MAPP is dead, dead, dead

August 8th, 2012

Just in today from PEPCO:

All,

I am writing to provide an update on PHI’s proposed Mid Atlantic Power Pathway (MAPP) project.

Today PJM issued the final results of its 2012 transmission analysis and due to factors such as lower load growth from the sluggish economy, the installation of new gas fired power plants, and the increase in demand response programs, no reliability violations were identified within the transmission planning window. As a result, the PJM Transmission Expansion Advisory Committee (TEAC) issued a recommendation that the MAPP project be canceled.  On August 24, 2012, the PJM Board of Managers will meet to make a final decision on the TEAC’s recommendation.

I would like to express my sincere appreciation for your interest and participation in the MAPP project over the past few years.

Thank you,

Mark Okonowicz
MAPP – Environmental Coordinator
Pepco Holdings, Inc.
P – 302-283-6115
C – 302-463-5438
mark.okonowicz@pepcoholdings.com

This is after their bogus claims, in 2008, of skyrocketing peak demand (utterly unsupported by fact) from a June 25, 2008 MAPP Presentation found on the DNREC site — this “forecast” is so outrageous, and cancellation is SO HILARIOUS in light of Todd Goodman’s objections to my chalenging demand:

demand

So let’s take a step back – what is MAPP?

mapptransmissionoverview

No, this isn’t about the Mid-Continent Area Power Pool… it’s the Mid-Atlantic Power Pathway (MAPP), and it is DEAD!

The Mid-Atlantic Power Pathway, a transmission line that was part of “Project Mountaineer,” a coal transmission web that was hatched at a 2005 FERC meeting.  MAPP was the NE part of line 4, below (Susquehanna-Roseland is the eastern part of line 1):

projectmountaineermap

Here’s the transcript of that meeting, too scary, but it’s important to read this:

FERC Transcript 5/13/05

They tried and tried and tried, against evidence, to ram all these projects through.  The did manage to get the first one through, the TrAIL (Trans-Allegheny Interstate Line) project, but PATH (Potomac-Appalachian Transmission Highline) is dead, Susquehanna-Roseland is permitted but not yet built…

Slowly but surely, PJM is admitting that transmission is not “needed” by any measure.  With MAPP, first they planned it as above, in the first map, and then they eliminated the part in Delaware from Indian River to Salem/Hope Creek nuclear plants:

mappnow

Despite this, Delaware’s DNREC issued permits for part of this project in Sussex County, Delaware!  Whatever for?  Why would they do this?  Aren’t they paying attention to things electrical?  DNREC should know this is not needed

Delmarva Power Receives Delaware Subaqueous Lands Permit

Delmarva Power & Light Company (DPL) has received the Subaqueous Lands Permit from the State of Delaware Department of Natural Resources and Environmental Control (DNREC) for the transmission line associated with the MAPP project in Sussex County, Delaware.  This permit grants DPL the ability to place temporary mats in the existing right of way to establish access and work areas over subaqueous lands to support construction activities.

Here is today’s good news — PJM’s latest review, just released, showing NO THERMAL VIOLATIONS — DUH:

August 9, 2012 Reliability Analysis Update

Here are two slides that say it all, the first focused on PATH but including MAPP, and the second, the “MAPP Project Analysis” results:

And the bottom line?  Another DUH, GOODBYE PATH AND GOODBYE MAPP:

Once again, we’re proven right.  How long have we been fighting all these transmission projects, how much time, effort and money showing it’s not needed, even when using INDUSTRY studies, documentation, forecasts.  All their claims of need are fabricated, reverse-engineering to get the result they want, billions of dollars of PRIVATE INTEREST, not PUBLIC interest, projects, built on the backs of landowners, with a FERC guaranteed 12+% rate of return for the owners/builders/developers.

The down side is the ratepayers are probably going to be hit with all these development costs because so many jurisdictions allow recovery for “CWP,” construction work in progress.  So we get screwed, but not as badly as if they had built the projects.

Like CapX 2020, this project was another of those personal projects.  MAPP was originally heading up through Delaware to the Salem/Hope Creek nuclear plants, and the Delaware part would have gone near us in Port Penn, we’re right across the Delaware River from Salem/Hope Creek.  They should know better than to try something like that!

.

bistransmissiontower

The DOE is hosting webinars on its 2012 transmission congestion study:

DOE 2012 Transmission Congestion Study Page

The study isn’t released out, even a draft, and the powerpoint isn’t available yet online.  GRRRRRRRR, we need that to have an idea what’s going on… oh, that’s probably why it isn’t there.  Soon, I’ll post it when it appears.

The first webinar was today, just over, and there are two more — just click on linked date to register:

What I’m seeing here from the powerpoint is that congestion is a non-issue.  And what is very clear from the congestion maps for 2009-2011 is that in 2009 there was essentially NO congestion, and it got worse in 2010, and then not so bad in 2011 but still far more than in 2009.  In essence, apparently what they’re doing has made it worse.

They did ask my question, based on the above observation of the 2009, 2010 and 2011 maps, and asked what the explanation was for absence of congestion in 2009:

A: He said that the relatively low level of economic activity was certainly a factor.  Temperatures were more severe in 2010 so that was a factor.  Yes, congestion, in terms of these three graphics, congestion is worse in 2010 than in the other two years, that is generally in the context of a generally declining pattern over a couple of years we’ve been looking at.  Don’t want anyone to get the impression that …. So part of this is that this is a function of scaling also?  Yes…

Uh-huh… right…

And then from slide 22, Preliminary Regional Findings: Midwest:

  • Data indicate on significant, persistent constraints, apart from those related to the development of remote renewable resources
  • Data do not indicate any areas with major reliability problems
  • The economic congestion that is occurring is small in relation to the total cost of wholesale electricity traded in organized spot markets.
  • Inconsistent market designs and practices between RTOS — as distinct from lack of transmission capacity — are a significant impediment to economically beneficial electricity trade.

But hey, we knew that!

Here are the prior “studies” from DOE:

2009 DOE Congestion Study

2006 DOE Congestion Study

And remember, the purpose of this is, in THEIR words, from THEIR site:

DOE’s Congestion Studies may contribute information needed to support the future designation of one or more National Interest Electric Transmission Corridors (National Corridors). On the basis of a congestion study, and after reviewing and considering public comments, the Secretary of Energy is authorized but not required to designate related geographic areas as National Corridors. Designation of a National Corridor has two effects:  1) it emphasizes that the Department considers the particular congestion problem to which the corridor pertains to be sufficiently acute to merit federal concern; and 2) it enables the Federal Energy Regulatory Commission to exercise “backstop” authority (under conditions specified in the Federal Power Act) to approve the siting of transmission facilities within the area of the corridor. In particular, the Commission may exercise its jurisdiction if a state agency has “withheld approval” for more than one year of an application to site a transmission facility within the corridor.

But wait, even they admitted in today’s Webinar that the courts have invalidated the designation of National Interest Electric Transmission Corridors both generally and specifically:

So we’re doing this … why???

It’s all about market, it has nothing to do with electric reliability, and billions are being spent to address a problem that does not exist and which is illegal to implement.  WRONG?  Prove it, please…

maidenrocksand_stribPhoto of Maiden Rock frac sand mining operation across the river

The MPCA has announced a frac sand mining air permit comment period for the mine proposed in Scott County near Shakopee.

I believe this is the first frac sand mining permit to go through MPCA air permitting (I’ll check). Here’s the MPCA’s Frac Sand Mining Page.

If you write comments, there are specific things that have to be included, it says “must” in the Notice and “shall” in the rules, so I think they mean it.  Here’s what the rules say about comments:

Subp. 2. Contents of written comments.

A person who submits comments under subpart 1 shall include in the comments the following:

C. the reasons supporting the person’s position, stated with sufficient specificity as to allow the commissioner to investigate the merits of the person’s positions.

You may request a contested case, and that must be done under Minn. R. 7000.1800 Petition for Contested Case.  If you plan to do that, also check out Minn. R. 7000.1900 Criteria to Hold Contested Case Hearing.

Send Comments and Petitions by August 27, 2012 to the MPCA:

Steve Gorg, Air Quality Permits Section

Industrial Division, MPCA

520 LaFayette Road North

St. Paul, MN  55155

steven.gorg@state.mn.us

Here are the primary documents from the MPCA site:

  • Document Intent to Issue Air Emission Permit to Great Plains Sand LLC, Shakopee – Notice Full Text
  • Document Draft Air Emission Permit
  • Document Technical Support Document
  • mesaba-netl-generic-gasifier.jpg

    Excelsior Energy’s Mesaba Project, the coal gasification plant that will not die, is returning to the Minnesota Public Utilities Commission on August 14, 2012.

    Notice – August 14, 2012 PUC Meeting

    At that time, they’ll address whether the original project’s permits apply to this project, and whether this one, under Minn. Stat. 216B. 1694, requires additional environmental review:

    **6.     E6472/GS-06-668 Excelsior Energy, Inc.
    In the Matter of the Joint LEPGP Site Permit, HVTL Route Permit and Pipeline (Partial
    Exemption) Route Permit Application for the Mesaba Energy Project in Itasca County.
    Should the Commission find, pursuant to Minnesota Statutes 216B. 1694 subdivision 3, that the
    site and route permits issued on March 12, 2010 for the Mesaba Energy Project are deemed valid
    for a natural gas fired plant located at the same site and that no additional environmental review
    is required under applicable state rules?

    This docket has been one of the longest strangest trips ever, a coal gasification plant that wasn’t needed yet fed by state and federal money, using CO2 capture and storage that does not, can not, and will not exist.  Here’s some history:

    Health Benefits of Coal (ya gotta read this one, HILARIOUS!)

    Mesaba – Extend the Hearing! (the hearing was a farce)

    And why are we here on the 14th?  The PUC granted a Site Permit to the project f/k/a Mesaba Project, the coal gasification plant:

    ALJ Recommendation – Mesaba Site Permit

    PUC Order and Site Permit – March 2010

    Then it starts getting complicated, Excelsior sends PUC letter saying it wants confirmation that the permits issued for the Mesaba Project coal gasification plant are valid for a natural gas plant, and that it would require no further environmental review:

    Excelsior Energy Request – May 31, 2012

    Notice of Comment Period

    Comment – mncoalgasplant.com

    Commerce CommentsSierra Club Comment

    And then Excelsior chimes again disclosing not much of anything about their “plan” for this gas plant:

    Excelsior’s Response to Commerce IRs June 26, 2012

    And then the Comment period is extended and we get another bite:

    MCGP Reply Comment

    And now we’re off to the races…

    In the Duluth News Tribune:

    Feds say no more money for Iron Range Excelsior Power Plant

    horsesasses.jpg