Big Stone is dead, dead, dead
November 2nd, 2009
Hot off the press from MDU — there’s contact info at the bottom.
DO SEND THEM CONDOLENCES AND A THANK YOU NOTE!!!
From MPR just now:
And a BSII Press Release found in the inbox:
November 2, 2009
Participating utilities announce wind-down of Big Stone II project
The participating utilities announced today that they will not build the Big Stone II Project, a planned 500-to-600-megawatt coal-fired power plant to be located near Milbank, South Dakota, and its associated transmission. The project required additional participants to move forward; however none have committed.
Big Stone II, a fully permitted project, had been determined to be the least-cost, environmentally sound baseload power plant for the project participants. The project’s high voltage transmission facilities were to be sized to also serve the region’s burgeoning wind energy development.
The Big Stone II Project participants were Central Minnesota Municipal Power Agency, Heartland Consumers Power District, Missouri River Energy Services and Montana-Dakota Utilities Co.
For information specific to each company, contact:
Mark Hanson, Montana-Dakota Utilities Co., 701-530-1093 or mark.hanson@mduresources.com.
Bill Radio, Missouri River Energy Services, 605-731-2522 or billr@mrenergy.com.
Russ Olson, Heartland Consumers Power District, 605-256-6536 or rolson@hcpd.com.
Lori Frisk-Thompson, Central Minnesota Municipal Power Agency, 507-526-2193 or lorift@cmmpa.org.
LS Power’s Sunrise River Energy in the news
November 2nd, 2009
Oct 19 Chisago County meeting re: LS Power Sunrise River Energy Station
How odd… it’s in both STrib and StPPP today… so comment opportunities abound!
Here’s the story from Dennis Lien:
Skeptics question Chisago power plant
Residents fear water pollution, say plans are too vague
By Dennis Lien
Updated: 11/01/2009 11:22:19 PM CSTBut critics have other concerns about what could be the largest natural-gas plant in the state.
And from the STrib’s Tom Meersman:
Protected aquifer feared at risk
It’s about appropriate land use
It can’t be used for industrial purposes in the seven-county metro area.
Others expressed doubts about the company’s change of mind on groundwater use.
Rob Kravitz lives about 2 miles from the site and opposes the plant, period.
Xcel’s 3rd Quarter – decline continues
October 29th, 2009
The decline continues, of course, of course…
Xcel’s 3rd Quarter investor conference call was this morning. I really enjoy these calls, because I get to hear them forced to tell bad news. And the bad news for me this morning was that it wasn’t as bad as I’d hoped it would be.
You can listen to the call on Xcel’s site:
You can also get a transcript of the call at Seeking Alpha:
Today I actually listened to it, and Krie, who sits next to me most of the day, got all fired up, and jumped off the couch and started in on her “squeaky bark,” not the bit #100 lb. German Shepherd “something’s going on down on the street” roar, or her frantic “I see a cat and I want LUNCH!” lunge, buther “squeaky bark,” sounding like a Pomeranian, too cute, and each time David Sparby said something, she start squeaky barking, like she does when she hears puppies on a Doggyspace video… hilarious. But I wonder what she was saying… or what she was hearing!
Anyway, here’s the real poop:
or at the SEC site:
It’s down, down, down, but … well, I want to see it down even more!!
Note the massive decrease in electric revenues, but that’s offset by an equal drop in fuel and purchased power, so the bottom line looks better. What I care about is sales, though, not the bottom line, and it’s good news to see Electric Revenues drop by 955 in 2009 thus far, or a tadbit under 15%. Works for me!!!
Looks to me like it’s down 3%! Need, schmeed, there isn’t any…
Capitalism happens — let the market decide!!
PolyMet Draft EIS released
October 28th, 2009
WOW… and here I thought PolyMet’s Draft EIS was as moribund as the EIS for Excelsior Energy’s Mesaba Project. Nope, here it is:
It’s HUGE, it will take a while, there are a lot of parts.
They are not accepting comments until after November 2, so after that time, I’ll post info on that.
Motions to Dismiss PATH Transmission Application
October 28th, 2009
HA! The Commission staff from both the state of Virginia and the state of West Virginia have both brought Motions to Dismiss the PATH transmission application. Hilarious! About time! PATH is the Potomac-Appalachian Transmission Highline.
Seems there’s a theme goin’ on…