Some articles from the PoM Public Hearings
November 14th, 2026
It was a long week, 258 miles between all the locations, plus the to and fro miles. There’s ONE hearing left, in Kasson on Monday, plus a virtual hearing that evening:
There was some good media coverage:
Pipestone: Objections heard during transmission line public hearing
Slayton: PUBLIC HEARING REGARDING POWERON MIDWEST PROPOSED LINES HELD IN SLAYTON
Worthington: PowerOn Midwest scrutinized by public comments
Windom: (none?)
(And before hearings: Fairmont Sentinel: PowerOn Project getting its necessity tested)
And waiting for others to show up!
At several of the meetings a man was handing out a packet of info from Arthur Firstenberg — much of it may have been from Firstenberg’s “The Invisible Rainbow: A History of Electricity and Life.” His handout: