Xcel Energy, or Northern States Power, whichever, has filed its brief in the Routing docket for the Hiawatha Transmission Project.

Xcel/NSP Post-Hearing Brief

Xcel/NSP Proposed Findings of Fact, Conclusions

Also filed is Notice that the transcripts are now available at local libraries, a big help because the cost is prohibitive, they’re not free here as they are in WI or available via FOIA as they are in New Jersey (called OPRA there):

Notice – Transcripts are in the libraries

Which states:

I write to advise that the transcripts for the evidentiary hearings held in the Hiawatha Transmission Project routing proceeding on April 12 – 21 and April 26 – 30, 2010, have been placed in the following libraries: East Lake Library, Hosmer Library, Franklin Library, Central Library, and Roosevelt Library. We have also provided an extra copy to the Central Library with a request that it forward it to the Nokomis Branch once renovations are complete. The transmittal documents are enclosed.

So those of you writing briefs now know where to go!!!!

STL in the news!

June 12th, 2010

stopthelines_sign3

Stop The Lines! has appealed the New Jersey Board of Public Utilities’ determination on the Susquehanna-Roseland transmission line, I’ve been representing them in this fracas, and from the news reports below, it looks like we’ve hit all the bases!

The Susquehanna-Roseland transmission line is absurd — they’re tearing down an existing low capacity line and putting up towers twice as high with … well… imagine this, QUAD bundled 500 kV line.  Really… that is what they applied for, but midway through the hearing, they admitted that the structures couldn’t handle that and reduced it to TRI-bundled 500kV.  ACSR at that, could it be more primitive?  It’s absurd, if they 190 foot towers fell, with a 75 foot Right of Way, that’s 115 feet that it could extend beyond the Right of Way.  It’s beyond absurd — it’s insane, and earth to mars, there are people right there, RIGHT THERE, don’t they care?

susquehanna-roseland

Plus it’s not needed, the Marketing Analytics report says it all:

Marketing Analytics – PJM 2009 State of the Market Report

Here’s the BPU order that we’ve challenged:

NJ BPU Order – April 21, 2010

This is from the Pocono Record — be sure to click on the linkedarticle below to get to the Pocono Record comment section:

Power line fight heads to NJ court

By Wayne Witkowski

For the Pocono Record
June 11, 2010

New Jersey activists fighting proposed increases in the voltage and tower height of the Roseland-to-Susquehanna power lines are taking their battle to appeals court.

Four environmental groups and one onf the two private organizations made up of concerned homeowners filed court papers this week against the state’s Board of Public Utilities and utility company PSE&G. The papers charge that BPU, which approved the plan unanimously without comment in February, did not exercise due diligence in properly reviewing the proposal.

Stop the Lines, based in Fredon, N.J., has filed suit. It is one of two active private organizaitions in New Jersey opposing the project, along with the recently established Save the Park group in Hardwick Township, N.J., which has a sign advertising its cause on Hollow Road in Smithfield Township.

The suit contends the review lacked a proper analysis of the need for the project, failed to consider the environmental impacts of construction or weigh the secondary impacts of importing coal energy from Pennsylvania.

The existing 47-mile link of the 145-mile route, which extends through the Delaware Water Gap National Recreation Area and specifically through Saw Creek Estates in Lehman Township, would add 500,000 kilovolts and raise towers to 195 feet. It is under the auspices of the PJM Interconnection, which includes PPL on the Pennsylvania side and PSE&G, which is looking to recoup $3 billion in costs stemming from the deregulation of the energy sector in New Jersey.

The project still awaits approval by the National Park Service. New Jersey Sen. Bob Menendez recently sent a letter to park Superintendent John Donahue asking him and the National Park Service to exercise due diligence in its decision, which is due in 2012.

PSE&G spokesman Karen Johnson defended BPU’s decision, saying PSE&G is aware of the appeal and believes there is “ample evidence” to support its decision.

And from the Daily Record:

Morris area citizens group sues over power line plan


BY COLLEEN O’DEA • STAFF WRITER • June 10, 2010

The citizens group Stop The Lines has filed an appeal challenging the state Board of Public Utilities’ approval of Public Service Electric and Gas Co.’s transmission line expansion through Morris, Sussex and Warren counties.

Stop The Lines’ appeal of the BPU’s January decision permitting the upgrade on PSE&G’s Susquehanna-Roseland power line is the second filed in appellate court in the last week. Four environmental groups that like Stop The Lines also had intervened in the proceedings filed an appeal last Friday.

The Stop the Lines appeal will focus on the lack of need for the expanded transmission line, which would add 500-kilovolt lines to towers as high as 195 feet along the 47 miles in New Jersey. The group also faults the BPU’s refusal to consider information on a possible decreased demand, health and safety impacts on landowners, residents and the environment and economic impacts ranging from loss of property value and tax revenue to inability of homeowners to obtain mortgages.

“Building 195-foot high towers within a 150-foot wide right-of-way is simply unreasonable,” said David Slaperud, a Stop The Lines trustee.

“We believe the ample evidence in the case fully supports the BPU decision that this line is needed for reliability,” said PSE&G spokeswoman Karen Johnson.

PSE&G is awaiting final environmental permits to begin working on the eastern half of the $750 million project, from Hopatcong to Roseland. It hopes to begin work this summer. The western portion, from Hopatcong to the Delaware River, has to await the completion of a National Park Service review because the line runs through the Delaware Water Gap National Recreation Area. That is expected to take until 2012.

The project was challenged in the BPU by citizen and environmental groups, several municipalities and the Montville School District. Ratepayers would foot the bill.

The line crosses from Pennsylvania at the Delaware Water Gap and proceeds through Warren and Sussex Counties. More than half the line would traverse Morris County, through Jefferson, Rockaway Township, Kinnelon, Boonton Township, Montville, Parsippany and East Hanover before ending in Roseland.

And in the New Jersey Herald:

Activists appeal state’s power line approval


FREDON — The most outspoken local opponent of the Susquehanna-Roseland power line is appealing its state approval in the court system.

Stop the Lines, the activist group that has been the most vocal and omnipresent adversary to the PSE&G line since its proposal in 2008, is appealing the Board of Public Utilities approval issued in February.

The appeal focuses on the need of the 500kV line, running 146 miles from the Poconos across northwestern New Jersey and into the heart of the Garden State. They will also question the economic impacts to property owners and municipalities along the line — which will double the height and triple the power of the existing 1920s-era transmission towers.

“Building 195-foot-high towers within a 150-foot wide right-of-way is simply unreasonable,” said David Slaperud, a Stop the Lines Trustee.

Four state environmental groups also appealed the BPU decision by the June 7
deadline.

PSE&G has maintained brownouts could roll down the line as early as 2012 if the upgrade is not complete. However, the National Park Service blessing to cross the Delaware Water Gap will not be available until that year — and PSE&G put off seeking final environmental permits for the 20-mile Sussex County stretch of the line last month.

susquehanna-roseland

It was one of those weeks.   First CapX 2020 provides official notice that the Brookings-Hampton transmission line is delayed.  [Motion to Suspend Proceedings!]

Hot in the heels of CapX 2020’s notice of “delay” of the Brookings-Hampton transmission line, PSEG provides official notice that it is withdrawing their NJ DEP permit for the Susquehanna-Roseland transmission line:

Please take notice in accordance with N.J.A.C. 7:A12.6(f). Public Service Electric and Gas Company (PSE&G) is hereby amending the above-referenced permit applications submitted to the New Jersey Department of Environmental Protection (NJDEP). PSE&G is withdrawing the applications for the section of the Project located to the west of the proposed Hopatcong Switching Station. The municipalities west of the Hopatcong Switching Station include Sparta Township, Byram Township, Andover Township, the Town of Newton, Fredon Township, Stillwater Township and Hardwick Township The company may resubmit a new application or applications to NJDEP for the western section of the Project at a later date.

It’s all here in their Notice to affected towns:

PSEG’s Notice of Withdrawal – NJ DEP

And here’s the real deal:

PSEG Amended NJ DEP Permit filed 5/14/10

The funniest part is this — AS IF!!!

hurlingagain

We know that they’ve got a problem at the Delaware Water Gap… we know they’ve got a problem at the NJ DEP… Now I wonder… how much of the Pennsylvania part is withdrawn???

Just like the CapX 2020 transmission project, the Susquehanna-Roseland transmission project was approved as a whole, the studies used to justify it were on the project as a whole, the BPU decision approving the project was on the project as a whole… so what, now they can say they just don’t need that part???  I don’t think so…

mapptransmissionoverview

The MAPP line, PEPCO’s Mid-Atlantic Power Pathway transmission line project through Maryland and Delaware, is in the news again. But why???  Where the line is not needed, and it’s withdrawn by PJM and PEPCO, why is this being accepted?  Why is this regarded as a “win?”

Remember that they pulled the project?

PEPCO letter 1.8.09 to suspend MAPP, includes 1.8.09 letter from PJM’s Herling

And before that, the part from Indian River to Salem was eliminated?

MAPP – PEPCO-PJM Press Release May 19, 2009

The May, 2009, Press Release says:

According to Gausman, PJM has also reviewed the need for the section of the line that would run from Delmarva Power’s Indian River substation near Millsboro, Del., to Salem, N.J., and has decided to move this portion of the line into its “continuing study” category. This means that the reconfigured MAPP line will now extend approximately 150 miles from northern Virginia, across southern Maryland and the Chesapeake Bay, and terminate at Indian River. The change would likely reduce the total project cost from $1.4 billion to $1.2 billion.

And then there’s the report that shows there’s no need, that demand is downdowndown, that “congestion” is downdowndown, that price of electricity is downdowndown, that demonstrates that the market concept that they’re all drooling over will have them aspirating their aspirations:

Marketing Analytics – PJM State of the Market Report 2009

So then why did they send out a press release last week:

PEPCO May 5, 2010 Press Release – MAPP Transmission Line

…which every Peninsula news outlet gave pretty much verbatim coverage?

And then there’s the PJM RTEP 2009, released February 26, 2010.

So here’s how their press release looks after the papers get it:

Delaware utilities: Plan takes power line under Choptank


Proposed route would lead to little disruption in Del.

By AARON NATHANS • The News Journal • May 8, 2010

Delmarva Power’s planned high-voltage power line would be submerged below the Choptank River through Dorchester County, Md., the utility announced this week.

The Mid-Atlantic Power Pathway would run from Virginia to Maryland, across the Chesapeake Bay and end at the Indian River Power Plant in Millsboro.

It is being planned by Pepco Holdings Inc., parent company of Delmarva.

The company reports it has been successful in acquiring 90 percent or more of the rights of way needed to build the line through Dorchester County.

This portion of the line would run below the Choptank River, making landfall east of Cambridge, Md. It would continue underground briefly before moving above ground northeast of U.S. 50. It would cross the Nanticoke River near Vienna, Md.

In Delaware, the power line would be built on existing rights of way, approaching from Mardela Springs, Md., moving toward Delmar, and finishing in Millsboro.

Delmarva would not need to widen existing rights of way or clear any vegetation in Delaware, spokesman Matt Likovich said. The existing poles along this route would be replaced to support the more powerful lines, he said.

The portion of the line that runs through Maryland requires approval from federal and state agencies, including the Maryland Public Service Commission. Delaware’s PSC has no such oversight authority.

“We’ve spent a great deal of time listening to the citizens of Dorchester County,” said Bob Jubic, project manager. “With input from landowners, residents, environmental groups and government officials, we believe that the Choptank Route is the best choice as it minimizes the impact on the environment, agriculture and culturally significant areas in the county.”

Pepco Holdings has already announced the route for the MAPP project on the other side of Chesapeake Bay. About 20 of the 72 miles there would need to have new structures installed, and would also need new structures to cross the Potomac and Patuxent rivers.

PSC approval is unlikely to come until PJM Interconnection, the regional power grid manager, decides next month whether new power lines will be needed to ensure electric reliability in the region. Delmarva officials say they are not waiting for that green light to plan for the line, which they hope to have in service in June 2014.

Delaware PSC Chairwoman Arnetta McRae wrote a letter to PJM last month expressing the commission’s opinion that the project should go ahead on schedule to relieve reliability and cost concerns, and to provide a future pathway for offshore wind power to flow through the area.

Maps of the route through Dorchester County will be on public display at the Holiday Inn Express in Cambridge, Md., on Wednesday from 4 to 8 p.m. during an information session with the company. For more information, call the MAPP office at (410) 221-6207 or visit www.powerpathway.com.

Now read the other “articles” and tell me if there’s an echo in the room:

Underwater power line route suggested
Proposal under Chesapeake avoids refuge

By Calum McKinney • Staff Writer • May 6, 2010

But the day before it was better, with some original quotes:

Delmarva Power proposes Choptank route for MAPP project

(with NO byline)

delawarewatergap

Imagine 190 foot transmission towers through the Delaware Water Gap, between Pennsylvania and New Jersey.

That’s what’s proposed by PSE&G for its Susquehanna-Roseland transmission line.  This quad/tri bundled 500kV line is HUGE, ugly beyond belief, and it’s just so big that I can hardly comprehend, there’s nothing that large that I’ve found.  Others like it are being cancelled by PJM due to lack of demand, and this one should be too…

From the Pocono Record:

Park Service report on power line plan released

Anyway, the National Park Service is doing an Environmental Impact Statement, and leading up to that is “scoping,” which, as Grant Stevenson noted yesterday at the Task Force meeting, is THE most misunderstood term.  I agree.  It just zooms over people’s heads, and comments end up being of the “I hate this project because___” and nothing that relates to what the scope of the environmental review should be.  Utter waste of time, and something to be mindful of with the CapX 2020 transmission scoping meetings coming up.

SCOPE: Range, area of coverage, breadth

So “scoping” in this sense is the range, area of coverage, and breadth of environmental review.

We had comments on the scope a few months ago, and there were something like 6,500 comments.  Yes, that’s right, SIX THOUSAND FIVE HUNDRED!  At the meetings I went to, it was standing room only and the comments were notably on point, they were profound examples of those rare uplifting meetings.  Facilitation of the meetings was so good it felt like they really were interested in what we had to say.  It was all taken down by a court reporter.  THAT level of attention and appreciation is SO rare… and dig this … afterwards I RECEIVED A THANK YOU NOTE FOR PARTICIPATING.  That is a first, I’ve never gotten a thank you note from an agency for showing up and speaking out.  I’m thinking of framing it (after sending it to MN’s Dept. of Commerce).

NATIONAL PARK SERVICE – SUSQUEHANNA-ROSELAND 500kV TRANSMISSION LINE PAGE

Here’s their report:

Public Scoping Report – Susquehanna-Roseland transmission

The next step?

The NPS is currently developing preliminary alternatives for the project. Our plan is to host public meetings to present and receive feedback on these preliminary alternatives this summer. Announcements and news releases will be prepared to inform and invite the public to these meetings.

We’ll keep you posted.