Click map for larger version:

path-map-small

PATH, the Potomac Appalachian Transmission Highline, is in trouble… AGAIN…

The good news is that the West Virginia Public Service Commission staff is challenging need for the PATH line, which was already postponed by PJM.  And then there’s these pesky states questioning the need, like Maryland, which challenged the corporate organizational form, noting that it wasn’t a utility so “get outta here!”

Now it’s time for the West Virginia PSC staff to raise its eyebrows and deliver a solid Motion to Dismiss:

WVa PSC Staff’s Motion to Dismiss PATH Application

For the entire docket, go here:

West Virginia PSC Docket for PATH Transmission Line

And here’s the way it looks in the press:

$2B PATH project faces dismissal by W. Va. regulators


Posted: 6:39 pm Thu, December 16, 2010
By Associated Press

CHARLESTON, W.Va. — An application to build a $2 billion power line from West Virginia to Maryland should be dismissed because less expensive alternatives should be considered first, say staff reviewing the project for the West Virginia Public Service Commission.

Developers of the Potomac-Appalachian Transmission Highline, or PATH, say the 765-kilovolt line is needed to meet projected power demand along the East Coast by 2015.

But PSC staff said it was “ludicrous” to continue with the project while changes to the region’s existing power grid are being contemplated. Staff specifically mentioned Virginia-based Dominion’s recent notice to rebuild its 500-kilovolt line from Mt. Storm in West Virginia to the Doubs substation in Maryland. That upgrade and other improvements are estimated to cost $500 million to $600 million.

Another planned project is the Mid-Atlantic Power Pathway in Maryland. The line is to provide power to the Delmarva Peninsula.

Dominion says the Mt. Storm-Doubs line, which was built in 1966, must be rebuilt to maintain service. Developers gave the line’s current condition as a justification for the PATH project and the separate Trans-Allegheny Interstate Line.

“The rebuild will be a more stable line with 65 percent increased capacity,” PSC staff said it its Dec. 10 filing. The additional capacity “will push the need for the PATH line further out on the horizon,” perhaps to 2020, staff wrote.

PATH is a joint venture of Allegheny Energy Co. and American Electric Power Co. The proposed 275-mile line would run from AEP’s John Amos plant in West Virginia, across three counties in Northern Virginia, to a substation near Kemptown in Frederick County.

At least 250 groups, representing landowners, The Sierra Club, local county commissions and boards of education are opposed to PATH’s construction. Many of them have submitted letters supporting the latest staff filing.

The filing marks the second time PSC staff has recommended the application be dismissed. In October 2009, staff sought to dismiss the application because Maryland’s utility commission had dismissed an application in that state, saying it had been improperly filed.

Instead, the utilities agreed to extend the deadline for when the PSC must make a decision from May 16, 2011, to July 28, 2011.

PATH spokeswoman Jeri Matheny said Thursday the Dominion line “ties in very well” with the PATH project. Also, once PATH is built the Dominion line can be taken out of service for a rebuild, he said.

Matheny did not have an immediate comment on the staff’s recommendation to dismiss the application, saying a formal response would be filed with the PSC next week.

Earlier this month PJM Interconnection approved the Mt. Storm-Doubs line, but also reaffirmed its support of the PATH project. PJM manages the electrical grid in a 13-state region.

If the three-member PSC doesn’t dismiss the PATH application, staff is asking that it require developers to submit new testimony regarding the economic and environmental aspects of the project. Staff is also asking that AEP and Allegheny Energy again agree to extend the decision deadline.

The commission has not taken any action on the staff’s recommendation, PSC spokeswoman Susan Small said Thursday.

transmission1sunset.jpg

It’s about time… a judge in Montana has declared that a private entity that is building the MATL transmission line does NOT have the power of eminent domain!  Well DUH a lot of us will say, this is a PRIVATE company, they’re not a regulated utility, so of course they wouldn’t have power of eminent domain.

“No judicial decision that this court is aware of provides authority for MATL’s position that a private merchant transmission line, without express or implied authority for condemnation, may pursue eminent domain proceedings,” she wrote.

But wait… what about CapX 2020, and their transmission plans from hell across the Midwest.  Let’s be clear — there is NO entity organized under the laws of the state of Minnesota named “CapX 2020,” and they have NOT declared, and refuse to declare what entity will own it.  At the same time, the Minnesota PUC agenda lately has had Xcel transferring its transmission assets to ITC.  So, what do you think they’ll do with CapX 2020 transmission after it is built USING THE POWER OF EMINENT DOMAIN TO DO IT?  $50 says they’re transferring it to ITC, or TRANSLink or whatever transmission only company they can find.  It’s a shell game, we know what they’re doing, but try to get the PUC to care!

shellgame

Judge denies MATL use of eminent domain


By KARL PUCKETT • Tribune Staff Writer•
December 14, 2010

A district judge in Montana ruled Monday that a Canadian developer of a high-voltage power line has no authority to condemn private property for the project.

The decision, filed Monday, is a victory for landowners trying to limit the impact of the Montana Alberta Tie Line. It also could carry ramifications for other developers proposing transmission projects to meet demand from wind developers asking for additional shipping capacity.

“Larry Salois only wanted to protect his mother’s property from the transmission line going through historic Indian archaeological sites,” said Salois’ attorney, Hertha Lund. “He never wanted a legal battle.”

Salois is the guardian of his mother, Shirley Salois, the property owner. They live east of Cut Bank.

In July, a Montana subsidiary of Tonbridge Power Inc. of Toronto filed a complaint to condemn their land in Glacier County District Court after Salois argued the proposed route should be adjusted across his property farther from tepee rings and a wetland.

Lund argued Tonbridge could not exercise the right of eminent domain because it is not an agent of the state that has been given express legislative authority to acquire private property.

District Judge Laurie McKinnon agreed and granted Salois’ motion to dismiss the company’s condemnation complaint.

“No judicial decision that this court is aware of provides authority for MATL’s position that a private merchant transmission line, without express or implied authority for condemnation, may pursue eminent domain proceedings,” she wrote.

The Legislature’s grant of eminent domain power to governmental bodies must be strictly construed, the judge said.

Private individuals and corporations, like state agencies, have no inherent power of eminent domain, McKinnon said, and their authority to use it must be derived specifically from the Legislature.

Years ago, condemnation by a public utility for the purpose of constructing electrical power lines was authorized by legislation, the judge said. That authority allowed the former Montana Power Co. to acquire property by eminent domain.

But that legislation has since been repealed “and MATL can cite no legislative authority for its pursuit of land acquisitions by eminent domain, either expressly or by necessary implication,” the judge said.

Tonbridge had asserted that an electrical transmission line is a public use, giving the company the right of eminent domain. Three wind farm developers have purchased capacity on the line. Poles started going in the ground in August with the company working around the Salois property.

Bob Williams of Tonbridge said the company was surprised and disappointed with the decision. Tonbridge is considering an appeal, he said.

Voluntary deals with landowners remain the company’s goal, he said. The Salois complaint was the company’s first condemnation action in Montana.

“That said, projects such as this that are in the public interest have to be able to fall back on eminent domain as a last resort,” Williams said.

“Even when we have exhausted all other options, it still means that landowners are compensated fairly.”

The MATL project was permitted under the Major Facilities Siting Act and the public need for it was determined during the review process, said Johan van’t Hof, Tonbridge’s CEO.

He argued the judge’s decision “doesn’t square with the reality” of private companies building cable, telephone, transmission and pipelines.

As a result of the decision, Lund, Salois’ attorney, expects other businesses planning transmission lines to seek a “legislative fix,” giving companies the power to condemn land for transmission lines.

NorthWestern Energy, the state’s largest utility, is planning the $1 billion Mountain States Transmission Intertie, which also would ship wind power. Tonbridge and renewable energy developer Gaelectric are jointly planning the “Green Line” between Great Falls and Townsend.

“I hope the Legislature protects the interest of the landowner and the small guy in this process,” Lund said.

The 215-mile transmission line will connect the electricity grids in Montana and Alberta between Great Falls and Lethbridge, Alberta.

Tonbridge still is negotiating easements with landowners along the southern half of the project from Cut Bank to Great Falls, where construction has yet to begin. Lund also represents 20 landowners along that stretch in easement negotiations. Those landowners have been pushing for tweaks in the line as well.

“This obviously puts them in the driver’s seat,” Lund said of the Salois decision.

Salois pushed the company to alter the location of poles planned for his property, outside of the 500-foot approved corridor, because he said the line was planned too close to Blackfeet tepee rings and a wetland.

In October, the Blackfeet Business Council agreed to write a letter in support of Salois’ efforts. The council said the land involved was once Blackfeet land and told Salois that he had the support of the nine-member council “in your efforts to fend off this incursion by a multinational company.”

“For now, things are protected,” Larry Salois said.

Tonbridge initiated settlement discussions with Salois a few weeks ago and hopes to reach an agreement before Christmas, van’t Hof said.

PEPCO is falling down on the job

December 12th, 2010

horsesassaward

Nearly two years ago, I attended a hearing for the Delmarva Power Integrated Resource Plan, which was the most bizarre hearing I’ve ever experienced.  At that time, I raised issues about decreasing demand, entered into the record the PJM demand documents that we’d used in the Susquehanna-Roseland transmission docket in New Jersey (also PJM), and raised concerns that no SAIDI, SAIFI and CAIDI reliability info was reported.  After that meeting, I presented Delmarva Power’s attorney Todd Goodman with a well-deserved “Horse’s Ass” award for his performance at that meeting.  The points I’d raised at that meeting about what was missing in their “IRP” were oh-so-valid:

Transcript – Delmarva IRP Hearing December 3 2008

It took a while, but last week, the Washington Post featured an article showing that PEPCO, utility in D.C. and Maryland, and the corporate parent of Delmarva Power, has an inexcusably miserable record for outages.   That’s something that’s demonstrated in the SAIDI, SAIFI and CAIDI reports!  And folks, don’t go conflating transmission with distribution as the cause for the outages, as utilities would have you do.  Anyway, here’s that article:

Washington Post Analysis: Why PEPCO can’t keep the lights on

PEPCO executives acknowledge need to improve reliability

As you read the article, note there’s not a word on D-E-R-E-G-U-L-A-T-I-O-N as a contributory factor, much less the primary reason.

Washington Post analysis: Why Pepco can’t keep the lights on

By Joe Stephens and Mary Pat Flaherty
Washington Post Staff Writers
Sunday, December 5, 2010; 12:38 AM

In high-powered Washington, one of the world’s most wired and connected metro areas, the region’s leading electric company has trouble just keeping the lights on.

Pepco delivers power to 778,000 customers in the District and neighboring parts of Maryland, including some of the most affluent communities and most important institutions in the nation. But in reliability studies, the company ranks near the bottom in keeping the power on and bringing it back once it goes out, an analysis by The Washington Post has found.

In fact, the average Pepco customer experienced 70 percent more outages than customers of other big city utilities that took part in one 2009 survey. And the lights stayed out more than twice as long.

Pepco’s reliability began declining five years ago, records show; company officials acknowledge that they have known of the problem but that they only started to focus on it more recently.

Moreover, Pepco has long blamed trees as a primary culprit for the frequency and duration of its outages, implying that the problem is beyond its control. But that explanation does not hold up under scrutiny, The Post analysis found. By far, Pepco equipment failures, not trees, caused the most sustained power interruptions last year.
Read the rest of this entry »

After four years, finally, the Public Utilities Commission has denied an extension of the old, old permit.  Kenyon Wind was first applied for way back in 2006.  To see the full PUC record, go to www.puc.state.mn.us and go to “Search eDockets” and then search for “06-1445.”  Recently, because their permit was expiring, it was granted and then two years was extended for two years, they came back to the PUC for yet another extension.

Here’s the report from the Red Wing Republican Eagle:

beagle

Kenyon Wind project in doubt after state denies permit extension

They haven’t built this project, despite being issued a permit on July 18, 2007, nearly a year after they’d applied.  Since that time, much has changed.  Goodhue County passed its Goodhue County Wind Ordinance.   The laws for Community Based Energy Development (C-BED) have changed, amended each year since it was passed.  And the Kenyon Wind Project has changed:

map

Here’s the CFER’s Comment:

CFERS Comment

Here’s Kenyon Wind’s comments:

Kenyon Wind Response to Comments

And the PUC denied the permit, 3-2.  Commissioners Pugh, O’Brien and Wergin voting to Chair Boyd and Judge Reha were the two voting against denial of Kenyon Wind’s request for extension.

EEEEEEEEEEEEE-HA!!!  It took four years, but this vaporware project is finally dead!

Seen on a North Dakota highway!

December 8th, 2010

Yes, it’s a roadside black lung testing station:

blacklungsnippet

blacklungblackhills-trip-2010-024