Supplemental EIS for Essar Steel Plant (f/k/a MSI)
March 22nd, 2010
The DNR has announced a Supplemental EIS for the Essar Steel project (f/k/a MSI).
THREE DAYS NOTICE!
March 25, 2010 from 5:30 – 7:30 pm
Nashwauk-Keewatin High School
400 2nd Street
Nashwauk, MN, 55769
Notice published 3/22 for a meeting on 3/25?
Here’s the document that is open for comments until April 21, 2010:
From the original MSI proposal, here’s the chart of Potential To Emit from the Air Permit:
So for a 50% increase, multiply those numbers in the Potential to Emit Chart by 150%. Take a look at those numbers and ask if that’s what you’d like in your lungs and fish.
In light of the changes proposed, a few issues:
* Does Essar now or anytime during the term covered by the supplemental EIS now being considered, and the term of the air permit currently issued, intend to use any amount of coal or metallurgical coke in any part of the mining, taconite or steel production processes or for energy at the Essar Steel Minnesota, LLC Nashwauk area facility, mine(s) or waste disposal and tailings sites.
* How many tons per day of coal/coke are projected be required for the facility during full operation in July, 2013, July, 2018, and July, 2023.”
* How many peak and average megawatts of electricity are now projected to be required for the facility in each year of operation, and specifically during peak operation in July, 2013, July, 2018, and July, 2023.
* How many peak and average million cubic feet per hour of natural gas are now projected to be required for the facility during full operation in July, 2013, July, 2018, and July, 2023.
* When will MPCA put air permit amendment out for review and comment?
And now for the Essar Supplemental EIS:
Here’s their announcement from the March 22, 2010 EQB Monitor:
SUPPLEMENTAL ENVIRONMENTAL IMPACT STATEMENT
PREPARATION NOTICE
DNR will prepare a Supplemental EIS on a proposal by Essar Steel Minnesota to increase the production capacity of the Nashwauk facility’s crusher, concentrator, and taconite pellet plant from 4.1 million tons per year (mtpy) to 6.5 mtpy. This will require the addition of a crusher/concentrator line, and the installation of a larger pellet furnace, to the project evaluated in the original Minnesota Steel Project EIS.
Page 4 EQB Monitor Vol. 34, No. 6
Publication Date: March 22, 2010The SEIS is designated to deal only with impacts, alternatives, and mitigation that are no longer adequately examined in the original EIS due to the changes in the project, information, or circumstances.
The DNR proposes that the following alternatives, impacts, and issues will be examined as part of the SEIS.
Alternatives: The SEIS will address four alternatives for the increased production in taconite pellets: 1) the Proposed Alternative (Increase taconite pellet production from 4.1 mtpy to 6.5 mtpy), which was not addressed in the original EIS; 2) the No-Action Alternative, which is the original “Build or Proposed Project” Alternative evaluated in the Minnesota Steel EIS; 3) a re-evaluation of best available control technology (BACT) for criteria pollutants whose emission are estimated to increase in amounts greater than the significant increase thresholds under 40 CFR Part 52, for any proposed changes to the BACT identified in the original EIS; and 4) air emissions control technology alternatives for mercury.
Impacts and Issues: surface water quantity and quality; wild rice; solid waste generation; air quality; contribution to global greenhouse emissions; mercury; cumulative air quality: Class I PSD Pollutants, Class I Acid Deposition and Ecosystem Acidification, and Class I Visibility Impairment; cumulative mercury; cumulative effects – climate change; and socioeconomics.
Special Studies or Research: updated mine plan; updated water quantity and water quality balance; wild rice; solid wastes generation estimates and disposal options; air emissions inventory; BACT evaluation for air emissions; Class I air quality analysis; Class II air quality analysis; mercury mass balance and control technology assessment; human health screening level risk assessment; screening level ecological risk assessment; greenhouse gas emissions inventory; cumulative effects on Class I air quality – PSD pollutants; cumulative effects on Class I air quality – acid deposition and ecosystem acidification; cumulative effects on Class I air quality – visibility impairment; cumulative health risk screening assessment; cumulative mercury; cumulative effects on climate change; socioeconomic effects.
The DNR will accept written comments on the Preparation Notice during a 21-day period beginning March 22, 2010. Comments must be received by 4:30 PM on April 12, 2010. Comments may be emailed to environmentalrev@state.mn.us with “Essar Steel” in the subject line. If using the email address, please include a name and mailing address so that it can be added to the mailing list.
A public informational meeting will be held on March 25, 2010 at the Nashwauk-Keewatin High School, 400 2nd Street, Nashwauk, MN, 55769, from 5:30 – 7:30 PM.
A draft SEIS is tentatively expected to be released for public review between October to December, 2010. The contact person at the DNR is: Bill Johnson, Planning Director, 500 Lafayette Road, St. Paul, MN 55155; 651-259-5126; bill.johnson@state.mn.us.
The arrogance that is Kersten
March 21st, 2010
From the sanctuary of her $585,000 (assessed) Edina home by the country club, Kathering Kersten goes on another inciteful rant. Somebody, please, lock her up in Gitmo so she gets a feel for what it’s all about!
In today’s STrib:
I couldn’t resist:
Showing ignorance of our “legal” system in practice
Thursday night at the Elmer Grange
March 21st, 2010
It was a packed house for the Upper Pittsgrove meeting regarding the Stella Solar project, or American Green Power Holding’s solar project, or whoever, they’re one and the same, Ed Stella is VP of American Green Power Holding, and according to their SEC filing, he did an “arms length” lease agreement with himself! From which he’ll get $1.3 million annually for ~600 acres of land. … sigh… I am really in the wrong business. It’s time to put together a vaporware project!
There were so many people that they decided to hold this part of the Planning meeting at the Grange Hall, so when they were done with the first agenda item, then everybody came over to the Grange. All the chairs were filled, and there was hour after hour of good questions.
In New Jersey, towns get an escrow to hire experts to review an application, and in this case, their experts are good. Sarah Birdsall, particularly, did a good analysis. I need to get the scanner working and post it. She’s requesting that the Town require a copy of the Power Purchase Agreement — I also want to see the PJM application.
UPDATE: I’d looked at the PJM queue, but I didn’t go back far enough. It’s in the “V” queue, and per Rania, their engineer, there are five 20MW queue spots, but I found 6, plus a 3MW, in Upper Pittsgrove (she’d said Shirley substation) so ??? Anyway, let’s get those feasibility studies in the record! And the rest as they come out. Given what the distribution system looks like there, and the low load, I’m not believing they can add in 100MW without some infrastructure changes, like substation expansion, new transmission (reconductored? bundled? double circuit?). We shall see.
The other thing that I think is really important is the economics of this, which Birdsall gets to when she wants a copy of the PPA. They don’t have one yet, and with the kidns of payments going to Stella under the lease, $1.3 million annually, and a $7.5 million kicker when they get the regulatory and land use permits nailed down, it’s very hard to see how a solar project would or could cash flow with those kinds of outgoes. That lease and $7.5 could well make the project unmarketable.
Here’s the report from Today’s Sunbeam:
Upper Pittsgrove solar farm plan tabled – for now
Saturday, March 20, 2010
By Phil Dunn
pdunn@sjnewsco.comThe project as it stands right now is split into two sections – an east and west site.
Other residents brought up noise concerns and the potential of decreased value to their property.
No decision making will be made on the application until at least the May land use board meeting.
78 MW of Solar PV in New Jersey?
March 14th, 2010
This is a map of the footprint of the 78MW Stella Solar and Atlantic Green Power project proposed for Upper Pittsgrove, New Jersey. I’ve ehard there are others planned nearby, but that this is the biggest.
Project description from Atlantic Green Power Holding Company 3Q 10-Q filing:
There are two meetings coming up about this project:
Informational Meeting
Elmer Grange Hall
Tuesday, March 16, 2010 from 6 to 8:30 p.m.
and the Land Use meeting where the town will approve or deny the application:
Upper Pittsgrove Town Hall
Thursday, March 18, 2010 at 7:30 p.m.
Now you all know how I love solar, from the solar hot water my father designed for the Minnesota Zoo to those simple little heaters you can make or buy:
Every house needs these simple solar heaters.
Solar PV should also be on the roof of every big box there is, and on every home. But to be clear, I don’t think it belongs covering prime ag fields a long way from load. That isn’t “highest and best use,” and just doesn’t make sense when you consider the capacity factor of solar and the line loss over transmission. So, this project seems odd…
Why do it? Well, look who is involved and the incentives — means, motive and opportunity — and given that, I hope the town will take a close look before jumping, at the very least, require these conditions (off the top of my head):
- No ag land be removed from production; and
- No ag land be removed from ag preservation designation; and
- Commercial solar be limited to commercial and industrial areas; and
- Commercial solar be limited to roofs in rural areas.
WHO IS GOING TO BUY THIS POWER?
LET’S SEE THE POWER PURCHASE AGREEMENT!
The article way below, from Today’s Sunbeam, says it is to be built on land that “is currently owned by Ed Stella and will be leased to Atlantic Green Power…” but the Atlantic Green Power site says that Edward Stella, Jr., is the “Vice President of Project Development.” From what I can see, this is their FIRST project. Edward Stella as VP? Really, it’s right here, so we’re not exactly talking about an arms length transaction:
Edward Stella, Jr.
Vice President of Project Development, Director
If he’s connected to “such customers as Scott’s, Coastal Supply, Home Depot and Lowes” why aren’t they putting solar on the roofs of those big boxes, where it can be used, and not on prime ag land far away from big boxes?
Atlantic Green Power Holding Company has been in existence since September 17, 2009, and Edward Stella, Jr., has been “Vice President of Project Development” and a “Director” for all of a month.
A press released based blurb provides two sources for more information:
Robert Demos, Jr., President & CEO of Atlantic Green Power Holding Company
and
Howard Greene, Greene Inc., and CLICK HERE FOR GREENEINCPR.COM — HA!!
So now, let’s look at Lodestar Mining… from their site, their ONLY press release listed posts these links for Atlantic Green Power and Lodestar. CLICK ON THESE LINKS THAT THEY PROVIDED:
LGST – their own link says “There are no All Market results”
Hmmmmmmmmmmm…
CLICK HERE for Lodestar’s 10-Q for the year ending June 30, 2008, with this statement:
CLICK HERE FOR LATE FILED 2008 10-K.
From their 10-K regarding their one option contract:
And this snippet:
And again, a statement of its tenuous existence as a going concern:
And again, the solar project particulars:
Pittsgrove Solar Farm
Something that caught my eye on their site — which is repeated in the SEC 3Q 10-Q filing — a press release that talks about the ARRA incentive, a 30% cash payment in lieu of federal investment tax credit, and federally guaranteed loans and a 30% investment tax credit. Seems ALL of those would apply here, so let’s say Mr. Stella is “motivated.”
Here’s the article from Today’s Sunbeam:
Scoping Comments for National Park Service
March 12th, 2010
Scoping Comments for the National Park Service EIS regarding the Susquehanna-Roseland transmission project are due today. Here’s the Comments for Stop the Lines, and I’ll add those I receive from others that come in.





