Freeborn Wind Noise Again!
November 9th, 2021
The Xcel Energy Freeborn Wind post-construction noise modeling equipment is up, this time at the tree line, not behind it.
Just filed today at the Public Utilities Commission:
Xcel Energy has 14 days to respond, and then off to the Public Utilities Commission for consideration. The Commission needs to take a hard look at what they’re doing, because these wind projects sited without rules and too close to people is harming those living in the project footprint.
Noise remains a problem for those trying to live in the middle of a wind project. No surprise when the owner uses a 0.5 ground factor to model bigger, louder turbines, several hundred feet above the ground (these have rotor diameter of 120 meters, or 393.701 feet!). This has been ongoing for so long, going on 5 years, I find I’m forgetting crucial details. But what’s happened in this docket, and what has happened in other dockets, all adds up, particularly with the Bent Tree noise exceedences demonstrated, and resulting settlements, and the Blazing Star noise issues going on right now.
Noise was a problem in Bent Tree with Vestas V-82 for the Hagens and Langruds.
Bent Tree Noise report confirms permit violations!
Wind turbine noise is a problem for the Blazing Star wind project with these bigger and louder Vestas V-120:
Blazing Star Wind NOISE!
More on Blazing Star noise
Freeborn Wind noise has long been an issue. Noise was a problem when the Freeborn Wind ALJ recommended denial of the permit because they had not demonstrated, using 0.0 ground factor, that they could comply. Yes, do not forget that we won that round, first recommendation of denial of wind permit application ever:
WE WON!!! ALJ Recommend Freeborn Permit be DENIED, or…
So then the PUC changes the rules, moves the goal posts, and allows use of 0.5 ground factor in modeling to predict noise, and don’t forget, these are now Vestas V-120 turbines, bigger and louder.
Freeborn? PUC upends ALJ’s Freeborn Wind Recommendation
Can you spell U-N-D-E-R-E-S-T-I-M-A-T-E ?? GI-GO???
Tried for an Environmental Assessment Worksheet and got the gong:
PUC Freeborn Mtg 2-6-2020
Filed a MERA claim (Minn. Stat. 116B.03) and we were booted out of court:
Association of Freeborn County Landowners v. Public Utilities Commission
And we appealed the Commission’s final decision on Freeborn:
Freeborn Wind appeal – we lose…
We are persistent. The noise numbers are too high, and they’re higher than pre-construction noise modeling predicted. Yeah, well, DOH, using the wrong ground factor.
The Commission needs to address this obvious problem and deal with the consequences. Avoidance just doesn’t cut it. This is real, and it’s not going away.