First the state court, though there’s that matter of a HUGE bond, and now federal court.

Here’s the Order:

https://fingfx.thomsonreuters.com/gfx/legaldocs/zgvomrqomvd/rulingLine.pdf

Bottom line:

Given the balance of harms implicated by the parties and the plaintiffs’ likelihood of success on the merits, a narrowly tailored motion for preliminary injunction will be granted with respect to land on or near
federal jurisdictional waters until issuance of this court’s decision on the parties’ cross-motions for summary judgment, which will be fully briefed within a day of the issuance of this order.

From REUTERS (!):

Judge delays construction on parts of $500 mln U.S. power line

Oh my, take a little time off, and look what happens!

Cardinal-Hickory Creek: Secret messages with former regulator prompt utilities to seek new permit for power line

Here are the Petitions from ITC and ATC filed Monday, June 28, 2021 at 10:00 a.m. and 10:09 a.m.:

And it’s instantly on the agenda for TOMORROW’S Commission meeting (meeting starts at 10:30 a.m.).

Listen to Live Broadcast HERE!

The “notice” was provided on Tuesday. June 29, 2021 at 3:15 p.m., not even 36 hours before the meeting (note there’s a “CS memorandum of 6/29” where Commission staff offers background and suggestions that we don’t get to see):

OBJECTION!!! Ja, you betcha, from Jewell Jinkins Intervenors and others:

What are we asking for? It’s pretty simple:

DALC and WWF filing just came in and they have a very different take:

And ATC and ITC’s scheme is getting some coverage:

Controversial transmission line through Iowa/Wisconsin suffers setback

Owners Of Controversial Power Line Project Ask To Refile Application After Messages With Regulator Surface

Routes through part of Iowa County

NEXT WEEK, LIVE AT PUBLIC SERVICE COMMISSION, starts 9:30 a.m., they’ll update link just before then:

http://apps.psc.wi.gov/vs2017/eventscalendar/broadcast/livebroadcast.aspx

Comments are due Sunday, April 14, 2019 (11:59!):

Here’s the DEIS in full:

Note the “need” section beginning on p. 49. It’s dependent on MISO — yes, that MISO, the one that blessed the so dramatically overstated “need” for the CapX 2020 build-out… the MISO that claims “need” when its LMP Coutour map is nearly always a bright or dark blue! The MISO that is all about “market” which has nothing to do with “need.” This section takes it back to “Upper Midwest Transmission Development Initiative” (hard to tell their mission, eh? But we know it was all about coal). If they’re going to go back to the history of this big transmission build-out, methinks that, particularly in Wisconsin, they should go back to the Wisconsin Reliability Assessment Organization (WRAO) Report that laid out the wish list of the transmission build-out.

Now, head to p. 80, Section 3.9, entitled “Applicants’ Alternatives to the Proposed Project.” This section presents ONLY the APPLICANTS’ alternatives, they get to determine what is or is not an alternatives, the parameters. Show me where it says in the WI statutes or rules that it only the APPLICANTS’ choice of alternatives to be considered?

Folks, we’ve got a lot of work to do…


LTE in Dodgeville Chronicle

December 8th, 2016

mvp345

See the lower 1/2 of MISO’s MVP project 5, running from near Dubuque, IA to the northeast to the “Cardinal” substation near Madison?  That’s the Cardinal – Hickory Creek transmission line.

The Dodgeville Chronicle ran my Letter to the Editor, just in time for the meeting last night, held by Rural Utilities Service, about the Cardinal – Hickory Creek transmission project:

From 4-7 p.m. on Wednesday, December 7th, the Rural Utilities Service (RUS) is hosting a scoping meeting at the Deer Valley Lodge in Barneveld. RUS will again collect scoping comments for its Environmental Impact Study as it decides on a loan to Dairyland Power Cooperative for a share of project costs. RUS held scoping meetings October 31-November 3, 2016 – why more scoping meetings now?

The Cardinal-Hickory Creek transmission project stretches from a substation near Peosta, across the Mississippi River and Wisconsin, near Dodgeville, to a substation near Madison. Last April, as reported in this paper, American Transmission Company’s Jon Callaway reported that the project schedule had been pushed out to 2018 or beyond. The reasons weren’t clear, and should be specified and made part of the RUS record.

Cardinal-Hickory Creek and the under-construction Badger-Coulee transmission lines are MISO’s (Midcontinent Independent System Operator, Inc.) MVP project “five” revealed five years ago in MISO’s MTEEP 11 report. That was 2011, and it was “postponed” in 2016. Why the delay? MISO’s 12.38% rate of return for construction has been successfully challenged in federal court. There’s a glut of electricity where even marketing electricity cross country is not alleviating the industry’s overproduction. MISO’s MVP economic modeling no longer hold under current scenarios. And maybe the delay is that and more!

Now’s the time to tell RUS to consider the economics, need and causes of delay in its financing decision. If delay is right for the project developers, RUS should also delay, and put financing on hold.

Carol A. Overland, Esq.
Red Wing, MN