LTE in Dodgeville Chronicle
December 8th, 2016

See the lower 1/2 of MISO’s MVP project 5, running from near Dubuque, IA to the northeast to the “Cardinal” substation near Madison? That’s the Cardinal – Hickory Creek transmission line.
The Dodgeville Chronicle ran my Letter to the Editor, just in time for the meeting last night, held by Rural Utilities Service, about the Cardinal – Hickory Creek transmission project:
Carol A. Overland, Esq.
Red Wing, MN
RUS Scoping Meetings for Cardinal-Hickory Creek xmsn
December 6th, 2016
Slow evening at Rural Utilities Service’s scoping meeting for the Environmental Impact Statement for the Cardinal – Hickory Creek transmission project. RUS is involved because Dairyland Power Cooperative (DPC) plans to hold a 9% undivided interest in the project, and are looking to RUS to provide the funding. RUS held two more meetings, following on prior meetings October 31 and November 1 & 2, because their notice for those meetings went out a day late, so another Notice went out:
Notice of Intent To Hold Public Meetings and Prepare Environmental Impact Statement (October 18, 2016
Where’s my prior post on these meetings? It’s gone! Here’s the dates and locations (click for larger version) — the last one is tomorrow in Barneveld, Wisconsin:
So to make quick work of it, this is cut and pasted from the RUS Cardinal Hickory Creek page:
Alternatives Evaluation Study (July 2016)
Notice of Intent To Hold Public Meetings and Prepare Environmental Impact Statement (October 18, 2016)
Macro-Corridor Study (September 2016)
Alternative Crossings Analysis (April 2016)
- ACA Table of Contents
- ACA Main Report Chapters 1-5
- ACA Main Report-Chapter 6-References
- ACA Appendices
SCOPING MEETINGS
I had a quick chat with Dennis Rankin who’s in charge of the environmental review on this and the Dairyland Q-1 South projects, and had a few quick things to register, particularly that ATC has announced that the project is delayed:
ATC postpones Cardinal-Hickory Creek project – The Dodgeville Chronicle -Dodgeville, WI
I had this article and a few comments to add tonight, and will file more detailed comments before the deadline — now January 6, 2017.
(don’t worry, I’ll get this looking pretty by the deadline!)
On the way in, there was new transmission marching across the countryside, so ugly:
And look how close to this house in New Vienna, right up near the garage, and not far from the house either — this line cut right through the middle of town:
But all in all, it was a beautiful day for a drive today!
NOTICE – Annual Hearing – Power Plant Siting Act
December 5th, 2016
Here we go again, the Annual Hearing for the Power Plant Siting Act.
The full Notice:
Now’s the time to dig back into the cobwebs of memory of all the dockets over the last year, and the last 20+ years, and let them know how the Power Plant Siting Act is working, and more importantly, how it’s not working.
Comments are open until January 20, 2017. To file in eDockets (highly recommended), go here, and log in. If you don’t have an account, register (it’s simple, and fast) and then file in docket 16-18.
Note something different, this year they’re going to go over pipeline projects:
Recently, I’ve been involved in a project working toward increased meaningful and effective public participation in a pipeline docket, and what’s going through my head as I attend meetings, conference calls, and read very long intense emails, is that this is exactly what we’ve been talking about at these Power Plant Siting Act hearings for TWENTY YEARS! This is exactly what we’ve been working to deal with in the Certificate of Need Minn. Ch. 7849 rulemaking for THREE YEARS! These are exactly the same issues I’ve been raising in docket after docket, gaining a remand in one, some “adjustments” in others, and even to the appellate court a couple of times — MCEA had more success in this (see the EIS decision here). And so little changes.
2006 Report to PUC – Docket 06-1733
2007 Report to PUC – Docket 07-1579
2008 Report to PUC – Docket 08-1426
2009 Report to PUC – Docket 09-1351
2010 Report to PUC – Docket 10-222
2011 Report to PUC – Docket 11-324
2012 Report to PUC – Docket 12-360
2013 Report to PUC – Docket 13-965
2014 Summary Comments– Docket 14-887
OK, folks, time to saddle up for another cattle drive! Let’s get to it!
And on December 20… sigh…
MPCA’s THREE Red Wing Ash releases today
December 5th, 2016
OK, time to get to it. There were THREE releases from the Minnesota Pollution Control Agency today related to the Red Wing/Xcel Energy/Lab USA ash mining project. THREE!
The ash mining project’s EAW:
Public notice period: 12-5-16 to 1-4-17; Project manager: Kevin Kain
And two solid waste draft permits, first NSP’s ash landfill:
INTENT TO MODIFY AND REISSUE AN EXISTING SOLID WASTE FACILITY PERMIT TO NSP- RED WING ASH DISPOSAL FACILITY, RED WING
Open for public comment through Thursday, January 5, 2017
And one for Lab USA (modify and reissue? Hmmmm…):
Intent to Modify and Reissue an Existing Solid Waste Facility Permit to Lab USA’s Ash Processing Facility – Red Wing
Open for public comment through Thursday, January 5, 2017
There’s a meeting at the Red Wing library on Wednesday, from 5-7 p.m. about the Lab USA EAW, but what about the permits?
Army Corps denies DAPL easement, but then??
December 4th, 2016
The internet is going nuts with news that the Army Corps of Engineers has denied the Dakota Access Pipeline permit. It’s a pause… not STOPPED!
Morton County Sheriff briefing on moving back from bridge
Bismarck Tribune: Police consider pulling back from Backwater Bridge
But what’s really happening with the permit? No direct statement from Army Corps yet.
UPDATE: From U.S. Army Corps of Engineers:
Now, from Dept. of Interior Secretary Sally Jewell:
It looks like what’s happening is that the ACoE is denying the permit for the route over the river and through sacred Indian lands, and will be looking for a reroute and doing an Environmental Impact Statement. ABC News states that pretty clearly below. It’ll be in “stick it there” mode, with the ACoE looking for somewhere to put it! I’ve been looking and looking, don’t see anything from ACoE directly.
NYT – Federal Officials to Explore Different Route for Dakota Pipeline
Dakota Access Pipeline denied near Sioux Reservation
U.S. Army Corps of Engineers denies easement for Dakota Access Pipeline
Administration orders review of Dakota Access Pipeline easement (this version most closely states what I’m guessing is going on)