Yesterday’s MariBell Open House
November 19th, 2025
It was PACKED, nearly full parking lot and room was crowded. Surprising in a rural area and a town of “2,847.”
Worth the trip down to Caledonia, Albert Collins on my tape loop the whole way (though also my father-in-law’s dance band version, that’s where I learned it). Worth it because now the notion of “MariBell” v. “Gopher to Badger” is now clear, and the 765kV line too.
“MariBell” is “only” the double circuited 765kV and 161kV (NOT 2 765kVs), the part that starts when the two lines are joined at Marion, MN, and down across the Mississippi into Wisconsin. The “Gopher to Badger” starts at the North Rochester substation down to Marion — does it then also cover the MariBell? Not clear.
The noteworthy point — Dairyland wants to use that existing 161kV line, and I guess this open house was mostly for those landowners. The RoW will need to be expanded to 250 feet, and they’re trying, wanting, to work with those landowners to get it done.
Supposedly they’re still trying to figure out how to get out of that North Rochester substation down to Marion — it’s getting crowded with that Pine Island data center 345kV line that’s proposed. Here’s that proposal – the yellow blob is the proposed substation expansion and the yellow line is the proposed 345kV line down into the cornfield. The green is the existing CapX line down to La Crosse and beyond.
Back to MariBell: Here are the handouts. Cookies were had, but NO COFFEE! Also, no announcement on the Public Utilities Commission’s eDockets, and no promises — I’ll do my best to make sure there’s an eDocket post when future open houses come up.
And how’s this for a non-answer?
I’d edit this to: “YES! Ratepayers will pay for this project, apportion amongst MISO ratepayers apportioned by the arcane MISO “Schedule 25.” Maybe it’s no longer Schedule 25, guess I’d better check.
In the Fillmore County Journal:
Houston County Commissioners Hear Initial Presentation on MariBell 765/161 kV Transmission Project
At the November 18 regular meeting of the Houston County Board of Commissioners, representatives of the MariBell 765/161 kV Transmission Project appeared before the commissioners for the first time to share information about the project with the board. The project is a partnership between Dairyland Power Cooperative and GridLiance.
Chairman Eric Johnson called the meeting to order at 9 a.m. Commissioners Cindy Wright, Robert Schuldt, and Greg Myhre were also present. Commissioner Kurt Zehnder was absent.
The agenda was unanimously approved.
The minutes from the November 4 meeting, and the minutes from the November 12 workgroup session were also approved.
Dairyland Power Cooperative Manager, Regional Transmission Projects, Clay DeWitt; GridLiance Heartland Sr. Director Development Jessica Hewitt; and Gridliance Heartland Project Director Josh Daubenspeck appeared before the commissioners to present an introduction of the project and answer questions.
DeWitt explained, “Today we’re going to talk about who the partners are, and we’ll have a full overview of the project, starting with the need, going through the actual project itself, the high level overview, the schedule, the benefits of the projects, routing considerations, and then right away easement process from a high level standpoint.”
Midcontinent Independent System Operator (MISO) “is the one who oversees and operates the grid in this particular area of the central United States,” explained Hewitt. “They are the ones that determine the project needs, and they, also, are responsible for this overall system planning.”
Commissioner Johnson said, “MISO is who we need to talk with.”
During and after the presentation, the representatives answered a range of questions from the commissioners and members of the public. The audience emphasized that communication with property owners must be improved in the future.
The representatives announced that they would be holding an open house in Caledonia on Tuesday afternoon from 4-6 p.m. at the community center. There will not be a formal presentation; instead, it is an opportunity to ask questions. More open houses will be held throughout the multi-year process. Postcards were sent to all property owners who will be affected, informing them of the open houses.
At 9:30 a.m. the commissioners closed the regular meeting and opened the public hearing to gather input regarding granting a six-year property tax abatement to assist in the construction of a cold storage facility at Sno-Pac Foods. The property is identified a Parcel No. 211163000. The commissioners closed the public hearing at 9:34 a.m. and reopened the regular meeting.
The board then unanimously approved the property tax abatement for Sno-Pac Foods, Inc. The anticipated completion date is July 2026.
The consent agenda was approved. Kelly Zielinski was hired as a Public Health and Human Services collections officer, and James Lyden was hired as a 67-day temporary/casual drop site supervisor.
In other business, the board:
- Adopted Resolution No. 25-39 and No. 25-40 in support of city of Houston and Caledonia’s Local Road Improvement Program (LRIP) applications.
- Accepted the recommendation from Commissioners Wright and Johnson and Parker to adopt the Houston County Policies and Procedures Manual.
- Approved a three-year contract with UKG and the Minnesota Counties Computer (MCCC) Cooperative for Human Resources, payroll, and workforce management software. One-time cost to launch the software is $17,655 and the yearly subscription fee is $43,065. The subscription fee for the current software program is $9,000.
- Discussed the county’s reorganizational structure and authorized Human Resources Officer Brent Parker to write and initiate a Request for Proposal (RFP) for external/economic development services for 2026.
- Approved the 2026 board meeting schedule as presented by Board Clerk/EDA Director Allison Wagner.
- Approved paying the bills totaling $683,018.84.
I need to write about Norway!
November 19th, 2025
Magestrate Judge Fitzpatrick orders release of Comey Grand Jury records
November 17th, 2025
It’s about time “Prosecutor” Lindsey Halligan had a major FAFO moment. And here it is, hot off the press of Magistrate Judge William Fitzpatrick:
There are ELEVEN specific Findings leading to the order to release the grand jury files. As noted in the grand finale:
And FYI, the grand jury records are NOT being released to the public, but instead released to the defense under protective order — which is not to say that these records will not be released in the future.
Was the DoJ that desperate to get an indictment, and that desperate to put in a “prosecutor” to do the dirty work? Seems so…
Transmission Open House TODAY, tomorrow, and Thursday!
November 17th, 2025
Today is the first of three “Open House” gatherings for the “MariBell” transmission project.
Caledonia?
From the PUC Comment Notice:
This MariBell Transmission Project is a 765kV DOUBLE CIRCUIT project, larger than anything in Minnesota. EDIT after 11/18 open house: BUT the double circuit is a 765kV (5,300 MVA) and the existing 161kV line. they want to follow the 161kV route. THIS is a good example of why you don’t want that 161kV getting its nose under your property’s tent!
We need this WHY?
And don’t worry, this isn’t happening in isolation, as you can see from the MISO map below. TODAY is the last day of the Comment period for the “Power on Midwest” line’s Requests for Exemption (from application requirements) and Notice Plan (how will folks find out about this):
Back to Maribell… (isn’t Maribell the name of some cow?) The MariBell transmission Project is MISO #26 of its “Tranche 2” mega-portfolio of transmission lines in the Midwest:
So far NINE of these projects, MISO #19-26, have Certificate of Need dockets (CN-25-109, 111 & 112, 116-122 — note #CN-25-117-120 have been consolidated under CN-25-117). with Notice of their intent to file applications. “MariBell” is Public Utilities Commission docket CN-25-121 (for Dairyland Power Cooperative) and CN-25-122 for Xcel Energy. So far, no notice if they’ve been, or will be, consolidated.
To look up the PUC docket, go HERE to eDOCKETS, click on the eDockets button there, and you’ll get the search screen. Search for 25-121:
There’s an open comment period now, REPLY comments are due TODAY on the Exemption Requests and Notice Plan (and this map from the Notice Plan is much better):
… so check out the Maribell Transmission Project‘s Notice Plan Petition and Exemptions Request, then pull up the docket, see what others have written, and get replies to those comments in TODAY by 4:30.
Challenge of Xcel’s new Mississippi River crossing
November 15th, 2025
Filed this week in Ramsey County District Court, a Minnesota Environmental Rights Act challenge of Xcel’s “Minnesota Energy Connection” transmission line’s crossing of the Mississippi River, a 3.2 mile segment of its 185 radial transmission line The purpose of this transmission line is to allow Xcel to retain its “valuable transmission interconnection rights,” at an expense to ratepayers of $1.367 BILLION. Yes, that’s BILLION!
Before this transmission project had even been applied for, the Dept. of Natural Resources let Xcel know, in writing, that it did wanted Xcel to utilize existing transmission line crossings of the Mississippi for this project, that it should not use a new crossing. And not just this initial Comment, but followed by others too! Why use an existing crossing, why not use this new crossing that Xcel wanted? Well, there are so many reasons…
DNR Comments, July 10, 2023, prior to Application, included in Application Appendix E. Remember that first sentence? Here it is again in a later comment:
DNR Scoping Comments, February 2, 2024 (attached). And that first sentence? Once more with feeling:
DNR Comments, November 25, 2024.
These tan routes in Figure 11 were preferred by the DNR, in addition to the “Purple Route” and expressly NOT the Xcel preferred route, the BLUE LINE route on the map:
Rather than pay attention and site it properly, Xcel hid the DNR’s “STRONG preference” and with more than a little sleight of hand, in its “Response to Agency Comments,” on page 2:
The ALJ omitted it from “DNR Route Preference” citing Xcel, not the DNR (!), and this “MDNR Route Preference” appeared in the Recommendation as if it WERE the DNR’s preference, which it was not, and next it morphed into what was called a “DNR Proxy Route.”
The excuse for this “DNR Proxy Route,” also in the ALJ’s report, the “DNR Proxy Route” that omitted the DNR’s one “strong preference” is convoluted and does not account for the DNR STRONG preference of the Purple Route or Route Segment 246 of the Blue Route:
Citing Xcel and not the DNR. “… to allow for some comparison among MDNR’s route preferences…” Oh, give me a break…
Again, basing this “MDNR Route” on Xcel’s Response to Hearing Comments.
The so-called “Evidentiary Hearing” was a farce, a transcript of 10 pages shows that there was little discussed, and the DNR was not called in to testify!
The “DNR Proxy Route” carried through to Staff Briefing Papers and to the Public Utilities Commission’s ultimate Order. Here’s the story from that Order:
“To enable a like-for-like comparison of route alternatives for which a route could be feasibly issued, Xcel developed a DNR Proxy Route that incorporated the most reasonable route segments in regions where the DNR supported more than one route segment.” Hmmmm, no mention of the DNR’s support of more than one segment crossing the Mississippi — the Purple Route and Route Segment 246 of the Blue Route. How did they get by with this omission?
The last line, “G” of that chart includes the Mississippi River Crossing, and it does NOT include the DNR’s preference of the “Purple Route” or Route Segment 246 of the Blue Route, bot utilizing existing Mississippi River crossings.
Once more with feeling:
In this map above, note how the Route Segment 246, proposed to utilize existing transmission for the Mississippi River crossing and route, was inexplicably routed not on the existing transmission side of County Road 8, proposed to utilize existing transmission corridor, but on the side of County Road 8 with NO transmission and with a large cluster of lakefront homes!
Xcel dismissed these two alternatives in Direct Testimony of Langan and attachments:
And then there’s the matter of burying the DNR Comments. The DNR is the agency charged with protection of our natural resources. Despite this charge, the Comments were hidden in the “Combined Hearing Exhibit” list filed by Xcel, and in the Dept. of Commerce’s long list of exhibits identified only by the eDockets filing number. The DNR Comments were not made an independent part of the record, and agency Comments were not identified in the “Combined Hearing Exhibit List.” Instead, these Comments were entered in a jumble of all the Comments received, with 15 links to batches of “Public Scoping Comments” labeled EERA-4. The DNR’s multiple Comments are buried within eDocket Document ID 20243-204514-03, pages 183-220 of the 227 page “Combined Hearing Exhibit List” filing. Is that nearly impossible to find? You betcha. To find them requires believing, knowing, that they’re there somewhere, opening each link and scrolling through thousands of pages of comments. Another DNR Comment is in the Xcel Application, Appendix E, which also requires knowing it’s there, and though the DNR Comment in Xcel’s Application is cited, once, it does not mention the opening sentence about the Mississippi River crossing stating its strong preference for an existing Mississippi River crossing. That initial sentence was repeated as the initial sentence of each comment regarding the Mississippi River crossing, yet omitted…
Note that when the ALJ in her Recommendation cites the DNR, she’s more often using “Xcel’s Response to Hearing Comments” which incorrectly characterizes, misstates, and omits the DNR’s strong preference of an existing Mississippi River crossing. If the ALJ cites actual DNR Comments, it’s from eDockets, and not a hearing exhibit from the “Combined Hearing Exhibits list, so not referring to a hearing exhibit! Hmmmmmmm…
This river crossing segment is a roughly 3.2 mile section of the 185 mile route, maybe 1.8% of this route? A similar portion of the cost? How hard can it be to route the transmission line with the existing transmission line along County Road 8, avoid all those lakeshore homes they’re so concerned about, and use an existing crossing of the Mississippi River?
We shall see… we’re asking Xcel to stop land acquisition activities on this small section, stop construction prep, stop final engineering, etc., as this winds it way through Ramsey County Court. Yes, we shall see…
p.s. look at this map, look at the pink transmission line alongside of County Road 8. In the Draft and Final EIS, that transmission line disappears as it heads to, or from, the northwest, it disappears to the right of the river crossing. Yes, it disappears! It’s hard to see here — I need to make a HUGE copy of this map!































