Xcel’s 2015 Peak Demand

February 21st, 2016

arrowdown

Remember Xcel’s CapX 2020 peak demand projections of 2.49% annual increase?  How wrong can they be?  And how unjustified was their basis for a Certificate of Need for CapX 2020?  And how are they held accountable for those gross misrepresentations?  This is why the rate case in progress, PUC Docket 15-826, is so important.

I love it when this happens… Xcel Peak Demand is again DOWN!  There’s a trend, and it’s called decreased demand.  Demand has yet to exceed the 2007 peak, and now it’s 8 years…

XcelPeakDemand2000-2015

Here’s the Xcel Energy SEC 10-K filed a couple days ago:

2015 – Xcel Energy 10-K

Is it any wonder they want to get away from a cost based rate a la their “e21 Initiative” scheme?  Particularly now that the bill for CapX 2020 is coming due and their newest rate case (PUC Docket GR-15-826) is now underway?

And the specifics, and note how they inexplicably forecast a 2016 peak of 9,327:

2015-Xcel Peak Demand Chart

 

horsesassaward

Here we go, thanks to Xcel Energy and Office of Administrative Hearings, based on the bias and double standards for participation and obstructions to intervention in the latest Xcel Energy rate case (PUC Docket GR-15-826).

Yes, Intervention in the rate case denied again:

20162-118122-01_Denial #2_Overland-NoCapX Intervention

And I quote:

Further, the Petition states that purposes for which No CapX 2020 was “specifically formed” (fn omitted) was to participate in dockets which are now closed, raising the question of why No CapX 2020 continues to exist.

aghast

H-E-L-L-O?!?!?!  This rate case docket is all about shifting the CapX 2020 and MISO MVP 17 project portfolio transmission costs from one scheme to another.   I specifically cited all the references to CapX 2020, MISO MVP, and transmission.

dohHere’s what has gone before…

Intervention Petition II

Xcel objection to second petition to intervene

Overland-NoCapX_Intervention Petition 2

Intervention Petition I

20161-117574-01_Order Denying Intervention Petition 1

No CapX 2020_Response to Xcel’s Objection

20161-116957-02_Xcel’s Objection to Intervention

NoCapX 2020 and Carol A. Overland_Intervention Petition Packet

And in a parallel track, note the double standard in pleading.

  • Note that Xcel has objected only to the Overland/No CapX 2020 intervention.
  • Note that Xcel has not objected to those who participated in the “e21 Initiative” which is the basis for this rate case “multi-year rate plan” and transmission shift.
  • Note how little the other “intervenors” say.
  • Note they do not state their interests.
  • Note they do not state how their interests are different from general ratepayers.
  • Note they do not state how their interests will not be represented by OAG and Commerce.

OAH has approved Interventions of “The Commercial Group,” “Suburban Rate Authority,” and “City of Mineapolis.”  I’m sure the approval of “Clean Energy Organizations” will soon follow, despite the lack of specific pleading and the apparent conflict with one “attorney” representing so many organizations that either have differing positions and interests, or which are adequately represented by other organizations and don’t need to intervene… funny how this double standard works…

Read the Petitions:

Petition to Intervene of the Commercial Group

Petition to Intervene of Suburban Rate Authority

Petition to Intervene 0f City of Minneapolis

Petition to Intervene 0f “Clean Energy Organizations”

Petition to Intervene of MN Chamber of Commerce

Check out each of these petitions.  Look at the pleading, what’s stated, and as importantly, what is NOT stated.  What are their interests?  How are the “interests” different than general ratepayers in their class?  How are their interests not represented by Office of Attorney General and/or MN Dept. of Commerce?

So what to do?  Participating in the public hearing is not sufficient, and if that’s the limited offering, well, there’s no Discovery for a public participant.  What’s next?  Fight for the privilege of an unfunded intervention, as if there’s nothing else to do?  The issues raised by Overland/No CapX 2020 will not be addressed otherwise.  And thos overt quashing of participation is not consistent with the “public” in “Public Utilities Commission” and the Commission’s mandate.

Meanwhile, FERC just denied the 2010 Petition for Intervention too in the case regarding the cost allocation for these CapX and MISO MVP projects, yes, that took them 5 1/2 years to do, so why now?  Check this out:

FERC Order – Docket ER09-1431 (p. 8)

Odd that should come up now… naaaah, not really.

booted-out

gavel

Apparently Judge Oxley did not like the Overland and No CapX 2020 Petition for Intervention in the rate case, late Friday the Order came out.  It was denied, without prejudice.  And yet interventions for Commercial Group, Suburban Rate Authority, and City of Minneapolis were granted…

20161-117574-01_Order Denying Intervention

… sigh… OK… fine…

Just filed at 12:01 a.m. Monday, January 25, 2016:

Overland-NoCapX_Intervention2_FINAL

These transmission issues being raised about CapX 2020 and the MISO MVP 17 Project Portfolio are so important that I’m going to be persistent.

Here’s the schedule, from the First Prehearing Order:

schedule

shame_shaking_finger

Shame, Xcel Energy.  Your basis for objecting to the Petition for Intervention of No CapX 2020 and Carol A. Overland is just not holding up when looking at other interventions, and noting that in your Xcel-existence, in all your rate cases, you’ve only objected to one potential intervenor.  So take that, Xcel:

No CapX 2020_Response 2 Xcel’s Objection

Here’s Xcel’s Objection:

20161-116957-02_Xcel’s Objection to Intervention

And here’s the original Petition for Intervention:

NoCapX 2020 and Carol A. Overland_Intervention Petition Packet

 

XcelLogoBanner

Yesterday at the Xcel Energy rate case prehearing conference, Xcel’s attorney, Eric Swanson, stated that they’d be objecting to the No CapX 2020/Overland intervention.  Just after that prehearing conference ended, their objection was filed:

20161-116957-02_Objection Intervention

Good idea, Xcel….

What do other Petitions for Intervention look like?  What other Objections has Xcel made to Interventions?  What do Petitions for Interventions that have been granted by an ALJ look like?  Let’s compare…

Recently, Xcel Energy’s Chris Clark, who I’d been working in tandem with years ago when he was just lowly corporate counsel cohort opposing the legislatively mandated Power Purchase Agreement for the Excelsior Energy Mesaba Project said, “I just don’t understand why the transmission side hates you so!” (rough, not exact quote).

Clark-Chris

Well, Chris, I guess you’re gonna find out.

I presume that this is just a way to eliminate anyone that they haven’t bought off in the course of that “e21 Initiative” where they “reached consensus” about wanting a business-plan based multi-year rate plan — many of the usual suspects were NOT present at that Prehearing Conference and there’d only been two Interventions filed prior to the Prehearing Conference, and only one filed since.

e21_Initiative_Phase_I_Report_2014

Yeah, great idea.  I testified against that effort at both Senate and House committees, where the room was backed full of those who’d “reached consensus” and they were all S-I-L-E-N-T as Sen. Marty and Rep. Garofalo ushered that bill through.  SHAME!  Will they show up for the rate case, and what position might the take?  Certainly not anything challenging the “Multi-Year Rate Plan.”

There was an interesting twist too.  I’d brought up that under Minn. Stat. 10A.01, Subd. 2, participation on a rate case is deemed lobbying, and requires registration and reporting when/if the thresholds are met, and requested that this requirement be addressed in the Prehearing Order.  The ALJ clearly knew nothing about it.

Minn. Stat. 10A.01, Subd. 2.  Administrative action.

“Administrative action” means an action by any official, board, commission or agency of the executive branch to adopt, amend, or repeal a rule under chapter 14. “Administrative action” does not include the application or administration of an adopted rule, except in cases of rate setting, power plant and powerline siting, and granting of certificates of need under section 216B.243.

I’d noted in the discussion that the lobbying statute is typically noted in the Commission’s referral to OAH, and thankfully, on the record, I’d thought to look at that Order, and there it was, p. 7:

Order10Areference

And I noticed that Eric Swanson was very, very quiet during that discussion.  HE is the one who charged me with not registering as lobbyist in the Not-so-Great Northern Transmission Line case, as attorney for Minnesota Power.  That was such a low budget virtually pro bono operation that there’s no way either RRANT or I would meet the thresholds for registering or reporting.  That gambit of his was just more harassment, trying to limit legitimate critique of their project and process.

So now, for a response to that Objection to Intervention of No CapX 2020 and Overland…