Busy day for Goodhue Wind Truth
February 2nd, 2012
Yesterday was a busy day for Goodhue Wind Truth.
First was a Motion to the Appellate Court:
Goodhue Wind Truth – Motion for Intervention/Request for Participation as Amicus Curiae
Next was our Petition for Rulemaking, filed yesterday as a part of our Power Plant Siting Act Annual Hearing Comments, and formally filed with Dr. Haar at the Public Utilities Commission.
The PUC is in charge of the Wind siting rules, well, the EQB was directed by the legislature in 1995 to promulgate rules, and finally in January, 2008, the Commission finalized the siting rules for wind projects under 25 MW (and above 5 MW):
And for projects 25 MW and above, they haven’t done anything, that was 17 years ago, so here we are… do we have to get a Writ of Mandamus?
WAKE UP PUC! Time to do some wind rules!
(2) procedures that the commission will follow in acting on an application for an LWECS;
(3) procedures for notification to the public of the application and for the conduct of a public information meeting and a public hearing on the proposed LWECS;
(4) requirements for environmental review of the LWECS;
(5) conditions in the site permit for turbine type and designs; site layout and construction; and operation and maintenance of the LWECS, including the requirement to restore, to the extent possible, the area affected by construction of the LWECS to the natural conditions that existed immediately before construction of the LWECS;
(6) revocation or suspension of a site permit when violations of the permit or other requirements occur; and
(7) payment of fees for the necessary and reasonable costs of the commission in acting on a permit application and carrying out the requirements of this chapter.
Leave a Reply