECIFICS FOR EACH PROJECT TO CONSIDER IMPACTS.
For example, here’s Xcel’s peak demand over the last 25 years, taken from their SEC 10-K filings (details HERE):
No specific info on electric use for the projects above that I know of. I have found info on tract website of various projects and the MW they use:
tract data centers showing acreage and MW
Cannon Falls, for example, a tract project, is 280 or so acres, and in that acreage range, they show from 120MW to 500MW. That’s a lot of wiggle room. What about those data centers above that have been proposed? A list of acreage and expected MW usage sure would help…
From deregulated Delaware, the Public Service Commission has taken notice:
Data centers will pay higher rate for electricity, state commission decides
by Olivia Marble September 8, 2025

Delaware energy regulators voted to stop energy-hungry data centers from connecting to the electric grid until a new electricity rate for them is calculated.
Why Should Delaware Care?
Delawareans have already seen energy prices rise, partially because of the growing electricity demands from large-scale data centers in the region. A higher electricity rate for data centers could limit the amount of energy data centers pull from the grid in the future.
Data centers in Delaware will soon have to pay more for electricity than other businesses as a result of steps that state regulators say will slow rising energy prices.
The Delaware Public Service Commission, the state body charged with regulating utility services, voted Wednesday to stop “large-load consumers,” such as energy-hungry data centers, from connecting to the electric grid until the commission can create a new “tariff,” or electricity rate, for them.
Delmarva Power is now in charge of figuring out what that new rate will be, and the Public Service Commission will decide whether to approve it.
This decision follows turbulence in Delaware’s energy markets that emerged last winter with spiking residential electricity bills. At the time, Delmarva Power attributed the bill increases to surges in electricity demand.
Six months later, Starwood Digital Ventures, a developer backed by private-equity, submitted plans to New Castle County to build a data center near Delaware City that would consume an additional 1.2 gigawatts per hour from the grid – or enough energy to power nearly 1 million homes, according to estimates from experts in the field.

While smaller data centers already exist in Delaware, Starwood’s project is the latest in an ongoing boom for the industry. It is propelled by tech companies that need bigger, more energy-intensive data centers to power new artificial intelligence applications, like ChatGPT, Google Gemini and Microsoft Copilot.
Is a higher rate needed?
The Delaware City data center would purchase power from utilities on a PJM regional electric grid that has already experienced price increases. Those were due, in part, to data center construction across multiple states, including Virginia, Maryland, Pennsylvania and Ohio.
Beyond demand, electricity rates also include the price of the infrastructure needed to bring electricity to the consumer, like power lines and transformers.
The cost of that infrastructure is typically spread among all consumers, because in the past, those infrastructure upgrades benefitted everyone, said Eliza Martin, legal fellow at Harvard University’s Electricity Law Initiative, an independent policy organization based at Harvard Law School.
But now, utility companies may need to pay for infrastructure that is only used to power hyperscale data centers, Martin said.
Martin co-authored a paper that revealed different ways that utility companies “are forcing ratepayers to fund discounted rates for data centers.”
Harvard-ELI-Extracting-Profits-from-the-Public
At Wednesday’s meeting, Delaware Public Service Commission Attorney Kate Workman cited a Synapse Energy Economics study, commissioned by the Sierra Club, that found that data centers will cause residential bills to increase by 10% in the near term and 4% in the long term.
“[That] is a huge increase when consumers are already struggling to afford the increased cost of power,” Workman said.
Delmarva to decide new rate
Different electricity users already pay different prices for electricity. In Delaware, residential customers pay 18.15 cents per kilowatt hour, commercial customers pay 12.45 cents and industrial customers pay 8.82 cents.
Typically, local utility companies like Delmarva negotiate rates with the different “rate classes,” or types of consumers, and the Public Service Commission approves or denies those rates.
But at Wednesday’s meeting, Workman and the state’s Division of the Public Advocate, which negotiates power rates on behalf of residential and small commercial consumers, argued that this new rate should be deliberated in public workshops that the Public Service Commission staff would conduct.
“This type of tariff is so new, so controversial and so multifaceted that we want to give the public the ability to give us their concerns so that we can possibly address them,” Workman said.
Delmarva’s attorney, Brian Jordan, argued that Delmarva has the expertise to determine the rate on their own, and anyone from the public could oppose it if they felt it was unfair.
The Public Service Commission did not vote at its Wednesday meeting on how potential workshops would be conducted. Its next meeting will be held on Oct. 15 at 1 p.m. The public can comment in person and virtually.
++++++++++++++++++++++++++++++++++++++++
Two obvious issues:
- Should data centers that are expected to use lots of electricity pay higher rates? Ja, you betcha!! Higher rates for data centers SHOULD be ordered by our Public Utilities Commission! DOH! The practice of charging residential customers the highest rate, then commercial with lower rates, and industrial with even lower rates is indefensible in a time when we’re supposedly working to decrease electric use.
- How much electricity will these data centers use? Who knows??!!?? Each initial inquiry, each foray into permitting, should require disclosure of expected MW needed for that project.
- Make that three issues. From Xcel’s flat peak demand, you can see we’re doing a good job, making progress with load shifting, efficiency, to the point that Xcel’s 2024 peak demand of 8,822 MW is down roughly 1,000 MW from Xcel’s 2006 peak of 9,859 MW! In its 2022 SEC 10-K, Xcel disclosed it was putting 1,500MW of EXCESS CAPACITY on the market!
1,500 MW is about 400 MW more than the generating capacity of the TWO nuclear reactors at the Prairie Island plant. And that’s just Xcel. How many data centers would operate on that 1,500MW existing capacity? And do other Minnesota utilities have excess capacity? Which and how much?
Considering Xcel’s peak demand, and our little knowledge of the “needs” of these data centers, who knows what the impact could be!
Let’s get the info we need!!
3rd BIG Transmission Line Comment Notice!
September 2nd, 2025
Great, just great… Received Notice of Comment Period for the 3rd of the BIG TEN TRANSMISSION LINES scheduled to spread a web, ANOTHER web, of transmission across Minnesota. This one is MISO Tranche 2 #20, PUC Docket CN-25-109 (technically E015,ET2, E017/CN-25-109), Maple River to Cuyuna:
Notice of Comment Period is down at the bottom — short version is:
Here’s the Exemption Request:
And the Notice Plan – and NOTICE that the Comment Period is only about the “Exemption Request” and not about the Notice Plan?!?!?!
Notice of Comment Period — it’s only for the Exemption Request, but do comment on the Notice Plan too. Notice is crucial because if people don’t get notice, how will they know (of course that’s the idea, eh?). The Applicant sets a Notice Comment schedule, and only lists a U.S. Mail address. Naaah, just send in with the Exemption comment.
Rate case, and we’ll pay for transmission
August 31st, 2025
Xcel’s latest rate case, raising rates AGAIN. PUC Dockets 24-320 and 24-321.
What are we paying for? Focus on what it IS, and not what it may well be next time around! Cutting future renewable develop and a big push for energy for AI is NOT happening yet, it is not affecting rates yet.
A large part of it:
- We get to pay $1.14 billion, or more, for Xcel’s private first-of-its-kind radial line to “preserve its valuable interconnection rights” at its Sherco substation:
- We get to pay for MISO Tranche 1 transmission:
Gee, thanks, Xcel Energy! And MISO too!
2nd MISO Tranche 2 project
August 31st, 2025
Next up, MISO Tranche 2’s #20, Public Utilities Commission Docket CN-25-116, adding a second circuit between “Bison” and Alexandria. The PUC is seeking comments on their Notice Plan, as with the previous MISO #21, CN-25-111, Iron Range – Arrowhead docket. (catch up on MISO Tranche 2 HERE – 24 projects at $2.1 BILLION)
Here’s their Notice Plan — now’s the time to pick it apart. Because it’s “just” adding a double circuit to the CapX 2020 Fargo line, there’s not much to say:
And here’s the PUC’s full request for Comments:
And the short version:
I quickly slapped together No CapX 2020 Comments based on the ones I’d filed the day before on the first MISO Tranche 2 project, further below. Again, this is “just” adding a 2nd circuit, but the “need” question remains — why is this needed — justify it, it has to be more than MISO/MISO’s utility & transmission members want it. MISO’s “approval” does not mean it meets Minnesota’s need criteria in Minn. Stat. 216B.243:
And for that other project, MISO’s #21, PUC Docket CN-25-111, the only Comments filed last week — ONLY THREE COMMENTS. This is a new greenfield project — what does it take to wake people up?
Expect to OD on MISO over the next few years:
- CN-25-109 MISO 20 – Maple River – Cuyuna 345 kV
- CN-25-111 MISO 21 – Iron Range – Arrowhead 345 kV
- TL-25-112 ” “
- CN-25-116 MISO 19 – Bison-Alexandria 345kv
- CN-25-117 MISO 22 – Brookings – Lakefield 765 kV
- CN-25-118 MISO 23 – Lakefield – East Adair 765 kV
- CN-25-119 MISO 24 – Lakefield-Pleasant Valley – N Roch 765 kV
- CN-25-120 MISO 25 – Pleasant Valley – N Roch – Hampton 345 kV
- CN-25-121 MISO 26 – N Roch – Columbia 765 kV Dairyland
- CN-25-122 ” ” Xcel