From Alison Milsaps and Dave Ulery, Block Plains and Eastern Clean Line:

To recap the events of recent weeks: Plains & Eastern, Clean Line’s regulatory crown jewel and the only of its projects to be fully (if questionably) permitted, is DEAD in Arkansas. Hallelujah. Don’t take our word for it, though. Let’s look at a little evidence:

Hubris: Clean Line’s Michael Skelly and the End of the Plains and Eastern Project…

You know, I love it when this happens.

Under the agreement, Clean Line Energy retains project assets east of Oklahoma, and NextEra Energy Resources owns only the project assets in Oklahoma.

Clean Line Energy added that the transaction will continue the project’s forward momentum and install a new sponsor to a transmission solution to the burgeoning wind sector in Oklahoma and the Southwest Power Pool.

A Clean Line Energy spokesperson on Dec. 22 told TransmissionHub of the deal, “We cannot disclose financial information.”

Clean Line Energy Partners, a Houston-based developer of five major transmission lines for wind-generated electricity, has dropped its interconnection agreement with TVA for one of its most promising projects after the federal utility declined to buy what Clean Line officials said would be cheaper and cleaner power for TVA…

But after years of study, TVA said the Clean Line project didn’t make economic sense for the nation’s biggest government-owned utility, since TVA already has enough power-generating capacity and is on path to get more than half of its power from carbon-free sources. TVA President Bill Johnson said the intermittent nature of wind power would require TVA to build other backup power generators, including natural gas plants, that would offset the promised savings from the wind-generated power sources alone.

“We’re looking at a power demand in the future that is flat, or declining slightly, so we don’t anticipate needing major additions to power generation for a decade or more,” Johnson said.

“We all are wondering at this point” what is going on, said Julie Morton, of Van Buren. “We are disconnected on the western end now. The TVA was going to take 3,500 of the 4,000 megawatts it was going to generate, but now it is disconnected on that end.

“We are stuck in the middle, unplugged at both ends, and the only way out for us is if Clean Line completely implodes, which I think is happening, and the Department of Energy withdraws from the project.”

and now…

Using powers contained in the Energy Policy Act of 2005, the department moved the project forward over the objections of Arkansas leaders.

Among other things, the law would enable the use of eminent domain to obtain property from unwilling sellers.

But the participation agreement allows the department to back out of the deal if “the Commencement Date has not occurred by December 31, 2018.”

In the letter, delegation members urged Perry to “pause the Project to either study or terminate its participation before the deadline.”

Since it was unveiled, the power line project has generated controversy.

Arkansas lawmakers ask DOE to block Clean Line transmission project

Don’t know what more we could possibly need to show that this project is O. V. E. R.  I do wonder if the appellate case was dismissed so there would be no precedent, and then, immediately after it was dismissed, all this happens.  Then, if they or someone else wants to try a Section 1222 project, the door remains open????