Yeah, you tell ’em!

A little birdie told me that there was a new MISO study for Excelsior, and whooooeeeee, here it is:

a324_interim_report-oasis_addendum1.pdf

OK, folks, once more with feeling:

BASED ON THE ABOVE RESULTS, IT IS CONCLUDED THAT THE REQUEST FOR 603MW FOR FIRM TRANSMISSION SERVICE CANNOT BE GRANTED AT THIS TIME. CONSTRAINTS ARE LISTED IN TABLES 2-1 THROUGH 2-14. ALL CONSTRAINTS MUST BE MITIGATED BEFORE SERVICE CAN BE GRANTED.

Pretty clear, eh?

Here’s my Motion to the PPA ALJ:

Motion to Include MISO System Impact Study

The birdie probably wanted to offset that awful testimony of MISO’s Clair Moeller yesterday…