beagle

They did change the headline, but the Red Wing Republican Eagle (“the Beagle”) printed my Commentary on Wednesday (the same day that the Public Utilities Commission postponed the Goodhue Wind May 2nd agenda item until June 20th!):

earth-day

Commentary: Respect blows strong for Earth and citizens

By: Carol Overland, The Republican Eagle

As I write this on Earth Day, I’m preparing for the Public Utilities Commission’s meeting next week which may seal the fate of the proposed Goodhue Wind project.

This is a poignant example of our obligation to respect the earth and its residents. By whatever name, this wind project has failed abysmally on all counts.

Citizen groups, individuals and elected officials have worked on this project for almost five years, and they have learned not only about this particular project, but about wind generation impacts.

Participation is the foundation of our democracy, and the people showed up, building their credibility at every turn. Local government wrestled with divergent interests to responsibly address the issues at stake. At tremendous cost and effort, residents learned to navigate regulatory agencies, respectfully participate in many meetings, research and consult experts, network with others, meet with county, federal and state agencies and committees, join a contested case, hold informational meetings with films and speakers, write comments and press releases, and testify before decision-makers. It’s been an exhausting rollercoaster ride.

Why pull the plug? The project has fallen apart.

T. Boone Pickens took his financing and turbines, abandoning the project. Trishe Wind, purchaser of National Wind, rejected the project. NSP declared the Power Purchase Agreements in default and rejected all subsequent proposals.

Ventum Energy, the sole local interest, was administratively terminated last August. New owner New Era operates out of a P.O. Box and doesn’t pick up mail.

There’s nothing left.

This project fails as a matter of energy policy, because it would not replace a single megawatt of fossil generation or reduce CO2 levels. The Renewable Energy Standard is a mandate to add generation, but it’s not “either/or,” because there’s no replacement or shutdown of fossil generation.

We have an electricity surplus, and the RES adds to that surplus, which utilities sell on the market rather than cut fossil generation.

Xcel Energy doesn’t need Goodhue Wind because it’s met its RES quota far ahead of schedule. Further, Goodhue Wind is not locally owned, not locally financed, and is not community energy development by any definition.

Developers utilized unethical practices in securing land contracts and silencing those who signed them, pitting neighbors and family members against each other. Much is deemed “trade secret,” but landowners are backing out, and the project’s land control is in doubt.

The Public Utilities Commission has asked reasonable questions, and New Era has not answered.

Environmentally, the Goodhue Wind project would do much harm. Despite Minnesota’s unfortunate exemption of wind projects from environmental review, we learned that “renewable” doesn’t mean there are no harmful impacts.

This project is located along the largest migratory bird pathway in North America. Eagles nest in the project footprint and the U.S. Fish and Wildlife Service estimates the project would kill eight to 14 eagles annually, 160-240 dead eagles over a 20-year project life.

The developers haven’t completed avian and bat surveys, one monitor has been hanging broken for seven months, and they refuse to comply with USFWS modeling guidance. Contractors have exhibited gross arrogance in conducting surveys and in contacts with landowners, including alleged trespassing and initiating legal action against a lawful resident, enraging the judge who dismissed the case.

Were the project built, it would be without regard to the residents and livestock, with turbines closer than the county ordinance prescribes, and closer than recommended by the Minnesota Department of Health.

If built, the project would inflict low frequency noise on adjacent residents and subject them to shadow flicker for which Commerce suggests “shades” as mitigation. The only way to mitigate the impacts is to site with adequate setbacks, such as the one-half mile buffer which the health department notes should eliminate complaints.

Wind must be sited correctly, because turbines aren’t easily moved.

This is Earth Day. It’s not about “being right” but about “getting it right.”

 

Carol A. Overland of Red Wing is the attorney for Goodhue Wind Truth.

 

excelsior-yahoos

I love it when this happens, it’s almost as good as the results of a google image search for “Excelsior yahoos” this morning:

ER13-1049 Order on Filing

littlebirdie-cardinal

Big thanks to a little birdie who relayed the good news:

hee hee hee hee hee, I LOVE it when this happens…

DSC01318

Greetings from the Range.  Today’s first Not-so-Great Transmission Line meeting was in Taconite. This is near where my Exclesior Energy Mesaba Project clients own property:

 

I got there late, but hey, got there before teardown, and had time for a chat with the GIS guy and a fleet of engineers.  There wasn’t quite the passionate standing-room-only turnout that there was against the Excelsior Energy Mesaba Project:

DSC01319

This project is moving slowly, and the application for the Certificate of Need has yet to be filed.  That makes sense because it was only last year that it moved from a C to a B project at MISO.  Here’s the listing (click for a larger view):

MTEP12

Today what I wanted to find out was “What’s happening at the border?” so I went over that with Mr. GIS.  Click HERE to pull up maps at the Minnesota/Canada border.  What I found was that none of the transmission corridors proposed have transmission lines in them, and there’s no corridor of any other sort either.  ???

And further south, north and near Taconite, there’s a funnel where all options end up in a narrow area with three narrow corridors: one corridor has a line that they told me had been taken out; one corridor has no road or transmission line, nothing; and the other one has a line going smack dab down the corridor.  Hmmmm, I wonder where they plan to put this new line?

(and each time I try to pdf them for posting, firefox crashes, AAAAAAAAAGH!)

… one moment please… or three… or four… I may never get that posted!

Anyway, I also had a chat with a fleet of engineers, because in considering “need” for the line, I want to know the capacity of the line, meaning emergency rating, so that I can get an idea what the claimed need represents compared to potential capacity.  So far, they say there’s a need for 250MW due to a PPA with Manitoba Hydro.  OK, lovely, but what’s that got to do with a 500 kV line?  I asked them what the emergency rating was of the line that’s there now, the 500 kV, and it took a while, they didn’t want to answer, giving waffly excuses about liiting factors.  I know all about limiting factors and things change, upgrades are happening all the time, so just out with it.  I finally was told that the existing 500 kV line was 1732 MVA.  OK, that makes sense.  Although it doesn’t make sense to me why Minnesota Power uses low capacity lines.  Xcel uses ACSS conductors, a higher capacity line, but MP uses ACSR, a lower capacity.  Why?  Why go through all the rigamarole of certifying and getting a route permit for a little line?  One engineer pointed out the Arrowhead as an example and yes, that’s a good example of planning that makes no sense, or a business decision that makes no sense.  If they’re going to go for it, why not make it worth their while?  Well, other than that there’s that pesky issue of needing to demonstrating need.  But one thing that was disturbing was that when asking for info on the existing line, to consider why that line wasn’t being upgraded, or double circuited, etc., one engineer said that they didn’t know that for the current line yet because they’re not there.  I was referring to the existing line and made that clear, but what I didn’t get into was that I know what the rating is for their planned line, that it’s in the MISO filing (see chart above, it’s also 1732 MVA).  He should know better than to think that I’d believe they don’t know what the emergency rating would be for the line they’re proposing!!!  AAAARGH.  Anyway, I’ll post that chart one more time so we’re clear the project and rating we’re talking about here:

MTEP12

That’s a 1732 MVA (A rating) for a line where all they’ve got to justify need so far is a 250 MW PPA with Manitoba Hydro.

 

 

arrowdown

How did this happen?  I forgot to post the link for the 2012 Earnings Call transcript from Seeking Alpha!  And it’s a doozy.  You can find the FULL TRANSCRIPT HERE.

Northern States Power – Minnesota estimates a  decrease of demand in Minnesota of about 1.2% (-1.2%) in 2013:

 Andrew M. Weisel – Macquarie Research

A few questions on behalf of Angie Storozynski. First question is you talked quite a bit qualitatively about the load growth expectations, but can you give us the number that you’re expecting for 2013 and in the long term?

Teresa S. Madden – Chief Financial Officer and Senior Vice President

Sure. I mean, in terms of 2013, maybe if I just talk about it by operating company. We’re — for NSP-Minnesota, we’re looking at a decrease of about 1.2%, NSP-Wisconsin expected to be flat. In Colorado, just under 1%, actually, that’s more about 0.6%. And in Colorado — I mean, excuse me, and in Texas, over — just around 3%, I would say. So overall, we expect it to come in between up to 0.5% on a consolidated basis.

 XEL Earnings Call, January 31, 2013. 

Benjamin G. S. Fowke – Chairman, Chief Executive Officer and President

Well, everything — overall, on the residential side, it’s safe to say everything is pretty flat. So then you move to the C&I side, and actually, the strongest C&I growth was in Wisconsin this year, followed by Texas, I think, followed by Colorado, which had small growth. And then we were — we didn’t grow at all in Minnesota for a number of reasons. That said, the economy definitely saw some signs of improvement in 2012. Housing permits were up. Job growth was better than the national average. Unemployment was equal to or better than the national average. So I think the economies are in decent shape across all our jurisdictions. Doesn’t necessarily mean it translates to high sales growth. And that’s consistent with our forecast. I mean, we’re not anticipating that we’re going to see a tremendous rebound in sales, even as the economies start to improve. I mean, I think, that’s our new normal, frankly.

That’s also reflected in their SEC filing showing decreased peak demand, from 9,792 in 2011 to 9,475 in 2012, and a forecast of 9,215 for 2013:

Northern States Power 10-K (2012).  Those are numbers I like to see.

Meanwhile, for example, Xcel has produced “forecasting” for the Hollydale Transmission Project that shows another picture entirely — that’s because the Hollydale application is based on old and outdated forecasts from 2006, the peak demand prior to the 2007 economic crash, and bases its need claim on a forecast of 1% annual growth in peak demand:

 

Hollydale Application, p. 42-48; 50-57; see also 12, 14, 35, 38; see also Table 2 and Table 3, p. 48-49.  Xcel’s “Hollydale Need Addendum,” dated January 24, 2013, exacerbates this error claiming a 1.8% growth rate and using a 1.8% growth projection for its forecasts.  Michlig Direct, Schedule 2, Hollydale Need Addendum, p. 24.  For the full Hollydale docket, go HERE and search for CoN Docket 12-113 or Routing Docket 11-152.

What would this “Percent Load Growth Over Time” chart look like with a -1.2% and no expected improvement for the foreseeable future?

 

 

NewEraLogo

The continuing saga of the Goodhue Wind project … well… it continues, with Reply Comments filed yesterday with the Minnesota Public Utilities Commission.  This encompases FOUR dockets at the PUC — to see them, go HERE and search for dockets:

09-1186  Certificate of Need

09-1349  Power Purchase Agreement

09-1350  Power Purchase Agreement

08-1233  Siting

This most recent flurry of Comments was triggered by the PUC’s Order requesting a lot of information from New Era and parties and the public:

PUC Order in Goodhue Certificate of Need docket

New Era responded with a request for delay and did not answer the PUC’s questions:

New Era – Request for Delay of Reply Deadline

So here are the Goodhue Wind Truth Reply Comments:

GWT Reply Comments April 17 2013

And New Era sent this a few minutes to 4 p.m. yesterday, with a couple snippets:

ReplyComments_20134-85824-04

At this point, given the Commission’s March 20, 2013 Order, New Era has no confidence that due process for this project will ever end, nor that an ABPP will ever be approved, however comprehensively and carefully drafted.

Nonetheless, for reasons not fully known to New Era, and after a delay of two and a half months from the date of its detailed proposals, NSP chose to reject all of these proposals, as set forth in their letter to New Era of April 12, 2013, a copy of which New Era expects NSP will file with the Commission or on about the date of these reply comments. New Era notes that while its proposals requesting an assignment of the power contracts were pending, NSP issued an RFP for additional wind energy and collected bids in response thereto, including bids from the three companies backing the New Era proposals.

New Era continues to believe that an assignment of the power contracts to a third-party site would be a reasonable compromise and solution to the difficult circumstances surrounding this project.

In its April 12, 2013 letter to New Era, NSP stated that New Era would have 30 days from that date to effect a cure of the power contract defaults.

So we fired off a quick response, particularly regarding New Era’s “Where does New Era go from here.”  How does one resist an invitation to tell them were to go?

GWT Reply Comments II April 17 2013

II. WHERE DOES NEW ERA GO FROM HERE?

New Era notes that all of its proposals to NSP to cure the defaults in the Power Purchase Agreements have been rejected as of a letter of April 12, 2013. GWT appreciates that disclosure. As of April 12, 2013, per New Era, NSP has stated that New Era has 30 days to cure the defaults in the PPAs. Therefore, as of May 12, 2013, or opening for business on Monday, May 13, 2013, New Era will be able to report status to the Commission and the Commission will know whether there has been a cure or whether the project is terminal. Regarding New Era’s question “Where does New Era go from here,” Goodhue Wind Truth requests that if, as expected, the defaults in the PPAs are not cured, that New Era go away, formally withdrawing the Certificate of Need and Siting applications. GWT takes no position as to New Era’s destination.

What result are we looking for?

Goodhue Wind Truth asks that the Commission provide the opportunity for New Era to withdraw its Certificate of Need and Siting applications. If New Era fails to withdraw its applications, Goodhue Wind Truth requests that the Commission either directly deny New Era’s request, or in the alternative, take no action to extend the Certificate of Need in-service date.

New Era, the clock is ticking…