Mesaba Project appellate decision
May 18th, 2010
It’s out, and although the court rejected the arguments of Excelsior Energy saying they didn’t get enough out of the PUC, and rejected the arguments of Minnesota Power and Xcel Energy, the bottom line is that the Public Utilities Commission won, their Order stands, and so in a small way, Excelsior Energy has “won.”
There were three issues before the court:
I. Did the commission err in determining that the Mesaba project is an IEP under Minn. Stat. § 216B.1694, subd. 1?
II. Does Minn. Stat. § 216B.1694, subd. 2(a)(7), require the commission to undertake its traditional public-interest evaluation?
III. Was the commission’s application of the IEP statute to Excelsior’s PPA arbitrary and capricious or unsupported by substantial evidence?
Bottom line?
We defer to the commission’s expertise as to the definition of the technical term ―traditional technologies.‖ The commission’s decision that the Mesaba project is an IEP is supported by substantial evidence.
The commission has the statutory authority to consider the public interest in evaluating the terms and conditions of an IEP’s PPA. Its decisions in this regard are supported by substantial record evidence and are not arbitrary and capricious. Accordingly, the commission did not err in concluding that Excelsior’s proposed power-purchase agreement with Xcel is not in the public interest under Minn. Stat. § 216B.1694, subd. 2(a)(7).
Here’s the full decision, issued today at 10:00 a.m.
May 18, 2010 Excelsior Energy-Mesaba Project Appellate Decision
Tomorrow – Excelsior Energy Appellate Decision
May 17th, 2010
Word is out – tomorrow we’ll know whether the Appellate Court thinks that Excelsior Energy qualifies as an Innovative Energy Project under Minnesota statutes. Stay tuned…
PJM & PEPCO’s MAPP line trying to appease
May 9th, 2010
The MAPP line, PEPCO’s Mid-Atlantic Power Pathway transmission line project through Maryland and Delaware, is in the news again. But why??? Where the line is not needed, and it’s withdrawn by PJM and PEPCO, why is this being accepted? Why is this regarded as a “win?”
Remember that they pulled the project?
PEPCO letter 1.8.09 to suspend MAPP, includes 1.8.09 letter from PJM’s Herling
And before that, the part from Indian River to Salem was eliminated?
The May, 2009, Press Release says:
According to Gausman, PJM has also reviewed the need for the section of the line that would run from Delmarva Power’s Indian River substation near Millsboro, Del., to Salem, N.J., and has decided to move this portion of the line into its “continuing study” category. This means that the reconfigured MAPP line will now extend approximately 150 miles from northern Virginia, across southern Maryland and the Chesapeake Bay, and terminate at Indian River. The change would likely reduce the total project cost from $1.4 billion to $1.2 billion.
And then there’s the report that shows there’s no need, that demand is downdowndown, that “congestion” is downdowndown, that price of electricity is downdowndown, that demonstrates that the market concept that they’re all drooling over will have them aspirating their aspirations:
So then why did they send out a press release last week:
…which every Peninsula news outlet gave pretty much verbatim coverage?
And then there’s the PJM RTEP 2009, released February 26, 2010.
So here’s how their press release looks after the papers get it:
Delaware utilities: Plan takes power line under Choptank
It is being planned by Pepco Holdings Inc., parent company of Delmarva.
Now read the other “articles” and tell me if there’s an echo in the room:
Underwater power line route suggested
Proposal under Chesapeake avoids refuge
By Calum McKinney • Staff Writer • May 6, 2010
But the day before it was better, with some original quotes:
Minnesota’s nuclear moratorium — gone?!?!?!
May 8th, 2010
I read with horror news of Rep. Bill Hilty’s amendment eliminating the moratorium on new nuclear generating plants that passed in a House Ominous Bill this week. WHAT ARE THESE YAHOOS THINKING? The Senate already approved it, and now the House… and I just can’t see Pawlenty doing anything but signing it with glee.
(sudden feeling of ice picks going through temples… buried in brain… electricity applied…)
AAAAAAAAGH!
Is this the “price” of the rollback of exemptions of utilities from eminent domain laws? Is it an attempt to look like they’re repealing it when “conditions” mean it won’t happen? (like those that said Obama really doesn’t mean what he’s saying about coal gasification or transmission, he knows better) Is it more of the same deal-making that took the Renewable Development Fund away from PrairIe Island Indian Community, or the enviro sell-outs that gave us the 2005 Transmission bill? Minnesota’s second nuclear waste storage facility at Monticello, now two piles piling with no plan in sight, PERMANENT?
What I’m hearing about this from various little birdies….
… is NOT encouraging — ooooohhhhhhh do I have a headache…
… apparently NO ONE OBJECTED!
NO ONE OBJECTED?!?!?!?!
AAAAAAAAGH!
Here’s the bill as it is on the Senate site:
Here’s how Rep. Bill Hilty, Chair of House Energy, amended it:
Page 4, after line 11, insert:
“Sec. 4. [216B.1695] NUCLEAR POWER PLANT; COST RECOVERY.
(a) The commission may not allow any of the following costs attributable to the construction of a nuclear generating plant begun after July 1, 2010, to be recovered from Minnesota ratepayers until the plant begins operating at a monthly load capacity factor of at least 85 percent:
(1) planning, design, safety, environmental, or engineering studies undertaken prior to construction; or
(2) the costs of obtaining regulatory approval, including permits, licenses and any other approval required prior to construction from federal, state and local authorities.
(b) The commission may not allow any of the following costs attributable to the construction of a nuclear generating plant begun after July 1, 2010, to be recovered from Minnesota ratepayers:
Journal of the House – 98th Day – Thursday, May 6, 2010 – Top of Page 11584
(1) any construction costs exceeding the projected construction cost of the generating plant and any ancillary facility constructed by the utility to temporarily or permanently store nuclear waste generated by the plant, as identified in the utility’s certificate of need application submitted under section 216B.243;
(2) the costs of insuring the plant against accidents that exceed the cost of insurance for a fossil fuel plant of equivalent capacity; or
(3) contributions from the plant to provide and maintain local fire protection and emergency services to the plant in case of an accident.
(c) Except for regulatory costs of state agencies, no revenues from taxes or fees imposed by the state of Minnesota may be used to pay for any portion of the preconstruction, construction, maintenance, or operating costs of a nuclear generating plant, or to assume any financial risk associated with an accidental release of radioactivity from the generating plant or an ancillary facility constructed by the utility that owns the generating plant to temporarily or permanently store nuclear waste generated by the plant.
Sec. 5. Minnesota Statutes 2008, section 216B.243, subdivision 3b, is amended to read:
Subd. 3b. Nuclear power plant; new construction prohibited; relicensing. (a) The commission may not issue a certificate of need for the construction of a new nuclear-powered electric generating plant provided that the certificate of need application contains a separate estimate of preconstruction and construction costs that does not include any of the costs identified in section 216B.1695, paragraphs (a) and (b).
(b) Any certificate of need for additional storage of spent nuclear fuel for a facility seeking a license extension shall address the impacts of continued operations over the period for which approval is sought.”
Renumber the sections in sequence and correct the internal references
Amend the title accordingly.
Way below is the list of yeas and nays, do send each of them a missive:
The ones who voted against it are the strangest set of bedfellows! But KUDOS TO THEM!
If you click on this to look at the whole back and forth with amendments, scroll to p. 11579 to start. Here’s the vote:
The bill was read for the third time, as amended, and placed upon its final passage.
Those who voted in the affirmative were:
Those who voted in the negative were:
Pawlenty gets slapped!
May 6th, 2010
You know life is good in Minnesota when the Supreme Court slaps The Green Chameleon, Gov. Tim Pawlenty!
(FYI, it’s been a busy week in CapX 2020 transmission line land, the scoping hearings, today is Cannon Falls. Check it out on www.nocapx2020.info)
Here’s the decision:
In short:





