The Red Wing Republican bEagle ran my commentary on wind siting, all of it!  Short version?  Respectful wind siting now!  The community must consent!

Viewpoint: Respectful siting process for wind turbines long overdue

By Carol A. Overland, Red Wing

It’s taken a decade, but the Minnesota policy battleship is turning regarding siting of wind projects. State agencies, in their rush to site wind, have dropped the ball — they have failed in their charge to regulate and protect the public and the public interest. We need a respectful siting process, and that is 20 years overdue. If Minnesota doesn’t correct our wind siting process, the legitimate pushback will make siting a wind project difficult at best.

Recently an administrative law judge issued a recommendation that the Freeborn Wind Project be denied because it had not demonstrated it could meet the state’s noise regulation, or in the alternative, give the developers some time to demonstrate how it will comply with noise standards at all times throughout the project footprint.

The Public Utilities Commission will make a permitting decision, typically a month or more out. It’s not final, but this recommendation is a crucial step.

The Freeborn Wind case involves many “firsts.” It is the first project in Minnesota to be sited using the siting criteria of the Power Plant Siting Act (criteria in Minn. Rules 7850). It is the first project in Minnesota where the siting permit was subject to a contested case proceeding, in essence a trial, where the applicant had to prove up its application before an administrative law judge. It is the first project where an administrative law judge has recommended the permit be denied.

Lax rules

Minnesota wind siting has been lax and much of that falls directly on the Department of Commerce. The Environmental Quality Board no longer has siting authority. It’s been that way since 2005, when the Energy Omnibus bill shifted it to Commerce, doing siting “analysis” for PUC — in addition not to using Power Plant Siting Act criteria, and until now, no contested case.

There is no environmental review, no environmental assessment worksheet, no environmental impact statement, required for wind projects. Wind projects, until now, were separated out from the Power Plant Siting Act and permits issued citing the wind statutes and rules Minnesota Statute 216F and Minnesota Rules 7854, which have NO siting criteria at all? All wind siting permits cite only Statue 216F and Rule 7854 as permitting authority! That compartmentalization is the doing of the Department of Commerce.

There are small wind “standards,” which were ordered in 2008, but that was not a rulemaking. It was a process that was a too fast response to a legislative mandate, and in essence, the PUC took small wind standards and stamped them as “Large Wind Energy Conversion System” standards.

Nothing has been done since, despite pre- and post-construction complaints, suggestions, interventions and rulemaking petitions. State agencies, in their rush to site wind, have failed in their charge to regulate and protect the public and the public interest.

Issues are real

Wind projects are by definition the nuisance moving to the landowners. All are sited where there’s an established community, and the wind projects lease land in patchwork sites for their projects. Communities are steamrolled. The way projects are sited, it’s inevitable that homes are surrounded, and turbines are close to homes.

Noise issues are real. Noise modeling isn’t necessarily predictive, and siting often doesn’t allow for margin of error. Shadow flicker is real, but landowners are provided with blinds to live in the dark or are told to take a trip to Florida during times of heavy shadow flicker. Eagle nests are not accounted for, or in one case, blown away by helicopter, and in another, removed after getting a permit.

It’s time to develop thoughtful and respectful siting; It’s long overdue. We can establish standards and rules so that wind projects are projects people can live with. We can require modeling that provides for margin of error. We can take into account the feelings of non-participants who already live in the area and will be affected by a project moving in. The community must consent.

Looking forward, if Minnesota doesn’t alter siting regulations and practices, it’s going to be very difficult to site wind projects.

There’s also a problem looking backward, for there are people now living in the midst of improperly sited wind projects. Not only does Minnesota need to address siting issues, but Minnesota needs to develop policies for those living near and affected by wind projects, as has been done for other types of utility projects. There are at least two wind project permits now before the Public Utilities Commission regarding noise and

Minnesota’s noise regulation. Wind turbines are massive structures with 55-foot diameter concrete foundations — it’s not like we can just pick them up and move them.

Permits say that if there are violations, the violations must be corrected, or the permit can be suspended and/or revoked. In short, solutions to problems in existing wind developments are not easy, and few options are practical.

What to do? A start is to revamp Minnesota’s permit complaint process, which is occurring now in one docket. The revised complaint process, after public comment and a hearing, should be applied to all permits.

Another step is to enact an “opt out,” similar to the “Buy the Farm” option for transmission (Minnesota Statute 216E.12, Subd. 4, where affected landowners can make the utility buy them out rather than live under a transmission line.

Other ideas include a promulgation and revamp of PUC and MPCA rules, which is a multi-year process.

Policy takes a long time to change. Will Minnesota’s agencies, utilities, wind developers, landowners, and legislators work on the changes or will it be a continued fight? Do utilities want to site wind projects in Minnesota?

With the developments over the last year, I’m encouraged that Minnesota will work toward respectful siting. Let’s make it happen.

Carol A. Overland is a Red wing attorney who represents Association of Freeborn County Landowners.

p.s. Minnesota’s existing Wind Standards and Exhibit A.

“January Pretzel” — a Bent Tree bent turbine blade 1/20/2018

Taken by the Hagens in the Bent Tree wind project

DOH!  The Bent Tree Phase II noise report is out and it confirms that the project is violating the siting permit.

Bent+Tree+08+573+PostConstNoiseMonPhase+II+Report+2+7+18

Bottom line:

Here’s the Phase I report:

Bent Tree_Noise Monitoring and Noise Monitoring Report_20179-135856-01

So now what are they going to do?

Tomorrow, the Big Blue wind project is at the PUC which is violating their permit too, and the PUC decision options are to revoke permit, suspend permit, or continue operations with compliance filings.

StaffBriefingPapers20182-139717-01

The process here is flawed (to put it mildly).  There is noise modeling required in wind project permitting, but clearly that isn’t sufficient to site them in a way that won’t steamroll the neighbors to the project.  The setbacks in MN aren’t adequately protective.  Deal with it, Public Utilities Commission!

Comments were due today on Minnesota Power’s request for Exemptions from the rules governing content of Applications for a Certificate of Need for a transmission line.

map01

Look at the red on that map — potentially affected areas where MP is looking to put a transmission line.  WOOOOO-EEEE, that’s a lot of land!

Minnesota Power’s proposed Great Northern Transmission Line is inching along in the Certificate of Need process.  Here’s Minnesota Power’s site:

Great Northern Transmission Line page

And to look at the full docket, go to www.puc.state.mn.us, click on “Search eDockets” and search for 12-1163.  The application is expected sometime in March or so, but I’d guess it will be later.

Here’s how they plan to let people know about the project — it was filed a while ago, Comments were due, and I tried and tried to get people to comment, oh well, here’s what was filed about the Notice Plan filed in October and the Comments filed in November:

MP Great Northern Transmission Line Notice Plan

Commerce Comments on MP’s GNTL Notice Plan

Overland Notice Plan Comments

That’s sitting at the PUC now.  So where are we?  Just starting out…  Here’s a diagram of the hoops for the PUC process, edited a bit by yours truly for handouts at the meetings a couple months ago, we’re at the very first box in the chart:

puc-process-edited1

Today, comments were due on the Minnesota Power request for Exemptions from some specific rules, Reply Comments, that is.  Here’s what’s been filed:

Minnesota Power Exemption Request

Commerce Comments – Exemptions Request

MP Exemptions Reply Comments

Overland-Legalectric Reply Comments

Goodhue Wind ain’t C-BED!

April 8th, 2010

Goodhue Wind is in the news, and the timing is perfect foreshadowing for next week’s PUC meeting.

In yesterday’s MinnPost:

T. Boone Pickens Tilting at Minnesota Windmills?

In today’s STrib:

Pickens wind turbines coming to Goodhue

In going through the THREE FOOT pile of mail waiting here when I got back, I’ve been reading the Dept. of Commerce Information Requests to Goodhue Wind, and I am pleasantly shocked, they are ON this.  What is “this?”  The basic financing and C-BED claims of this project — it’s been smoke and mirrors from day one, and Commerce is paying attention, digging for more information, and it’s impressive.  MUST GIVE CREDIT WHERE CREDIT IS DUE, particularly to Commerce!!!

MOES Reply Comments

Staff Briefing Papers

THESE FILINGS ARE MUST READS!

Just in — here are the PUBLIC AWA/Goodhue’s responses to Commerce Information Requests.  All of these below are the PUBLIC versions — I don’t see much to gain by reviewing the specifics because that’s pretty restrictive.

First, Dockets 09-1349l 09-1350 and 09-1186 (PPA & Certificate of Need):

IR 1-4

IR 5

IR 5a

IR 5 Supplemental

IR 6

IR 7

IR 8 & 10

IR 9

IR 11

IR 12-13-14

Next, Docket 08-1233 (the siting docket)

IR 1

IR 2-3