I’d say it’s more “regress” than progress… Anyway, Gopher to Badger? Shouldn’t it be “Prairie Dog to Badger,” as the 765 kV overlay section of Tranche 2.1 starts in South Dakota? And of course it goes beyond “Badger.”

Anyway, this “Supplemental Information” (202611-238460) was just filed, and it looks like a prelude to filing the route application:

They had to file simulations, ordered by the Commission in its Certificate of Need”completeness” determination, and here are a few — how decorative:

And these on Co. Rd. 5 south of Caledonia:

Looks like someone’s been driving across the field into the tree line.

This also Co. Rd. 5:

Why would I say it looks like a prelude to filing the route application? Simple, they’re using the route docket number, TL-26-156, the first Applicant filing in that docket.

Comments are closed.