Did I hear that right???

I’m fighting with PSEG out in New Jersey, representing Stop the Lines on the Susquehanna Roseland transmission line.  PSEG can be vile… but on this one point, PSEG’s Ralph Izzo is right. Now, if we can just get him to be consistent.

Transmission is not rocket science, and Izzo statements reflect that he understands what Midwest transmission is all about — $$$ and coal.  He and PSEG have joined the many who are standing up to Midwest transmission plans.  Now, is the Midwest paying attention?  As PUC Chair Boyd said at the last Legislative Energy Commission meeting, they need a solid business plan.  Guess what — they don’t have one, DUH!!!!  There’s no market (Doesn’t Chair Boyd or anyone else in the room think there’s something a little too cozy about Boyd advocating for transmission with MISO???).

Today at a conference, PSEG’s Izzo let loose and let them have it:

Izzo also outlines his opposition to transmission superhighway proposal. “A subsidized national build out of transmission is economically unjustified and, since it will be utilized significantly to also transport energy from coal plants, environmentally self-defeating,” said Izzo. “While purporting to help move green energy, the new lines would more often be moving electricity from coal plants to new markets in the East.”

Here’s some propaganda from PSEG:

FULL TEXT OF IZZO’S SPEECH

The Role of Transmission in a Clean Energy Economy

In short:

A national transmission build-out would cause more expensive projects to be built, enable coal plants to run more often, and hurt local efforts to promote renewable generation.  It also would create a new national bureaucracy and have a chilling effect on the development of new renewable projects while transmission routes are planned and built.

Now just who does this sound like?!?!?!?! Hilarious… dig this, though he’s not admitting the INTENTIONALITY of the transmission scam:

This physical reality results in an unintended consequence of building large superhighways of transmission lines that go far beyond delivering green power to the grid. It will provide access not just to renewable resources, but to all power plants in the surrounding region where the lines are built. For the Midwest Independent System Operator (MISO) market region, which currently generates more than 75 percent of its power from coal, coal plants also will gain new, additional access to eastern markets and higher prices. So, instead of Midwest renewable energy competing against Midwest coal-fueled electricity, both coal and green energy will travel along these new lines to more easterly markets and replace eastern renewables and eastern power generated with cleaner, but more expensive, natural gas, which is more prominent in the East. Greenhouse gas emission reduction targets will be more difficult to achieve, and it will put upward pressure on emission prices.

And this broad view so contradicts their Susquehanna-Roseland transmission plan, which is all about coal from Amos = it’s the NE part of “Line 1” in Project Mountaineer.  PSEG, you can’t have it both ways!  Let us hope that now that he’s spouting opposition to the Great Midwestern Transmission Scam he’ll see the scam of New Jersey transmission.  At least we’ll now have this to use.  THANK YOU, RALPH IZZO!

projectmountaineermap

Big Stone II is zu ende???

September 11th, 2009

bigstoneiiproject

Otter Tail Power has withdrawn from Big Stone II.  Odd way to put it because Big Stone II IS Otter Tail Power.  OTP was the big one left in the game and now they’re gone.

Otter Tail Power has withdrawn from the Big Stone II coal plant.  Really?!?!?

Pinch me, I must be dreaming…

Here’s their post about it on their BSII site – love the euphemisims:

Big Stone II announces participant changes

Otter Tail Power Company withdraws; Project pursues new participants

(Fargo, ND – September 11, 2009)—The participating utilities announced today the withdrawal of Otter Tail Power Company from the Big Stone II Project, a planned 500-to-600-megawatt coal-fired power plant located near Milbank, South Dakota, and its associated transmission. The remaining participants emphasized that Big Stone II will go forward if sufficient participants can be found to join the project.

Tom Heller, CEO of Missouri River Energy Services, which has the project’s largest share, stated that Big Stone II is still the least-cost, environmentally sound baseload power plant for the remaining project participants. “Big Stone II is a fully permitted project that will provide participants’ customers with least-cost generation for decades. It will improve the emissions profile of the existing Big Stone Plant, and the transmission facilities will be sized to serve the region’s burgeoning wind energy development,” he said.

While Heller conveyed the project’s regret that Otter Tail had to withdraw, he said other potential new participants have expressed interest in joining the project and exploratory discussions are underway.

The current Big Stone II Project participants are Central Minnesota Municipal Power Agency, Heartland Consumers Power District, Missouri River Energy Services and Montana-Dakota Utilities Co.

In the first blurb to come over the wire, below, there’s one phrase that stands out:

have resulted in challenging credit
and equity markets that make proceeding with Big Stone II at this time
untenable for Otter Tail’s customers and shareholders.

I knew that financing was not happening and dependent on a big cash infusion from Bill Gates. Financing anything now is pert near impossible, hence the big cost allocation dust up for CapX lately, and Big Stone II was no exception.  Who on earth, who in their right mind, would invest in a coal plant today?  That falls squarely in the “HOW STUPID CAN WE BE” category, no doubt about it.

Ill post more as it turns up.  From Marketwatch:

Otter Tail Power Company Announces Withdrawal From Big Stone II

FERGUS
FALLS, Minn., Sep 11, 2009 (GlobeNewswire via COMTEX) — Otter Tail
Power Company today announced its withdrawal — both as a participating
utility and as the project’s lead developer — from Big Stone II, a
500-to-600-megawatt coal-fired power plant proposed for near Milbank,
South Dakota, with related transmission upgrades in South Dakota and
Minnesota.

According
to Otter Tail Power Company President and CEO Chuck MacFarlane, the
broad economic downturn coupled with a high level of uncertainty
associated with proposed federal climate legislation and existing
federal environmental regulation have resulted in challenging credit
and equity markets that make proceeding with Big Stone II at this time
untenable for Otter Tail’s customers and shareholders.

MacFarlane
explained that Big Stone II contractual agreements require a commitment
to proceed after the project receives all major permits, creating a
financial obligation on each party that agrees to go forward. “Each Big
Stone II participant is in a different position in terms of means and
impact of raising capital and mechanisms for recovering those costs
from customers,” he said. “Given the legislative and regulatory
uncertainties and current economic conditions, Otter Tail Power Company
is unwilling to create a binding financial obligation of approximately
$400 million for its share of the project at this time.”

Big
Stone II had been scheduled to be on line in 2011, and now the plant
would not begin operating until late 2015 at the earliest. MacFarlane
said that the company no longer could delay the project to obtain
greater clarity on — and to mitigate — risks unique to Otter Tail.
Accordingly, Otter Tail chose to withdraw and allow the others to
proceed. “We believe the project is important for the region, both in
terms of adding baseload power and enhancing regional reliability,”
MacFarlane said.

While
Otter Tail Power Company has invested more than $300 million in wind
energy generation during the last three years, MacFarlane added that
dispatchable generation remains an important need for Otter Tail Power
Company’s customers. As a result, over the next three to six months,
Otter Tail Power Company will continue to evaluate other options to
meet its customers’ need for reliable electricity.

MacFarlane
also expressed his company’s gratitude for the backing shown for the
project. “Our company appreciates the support that customers,
regulators, labor, business leaders, and political leadership have
shown the project. We especially thank South Dakota elected officials
and communities within the plant’s vicinity for their commitment,” he
said.

dealwithdevil

Wind on the Wires” and AWEA are whining and crying in the press about unfair treatment to wind generators.   They do a deal with the devil to promote transmission and now are getting screwed — sorry, I won’t be hosting a pity party here!

AWEA PRESS RELEASE HERE.

AWEA and WOW’s FERC filing to protest MISO cost allocation proposal

To look at the full FERC docket, GO HERE TO FERC SEARCH PAGE, and search for docket ER09-1431.

“Wind on the Wires” is a subset of the Izaak Walton League – Midwest, not a separate organization.  Some background here:

Years ago, the Midwest Izaak Walton League, together with MCEA, ME3 (Fresh Energy) and North American Water Office, did a deal with Xcel, and a massive “Wind on the Wires” grant was announced a couple of days later.  The deal was to support a massive transmission buildout, specifically, to work to change state and federal law; to support transmission projects; to usher them through the legislature, state and federal administrative venues, to support at industry transmission planning groups; to support changes in rate recovery; to support changes in transmission need and siting criteria; and to allow transmission-only companies, all the things that Xcel wanted to roll out CapX 2020, JCSP, and whatever else is in their dreams.

Really… it’s all here:

Settlement Agreement – ME3, Waltons, MCEA, NAWO

$8.1 Million Wind on Wires grant from McKnight/Energy Foundation

Waltons 2007 Form 990, shows Beth Soholt, WOW Director & Matt Schuerger, Energy Systems Consulting, p. 19

This 2003 Settlement Agreement was in the Minnesota PUC’s TRANSLink docket, where Xcel wanted a transmission only company, not yet allowed in Minnesota.  For the docket, go to www.puc.state.mn.us and then click on “eDockets” and search for docket 02-2152.  F”or the resulting legislation, some of it, see 2005 Transmission Omnibus Bill from Hell.

So they jump through all those hoops and where are they?  What happens?

gettingscrewed

Back to Cost Allocation of Transmission.

Let’s see… there was one cost allocation scheme,  50-50 split between owner utilities and generators connecting.  Otter Tail Power objected and so the utilities changed it to a 90-10 split, and now “Wind on the Wires” and AWEA are screaming, whining and crying saying it has to go back.  This has to do with how the utilities characterize the purpose of the line, be it for “Reliability” or “Generation Interconnection” and how costs are apportioned are different.  In the CapX proceeding, the “Brookings line” was not declared, and the Fargo and LaCrosse lines were deemed “Reliability” but that’s absurd…

CapX’s Grover – Direct Testimony

CapX Application- Appendix D-5 – Cost Allocation

For “Baseline Reliability” projects here’s the cost allocation scheme:

baselinereliability

For “Generation Interconnection” here’s the cost allocation scheme:

generationinterconnectioncostallocation

Ummmmm…  a little more background here now that we’re talking about interconnection… does anyone remember the name of that coal plant that Otter Tail Power just got permitted to build?  Oh, yeah, right, it’s BIG STONE II.   And what was the name of that big honkin’ coal plant that “suddenly decided” to produce electricity rather than syngas?  South Heart, yeah, that’s it.   See “South Heart coal gasification — Coal on the Wires.” Both plants strategically placed to use CapX 2020 transmission.  So what is the impact of this shift to Otter Tail Power and their Big Stone II project?

Here’s the Big Stone electrical link to CapX — it’s all connected:

sw-mn-its-not-for-wind-map

Here’s new connector ND transmission announced April 3 — it’s all connected:

capxphaseii-map-corridorupgrade-res-projects-2-246x300

And of course, the big picture of CapX 2020 – click on it for a bigger picture to really appreciate those lines starting in the Dakotas:

capx2020-powerpoint-p-7-big-picture-map.jpg

Here’s an article from last week about their objections:

Wind industry protesting plan to pay for new lines

Cost-sharing proposal decried as threat to renewable energy goals


By Leslie Brooks Suzukamo
lsuzukamo@pioneerpress.com
Updated: 08/14/2009 12:01:26 PM CDT

The emerging wind industry in Minnesota and the Upper Midwest could be shut down by the cost of connecting to high-voltage transmission lines if a proposal by the organization that controls the Midwest’s power grid goes through, wind advocates say.

The grid operator and some utilities say the wind industry is overstating the effect, but the long-simmering dispute over who should pay for new transmission lines boiled over Thursday.

If the matter can’t be resolved, the wind industry insists, Minnesota’s renewable energy goals would be at risk.

The Midwest Independent Transmission System Operator, which covers 13 states and Manitoba, Canada, last month proposed changing the way costs are shared for new transmission lines. It wants to put 90 percent of the cost on energy generators, including the wind farms springing up across the Dakotas and southwestern Minnesota.

Previously, the cost has been split 50-50 between energy generators and transmission-line owners, typically utilities.

However, Otter Tail Power of Fergus Falls told the grid operator, known as MISO, recently that unless the sharing agreement is changed, Otter Tail would pull out of the system.

Wind farms in the Dakotas representing a total of 10,000 megawatts of electricity — a significant chunk of the power waiting to be added to the grid — wanted to connect to Otter Tail’s grid to reach Minnesota and the rest of the transmission system operator’s territory, said JoAnn Thompson,

Otter Tail’s manager of federal regulatory compliance and policy. Otter Tail consumers were going to have to pay half the cost of the new transmission, even though they would use almost none of that power, as it would be transmitted onward, she said.

“We support developing renewable energy but not at a substantially disproportionate impact to consumers,” she said.

The new cost-sharing proposal, which was submitted to the Federal Energy Regulatory Commission for approval, would increase the cost of developing wind energy projects so much they would no longer be economical, wind energy advocates said Thursday.

The American Wind Energy Association in Washington, D.C., and Wind on the Wires, a St. Paul-based industry association, filed a protest Thursday with the energy regulatory commission opposing the proposal.

“If (the transmission system operator) loads up the cost (of new transmission) on the generators, we won’t get new transmission built,” said Beth Soholt, executive director of Wind on the Wires.

“So unless we get the cost of new transmission spread out more evenly in the MISO footprint, wind-energy development is going to come to a screeching halt.”

The changes also could throttle efforts to export wind energy from the Upper Midwest to the rest of the country, the American Wind Energy Association added.

The Upper Midwest has been dubbed “the Saudi Arabia of wind” because of the region’s gusty conditions, but unless big and expensive transmission lines are built, there is no way to get that power from the scores of wind-energy projects proposed for the isolated prairie to energy-hungry metro areas like the Twin Cities, Chicago and points east, American Wind Energy Association analyst Michael Groggin said.

But Xcel Energy, which must generate 30 percent of its electricity from renewable energy by 2025, says the impact will be temporary. Xcel on Thursday asked the Federal Energy Regulatory Commission to require MISO to propose an alternative plan by April 1 next year, to be effective July 1, said Kent Larson, Xcel’s vice president of transmission.

MISO said it requested the shift in cost sharing to keep Otter Tail from bolting from the organization, which is voluntary. If Otter Tail pulled out, the wind farms in the Dakotas would have to pay higher rates to use Otter Tail’s lines as a bridge to the big cities anyway, said Clair Moeller, MISO vice president of transmission asset management.

A proposal by American Wind Energy Association and Wind on the Wires to spread the cost of new transmission to all MISO members would have caused utilities in the eastern part of the territory with no renewable-energy requirements to leave, Moeller added.

If members left MISO, the system of using the organization as a market to buy the cheapest electricity on the system would fall apart and rates would go up, Moeller said.

“So we were on the horns of a dilemma,” he said.

So if “Wind on the Wires” and AWEA object to “generator pays” transmission, where it’s the generator causing the need, then they’re now in essence advocating for a different scheme for Big Stone II and South Heart coal plants too.  Oh, good idea…

Here’s another one that turned up — WOW and AWEA sent out a raft of press releasees

Wind Industry Fights Midwest Transmission Proposal to Stay Alive

by Stacy Feldman – Aug 17th, 2009

The burgeoning wind industry in America’s Upper Midwest could be at risk of shutting down if a new transmission policy by a local grid operator goes through, according to a pair of wind advocacy groups.

Even worse — the plan could put the nation’s renewable energy goals in jeopardy.

The American Wind Energy Association (AWEA) and Wind on the Wires (WOW) have filed a protest with the Federal Energy Regulatory Commission (FERC) to stop a proposal by the Midwest Independent Transmission System Operator (MISO) — one that would dramatically change the way costs are distributed for new transmission lines.

Specifically, the plan would force energy generators to bear a 90 percent share of new transmission costs in the region, wind farm developers included.

Currently, generators and utilities split the price paid, 50-50.

For the wind industry, that would be seen as a shame. Current plans for regional wind are grand. Developers want to build a wave of utility-scale wind farms, and get the ones that have already sprouted plugged in. In fact, a decent chunk of the power waiting to be added to the grid in the Midwest is wind.

But if FERC approves the proposal by MISO, which covers 13 states, those megawatts may have to keep on waiting. Here’s why:

“The proposed change would nearly double the cost for a wind plant to connect to the power system in the Upper Midwest, potentially forcing many wind plant developers to pull the plug on tens of billions of dollars of investment they have planned for the region,” said AWEA in a statement.

Simply put, wind would no longer be economical under the MISO scheme, and some projects that are waiting in the wings would be killed.

Without the planned turbines, states in the Upper Midwest, which include Minnesota, Wisconsin, Illinois, Indiana, and the Dakotas, may struggle to meet their renewable energy goals and mandates, the AWEA says. America as a whole would be hard-pressed to reach the White House ambition of doubling the nation’s supply of renewable energy in the next three years sans the Upper Midwest, known as the “Saudi Arabia of wind.”

As AWEA and WOW see it, the MISO policy is “unworkable” for the wind sector because of this fact. It assigns nearly all of the costs of upgrading the grid to the next wind plant waiting in line to connect to it. It’s akin to

“requiring the next car entering a congested highway to pay the full cost of adding a new lane,” said WOW Director Beth Soholt.

The Upper Midwest isn’t alone on this issue. Transmission has become the major tripwire to America’s green-powered future.

One of the biggest hang-ups is over a cross-country transmission superhighway that would zap electricity from America’s midsection to the urban areas that need it. The plan carries a massive, multi-billion dollar price tag. Those in favor say it would move the nation toward a clean renewable energy future. Those against see it as a total waste of cash, a covert attempt to serve some of the dirtiest coal plants, giving them access to new markets through transmission.

And then there’s the big issue of cost: Who would pay for it?

The MISO proposal is a local version of that long-simmering cost dispute.

What’s clear is that loading up the costs on generators could price many wind farm plans out of existence. There’s also the issue of costs to electricity consumers. The price hike to generators that a shift to MISO’s cost sharing would bring would be passed onto certain Midwestern consumers. They’ll end up paying more for the transmission of wind, and may not even benefit, if it gets sent to neighboring states. That could stymie public support for new wind energy.

AWEA and WOW have an alternative vision — to more broadly distribute transmission-line investments “in a way that matches the broadly distributed benefits of building a stronger grid, such as improved reliability and reduced power prices.”

But MISO’s rationale for its policy suggests something else entirely — that wind shouldn’t be the only game in town in the Upper Midwest.

“We continue to focus on addressing the challenges of integrating large quantities of wind through ongoing work with our stakeholders and state officials. This work includes developing long-term transmission plans, cost allocation strategies and other market solutions that preserve and enhance the ability of all resources, including wind, to integrate and operate efficiently.”

FERC has not indicated whether it favors MISO’s proposal or would recommend changes.

In a ruling in June on the Southwest Power Pool (SPP), the agency sided with the wind industry, deciding to more broadly and fairly spread the cost of building new transmission to all users of the SPP electric grid.

SPP serves Kansas, and parts of New Mexico, Texas, Oklahoma, Arkansas, and Louisiana, Missouri and Nebraska. In response to the decision, AWEA was hopeful for future transmission rulings:

“We hope other regions and the federal government will follow their lead and institute similar reforms so that we can begin to put the world-class wind resources that are currently stranded in rural parts of this country to use.”

hibbing-biomass

Really, that’s what they said at a meeting where the operators of the Hibbing “biomass” plant were confronted with all the problems, dust, noise, neighbors fed up and bringing in the evidence.  This is the plant that was violating its air permit and was fined and shut down,
but of course air permit limits were INCREASED and it reopened.
GRRRRRRRRRR.  And when they were told to clean it up, given a deadline, they said:

“I think we need to sit down and prioritize these things and get our butts going,” said Fena.  “We should be able to tackle some of these issues, like some of the noise, right away. If we can’t, we  should be shot.”

Thanks to Charlotte Neigh for sending this in.  Let’s keep an eye on this one!  Ready… aim…

Commission vows to take action on dust, noise

Meeting draws more complaints from neighbors

by Kelly Grinsteinner
Assistant Editor

HIBBING
— Members of the Hibbing Public Utilities Commission (PUC) will have
just more than one month to devise a game plan on how to be better
neighbors.

The commission will hold another public forum, as it
did Monday evening, to address concerns raised by its neighbors about
fugitive dust and noise coming from the facility. The meeting will be
held at 6 p.m. Tuesday, July 14.

“We may not have a resolution,
but we will have a plan of attack,” Jim Fena, the commission’s newest
member, promised the room of more than 30 frustrated nearby residents.
“It will be top priority. We need to make progress on this, and do more
than give lip service.”

In the meanwhile, some analysis will be conducted on the fugitive dust
wiped up by neighbors and presented to the commission on Monday.

Kathy Nyberg handed over two black rags that were once blue. She has
used the rags to wipe her window sills.

“This can’t be healthy,” she said. “I clean. I get this. It’s in my house. I
breathe it. It’s going into my body, into my lungs. It can’t be
healthy.”

Linda Johnson said she
hoses down the swing set and scrubs the slide before she lets her
grandchildren use it. The fugitive dust and ash, she claims, has also
pitted the windshield of her vehicle and ruined the cover to her hot
tub.

Gerry Wyland showed photos — ash and coal dust on his home,
in the alley and even on his kids. The snapshot of children showed
their legs looking all muddy, but there was no mud, he noted.

“You are supposed to control this from happening,” he challenged the
commission. “You need to find a better way to suppress this.”

Mandy Gherardi spoke about how her children have endured allergies and
respiratory infections, which she feels may be attributed to the
utility’s fugitive dust and dirt.

“It’s something that’s going off in my head,” she said. “Something
needs to be done.”

Colleen Hall said she and her son suffer from asthma. They can’t hang out in
the back yard because of the fugitive dust and she is embarrassed to
entertain at home, she said.

“Everything is so filthy,” she added. “I can’t clean it. We can’t sell
it. We’re stuck.”

Several others spoke about putting new siding on their homes and making
improvements to their properties only to be discouraged when they find
soot, dust and grime everywhere.

“Are you going to help us clean?” Marianne Just asked the commission. “We all are rate payers,
but these are additional expenses out of our own pockets.”

Just gave the commission a bag of clothes filled with soot that she had
wiped from her glass table top over the period of a week.

Many neighbors agreed that the problem has compounded over the past three to
four years, which coincides with the Biomass project. HPU officials
also confirmed that the volume of coal and ash they have been burning
has nearly tripled.

Fena credited that to becoming more of an electricity-generating facility, a switch from the utility’s prior
years of producing mainly steam.

HPU is contractually obligated to produce so much electricity, be it by burning wood or coal. And the
utility is forced to burn more coal when the Biomass is down or when
wood supply is short.

“Because the process requires so much more, there will also be that much more dust and noise,” said Fena.
“We’re aware of the situation and aware of the rub. Now we have to deal
with it.”

Several neighbors talked about the noise annoyances, including the banging of gates on trucks, exhaust noise when two of the boilers run simultaneously and about a safety valve popping on and off
at night.

Bob VonAlman said the noise is so distracting that he can barely hold a conversation in his backyard. Jason Johnson said he hears trucks jake braking at unreasonable hours of the morning.

Linda Johnson imitated the irritating noise she hears coming from the plant.

“It’s sad when you wake up dreaming of WD-40,” she said.

HPU General Manager Jason Fisher outlined the steps the HPU has taken to
cut down on fugitive dust since December. Those efforts have included
installing belt cleaners on wood handling belts, enclosing one side of
the coal storage hut and installing spray nozzles on the coal-ash
handling system to wet the ash during unloading. He also said they
currently have a cost estimate for a hood for the receiving area.

In terms of noise, the utility has installed cameras to monitor trucks
unloading at the HPU to ensure drivers are doing their part to cut down
on noise. Fisher said that “has gotten better.”

The utility has also “made some corrections” to the safety valve on the wood boiler to
help alleviate that “gun shot sounds,” according to Fisher. They also
have a cost estimate for a baffle system for the stack of the combined
boilers.

Chair John Berklich and Commissioner Gary Kleffman
commented on how surprised they were to hear so many, including some
new, complaints.

“I wish we would have known this to be able take some action,” said
Kleffman. “…We have a lot of work ahead of us.”

Residents were encouraged to call the utility when the noises happen and when
they have complaints. In contrast to his predecessor, Fisher was
acknowledged by the neighbors for returning their phone calls and being
responsive.

Neighbors first aired their concerns during a similar meeting that took place in mid-December. A couple of those parties had petitioned its commission at their regular meetings for
some time, but felt as though they had gone unheard.

Larry Schloesser has been vocal on the issue for some time. He’s lived across
the street for more than 30 years and said it’s never been so bad. He
advocated for building a wall about the entire facility.

“Keep yours on your side of the street, and I’ll keep to my side of the
street,” he said.

Rick Johnson has been along-side Schloesser advocating for something to be
done. He acknowledged that some things had been done, but said the big
problems aren’t fixed.

He accused Berklich and Kleffman of lip service, and asked when the commission was “going to admit this Biomass thing is a failure?”

Other suggestions offered by the neighbors included dismantling and moving Biomass, buying out homes surrounding the utility, paying to clean homes and talking with companies like Excel and Minnesota Power to relax contracts to cut back on the facility’s current capacity.

Several comments were made that HPU needs to determine whether the fugitive dust is posing a health risk, which could be more costly in the long-run if it is.

The meeting was the first time Fena was on the receiving end of the complaints.
After listening to the many grievances, he vowed that the utility would
address some of the issues immediately.

“I think we need to sit down and prioritize these things and get our butts going,” said Fena.
“We should be able to tackle some of these issues, like some of the noise, right away. If we can’t, we should be shot.”

Kelly Grinsteinner can be reached at kelly.grinsteinner@mx3.com.
To read this story and comment on it online go to www.hibbingmn.com

economist_logo

I’d wondered why “The Economist” had shown up in my blog stats, and now I know.  But from the viewpoint of this article, it’s clear they didn’t do more than scratch the surface of transmission in the Midwest.  This is “party line” all the way — I hope they’ll now take the time to read NYISO and ISO-NE’s letter of withdrawal from publication of JCSP!

YOUR TURN!  Let them know what you think and why — the registration is instantaneous and easy, so COMMENT AWAY!

Spreading green electricity: A gust of progress

Apr 30th 2009 | CHICAGO
From The Economist print edition


Creating windpower transmission in the Midwest

FRANKLIN ROOSEVELT helped bring electricity beyond America’s cities to its most distant farms. Barack Obama hopes the countryside will return the favour. Much of this challenge rests in the gusty upper Midwest. In recent years Interstates 29 and 80, highways of America’s heartland, have teemed with lorries bringing wind blades to new plants. Efforts to build transmission have moved more slowly. There are 300,000 megawatts of proposed wind projects waiting to connect to the electricity grid, says the American Wind Energy Association. Of these, 70,000 megawatts are in the upper Midwest.

Now action is at last replacing talk. Firms are proposing ambitious transmission lines across the plains. The region’s governors and regulators are mulling ways to help them. The federal government is playing its part. In February the stimulus package allotted $11 billion to modernise the grid. Since then members of Congress have proposed an array of bills to develop transmission. Jeff Bingaman, chairman of the Senate energy committee, intends to start marking up transmission plans next week—though debate over other parts of the energy bill may delay progress.

America’s grid is complex: 3,000 utilities, 500 transmission owners and 164,000 miles (264,000km) of high-voltage transmission lines are stretched across three “interconnections” in the east, west and Texas. If wind is to generate 20% of electricity by 2030, as in one scenario from the Department of Energy, about $60 billion must be spent on new transmission. Just as important, regulations must change.

Historically, electricity has been generated close to consumers. Regulations are ill-suited for transmission across state borders. Rules for allocating a project’s costs burden local ratepayers rather than distant beneficiaries. One state’s regulators can scuttle a regional plan. The process for seeking approval from federal agencies is so disjointed and slow that pushing a line over a national park or river might as well be crossing the Styx.

American Electric Power (AEP) built a transmission line from West Virginia to Virginia in two years. The approval process had taken 14. “There are lots of people with authority to make pieces of the decision,” explains Susan Tomasky, president of AEP Transmission, “and no single entity that can say ‘yes’ or ‘no’.” Despite recent changes, the Federal Energy Regulatory Commission (FERC) has limited power to make projects go faster.

Fortunately, officials have started to address these problems. In September 2008 the governors of the Dakotas, Iowa, Minnesota and Wisconsin formed an alliance to co-operate on regional planning. Midwest ISO, which supervises 94,000 miles of high-voltage lines, is considering ways to spread the costs of new transmission beyond local ratepayers and taking part in preparing a broad plan for the eastern interconnection.

Federal legislation will help too. Harry Reid, the Senate’s Democratic leader, Mr Bingaman and Byron Dorgan of North Dakota have offered three of the most prominent proposals. Each would require comprehensive plans for the interconnections, and would, to varying degrees, expand FERC’s authority to locate big new projects and allocate their costs.

Initiatives like this would help to encourage firms already eager to invest. Two of the most ambitious plans belong to AEP and to ITC Holdings, which each want to build lines from the upper Midwest to cities farther east. In April FERC offered ITC’s “Green Power Express” initial incentives to push the project along.

However, even quick progress in the world of transmission is slow. If all goes according to schedule—an unlikely thought— the Green Power Express would still not be in service until 2020. Fights in Washington are inevitable. FERC’s role in siting projects is controversial. More important, this debate may be bogged down by broader ones, such as the fight over a mandate to make a greater share of electricity from renewable sources. Meanwhile the winds whistle across the plains.