And even more transmission?

April 10th, 2021

We’ve seen increased promotion of even more transmission, with claims it’s NEEDED, sorely needed, to reach renewable goals. What utter crap…

We’ve also seen “Grid North Partners” spreading their misinformation, working on making a “CapX 2050” happen.

Do we really need to do this AGAIN?!?!?!

Apparently, they think we do… sigh…

This appeared recently, an article linked to this blurb, and it’s disturbing:

Right… read it and get ready for another decade long fight. I figure I’ve got that long and more, so let’s get to it! Are you ready?

Transition… transmission… transition… transmission…

PPSA Annual Hearing Report

December 30th, 2020

It’s out, the Administrative Law Judge’s report on this year’s Power Plant Siting Act Annual Hearing. The hearing this year was particularly frustrating, horrible turnout, and I’ve got a part in that, because I didn’t spend the massive amounts of time getting notice out to people, drumming up interest, so there is that…

Here’s the Report:

Here are a couple of documents to check out that I included with a written comment:

PPSA Annual Hearing NOW

November 20th, 2020

RIGHT NOW! It’s the PPSA Annual Hearing… sigh… here we go again.

Go to webex, Event # 146 311 2620. The powerpoint slides will be here (and will also be filed on eDockets).

To be able to comment, you have to get on the phone 866-609-6127, Conference ID: 4449079, and to comment, you need to press #1 and get in queue.

Here is the Commerce info about this year’s projects:

And for the record, folks, note that wind is not exempt from many of the parts of the PPSA:

“Free marketers,” duck and cover. And utilities, contractors, get ready… Just in, for Public Inspection, will be released Monday:

The gist of it is that utility infrastructure and equipment should not be coming in from other countries, particularly “adversaries.” Threat? What threat?

From the E.O., p. 2-3:

I further find that the unrestricted acquisition or use in the United States of
bulk-power system electric equipment designed, developed, manufactured, or supplied by persons owned by, controlled by, or subject to the jurisdiction or direction of foreign adversaries augments the ability of foreign adversaries to create and exploit vulnerabilities in bulk-power system electric equipment, with potentially catastrophic effects. I therefore determine that the unrestricted foreign supply of bulk-power system electric equipment constitutes an unusual and extraordinary threat to the national security, foreign policy, and economy of the United States, which has its source in whole or in substantial part outside the United States. This threat exists both in the case of individual acquisitions and when acquisitions are considered as a class. Although maintaining an open investment climate in bulk-power system electric equipment, and in the United States economy more generally, is important for the overall growth and prosperity of the United States, such openness must be balanced with the need to protect our Nation against a critical national security threat. To address this threat, additional steps are required to protect the security, integrity, and reliability of bulk-power system electric equipment used in the United States. In light of these findings, I hereby declare a national emergency with respect to the threat to the United States bulk-power system.

WHAT?!?!

The June 25, 1998 blackout report needs to be on the interwebs available to the world.

June 25, 1998? That’s the night of the transmission fail that disconnected the Midwest from the Eastern Interconnect. That question was asked by Minnesota Power’s attorney of each and every witness, I think other than MP, but maybe MP witnesses too, in the Arrowhead transmission project hearing, circa 1999-2000. There were cries of “Hospitals will go dark without the Arrowhead project,” “We’re going to freeze in the dark in an incubator” which became “We’re going to freeze in the dark on a respirator without a job” — it was so histrionic.

The Arrowhead transmission project was project 13J of the WRAO Report, and the WIREs Report, which presented many transmission lines, but chose the Arrowhead transmission project as the “be all and end all” of transmission in the Midwest, that it would fix all the transmission problems:

The hearing went forward, 2 weeks in Minnesota, where MP got an exemption from Minnesota Power Plant siting law, and for TWO MONTHS in Wisconsin, for Round 1, then 2 weeks after the cost went way up, and another 3-5 days of hearing later when cost went up again. They got their permit, it’s up…

But in that first hearing, I did get to introduce the report that showed that the June 25, 1998, blackout was NOT caused by too little capacity, it was not caused by an unreliable transmission system. It was caused by corporate greed, transmission operators running the Prairie Island-Byron 345kV’s TCEX flow over the limit, disregarding operating guides, and disregarding requests and demands to ramp the power down, violating MAPP Operating Standards and NERC Operating Policies. SHAME, NSP, SHAME!!! And MP was so tacky, trying to attribute their desire for bulk power transfer to the blackout, that the Arrowhead project would save us. Yeah, right…

Here’s the report, below, it’s a gem, I’m posting this today because I’m shoveling off my desk and there are a lot of gems here, so posting them will get them out into the world in perpetuity — can’t disappear something from the internet! Scanning them in is taking a while, a royal and dusty pain in the patoot, but just for you inquiring minds, HERE IT IS:

Here are a couple snippets, starting with p. 2:

Bottom line?

OPERATE WITHIN OPERATING GUIDE LIMITS!!

DOH!

The report goes on and on with stupid human tricks – the flow was NOT reduced by NSP System Operators:

From pps 10-11:

So if the operators had been doing the job, not focused on keeping that line operating with all that power flowing through it, selling that power, the blackout may not have happened. Great…

And for some reason, NSP operators were not communicating:

300 MW above the operating guide limits:

OPERATE WITHIN OPERATING GUIDE LIMITS!! DOH!

Operator error is a too-generous way to put it — but for the efforts to NOT reduce power flows, the inadequate response of system operators and their failure to communicate the degree of the problem, the blackout may not have happened. And then utilities have the nerve to say that because of the June 25, 1998 blackout, we need the 13j Arrowhead transmission project?