Xcel, cost taxation? WHAT?

April 30th, 2021

Just wow… It’s the sort of thing that makes my head burst!

Association of Freeborn County Landowners has been challenging the invasion of Freeborn Wind, a/k/a Xcel Energy a/k/a Northern States Power into this existing community.

Hundreds of meetings, filings, over the last FOUR YEARS, and we got the first contested case hearing ever for a wind project in Minnesota… the first in 20+ years of siting wind projects, and the first time a projects comes to the test, the ALJ recommends the permit be denied!

The Recommendation of the Administrative Law Judge:

The Public Utilities Commission does a perverse and contorted 180 and lets Freeborn have their way, and the public, residents be damned.

Freeborn? PUC upends ALJ’s Freeborn Wind Recommendation

Then 17 turbines left for Iowa, but 24 remain.

… we get tossed out by the appellate court, which affirmed the Commission’s decisions and Orders.

Freeborn Wind appeal – we lose…

And earlier this week, they serve this:

Let’s see… they have open access to ratepayer pocketbooks, they’re reimbursed for their costs! BY US! We ratepayers have to pay! Meanwhile, for the public to show up, and to challenge for FOUR YEARS on this project, or any project, like the Mesaba project, or CapX 2020!, people hold garage sales, put grain in at the elevator, a silent auction in a tornado, and plain old arm-twisting to cover our comparatively nominal costs.

Our objection just filed:

NOW THEY THINK WE SHOULD PAY THEM $3,312.75?

Meanwhile, don’t cha wonder how’s Xcel Energy doing these days? Their 1Q report just out… More customers, decreased sales, and stock soars:

Hmmmmmmm, remember that Texas storm? Here’s the impacts:

Xcel easily tops earnings estimates

Ain’t capitalism grand…

The settlement agreements for Minnesota’s first landowner buyouts were approved by the Public Utilities Commission at its agenda meeting on May 17, 2018.  Today, it’s REAL, the written order has been filed.

18-059++08-573-DW_ORDER

Thanks to Alliant/Wisconsin Power & Light for their work in getting this done. Now, time for a couple of closings!

And at the same time, let’s whip this wind siting process into shape!

The Red Wing Republican bEagle ran my commentary on wind siting, all of it!  Short version?  Respectful wind siting now!  The community must consent!

Viewpoint: Respectful siting process for wind turbines long overdue

By Carol A. Overland, Red Wing

It’s taken a decade, but the Minnesota policy battleship is turning regarding siting of wind projects. State agencies, in their rush to site wind, have dropped the ball — they have failed in their charge to regulate and protect the public and the public interest. We need a respectful siting process, and that is 20 years overdue. If Minnesota doesn’t correct our wind siting process, the legitimate pushback will make siting a wind project difficult at best.

Recently an administrative law judge issued a recommendation that the Freeborn Wind Project be denied because it had not demonstrated it could meet the state’s noise regulation, or in the alternative, give the developers some time to demonstrate how it will comply with noise standards at all times throughout the project footprint.

The Public Utilities Commission will make a permitting decision, typically a month or more out. It’s not final, but this recommendation is a crucial step.

The Freeborn Wind case involves many “firsts.” It is the first project in Minnesota to be sited using the siting criteria of the Power Plant Siting Act (criteria in Minn. Rules 7850). It is the first project in Minnesota where the siting permit was subject to a contested case proceeding, in essence a trial, where the applicant had to prove up its application before an administrative law judge. It is the first project where an administrative law judge has recommended the permit be denied.

Lax rules

Minnesota wind siting has been lax and much of that falls directly on the Department of Commerce. The Environmental Quality Board no longer has siting authority. It’s been that way since 2005, when the Energy Omnibus bill shifted it to Commerce, doing siting “analysis” for PUC — in addition not to using Power Plant Siting Act criteria, and until now, no contested case.

There is no environmental review, no environmental assessment worksheet, no environmental impact statement, required for wind projects. Wind projects, until now, were separated out from the Power Plant Siting Act and permits issued citing the wind statutes and rules Minnesota Statute 216F and Minnesota Rules 7854, which have NO siting criteria at all? All wind siting permits cite only Statue 216F and Rule 7854 as permitting authority! That compartmentalization is the doing of the Department of Commerce.

There are small wind “standards,” which were ordered in 2008, but that was not a rulemaking. It was a process that was a too fast response to a legislative mandate, and in essence, the PUC took small wind standards and stamped them as “Large Wind Energy Conversion System” standards.

Nothing has been done since, despite pre- and post-construction complaints, suggestions, interventions and rulemaking petitions. State agencies, in their rush to site wind, have failed in their charge to regulate and protect the public and the public interest.

Issues are real

Wind projects are by definition the nuisance moving to the landowners. All are sited where there’s an established community, and the wind projects lease land in patchwork sites for their projects. Communities are steamrolled. The way projects are sited, it’s inevitable that homes are surrounded, and turbines are close to homes.

Noise issues are real. Noise modeling isn’t necessarily predictive, and siting often doesn’t allow for margin of error. Shadow flicker is real, but landowners are provided with blinds to live in the dark or are told to take a trip to Florida during times of heavy shadow flicker. Eagle nests are not accounted for, or in one case, blown away by helicopter, and in another, removed after getting a permit.

It’s time to develop thoughtful and respectful siting; It’s long overdue. We can establish standards and rules so that wind projects are projects people can live with. We can require modeling that provides for margin of error. We can take into account the feelings of non-participants who already live in the area and will be affected by a project moving in. The community must consent.

Looking forward, if Minnesota doesn’t alter siting regulations and practices, it’s going to be very difficult to site wind projects.

There’s also a problem looking backward, for there are people now living in the midst of improperly sited wind projects. Not only does Minnesota need to address siting issues, but Minnesota needs to develop policies for those living near and affected by wind projects, as has been done for other types of utility projects. There are at least two wind project permits now before the Public Utilities Commission regarding noise and

Minnesota’s noise regulation. Wind turbines are massive structures with 55-foot diameter concrete foundations — it’s not like we can just pick them up and move them.

Permits say that if there are violations, the violations must be corrected, or the permit can be suspended and/or revoked. In short, solutions to problems in existing wind developments are not easy, and few options are practical.

What to do? A start is to revamp Minnesota’s permit complaint process, which is occurring now in one docket. The revised complaint process, after public comment and a hearing, should be applied to all permits.

Another step is to enact an “opt out,” similar to the “Buy the Farm” option for transmission (Minnesota Statute 216E.12, Subd. 4, where affected landowners can make the utility buy them out rather than live under a transmission line.

Other ideas include a promulgation and revamp of PUC and MPCA rules, which is a multi-year process.

Policy takes a long time to change. Will Minnesota’s agencies, utilities, wind developers, landowners, and legislators work on the changes or will it be a continued fight? Do utilities want to site wind projects in Minnesota?

With the developments over the last year, I’m encouraged that Minnesota will work toward respectful siting. Let’s make it happen.

Carol A. Overland is a Red wing attorney who represents Association of Freeborn County Landowners.

p.s. Minnesota’s existing Wind Standards and Exhibit A.

Gro Wind south of Northfield

November 29th, 2010

Right now, the Northfield Planning Commission is reviewing the idea of the Spring Creek LLC wind turbine planned for the Northfield Urban Reserve district.  Here’s some on that from Tracy Davis:

Wind Turbines in the “Urban Reserve” around Northfield

In another exciting development, Tom Dunnwald filed for a Writ of Mandamus, to tell Rice County to follow the law, and damned if he didn’t get it!  In this case, the County didn’t provide proper notice for the Conditional Use hearing, and they have to do it over.

This is the same county where I had a laundry list of instances where they had not followed the law and the judge said, “They know they should follow the law so I’m not going to tell them to follow the law” and tossed us out.  So perhaps Mandamus is the way to go rather than a Declaratory Judgment?!?!  Go figure…

Here’s the poop from the Northfield News:

Mandamus trips up wind turbine development

By: JOSHEPH LINDBERG

Posted: Friday, November 26, 2010 9:17 pm

Rice County officials have been ordered to re-notify residents in Northfield Township of a public hearing on the proposal to build two wind turbines in the area.

A county judge ordered a writ of mandamus earlier this month, which could force Rice County officials to re-notify dozens of individuals affected by the proposed construction of wind turbines in Northfield Township — and delay any county action on turbine construction approval.

Relatively rare in the course of legal proceedings, mandamuses are “[I]ssued by a superior court to compel a lower court or a government officer to perform mandatory or purely ministerial duties correctly,” according to Black’s Law Dictionary.

Gro Wind LLC is trying to move forward with a pair of 326-foot-tall commercial wind turbines, slated to be built in the southeastern corner of Northfield Township. The approval of conditional use permits for the agriculturally zoned land has been postponed due to legal action taken by several residents.

Similar to an injunction, the mandamus forces Rice County officials to send out individual notices to properties near the proposed site, notices that residents in the area say they did not receive within the legal time frame.

The judge issues a mandamus after a evaluating the “clear intent” of a law that a governmental body needs to uphold, said Tom Dunnwald, an attorney representing one of the residents in Northfield Township. In this case, the issue was the notification of local residents about a public hearing.

The county is required to notify residences of public hearings regarding certain high-impact projects 10 days before they occur. The county put a notification in the paper, but some residents were not notified by mail until three days before the hearing, Dunnwald said.

One individual in the area did not get their notice in time due to improper postage on the notification, said Rice County Commissioner Galen Malecha.

Read the rest of this entry »

Goodhue Wind ain’t C-BED!

April 8th, 2010

Goodhue Wind is in the news, and the timing is perfect foreshadowing for next week’s PUC meeting.

In yesterday’s MinnPost:

T. Boone Pickens Tilting at Minnesota Windmills?

In today’s STrib:

Pickens wind turbines coming to Goodhue

In going through the THREE FOOT pile of mail waiting here when I got back, I’ve been reading the Dept. of Commerce Information Requests to Goodhue Wind, and I am pleasantly shocked, they are ON this.  What is “this?”  The basic financing and C-BED claims of this project — it’s been smoke and mirrors from day one, and Commerce is paying attention, digging for more information, and it’s impressive.  MUST GIVE CREDIT WHERE CREDIT IS DUE, particularly to Commerce!!!

MOES Reply Comments

Staff Briefing Papers

THESE FILINGS ARE MUST READS!

Just in — here are the PUBLIC AWA/Goodhue’s responses to Commerce Information Requests.  All of these below are the PUBLIC versions — I don’t see much to gain by reviewing the specifics because that’s pretty restrictive.

First, Dockets 09-1349l 09-1350 and 09-1186 (PPA & Certificate of Need):

IR 1-4

IR 5

IR 5a

IR 5 Supplemental

IR 6

IR 7

IR 8 & 10

IR 9

IR 11

IR 12-13-14

Next, Docket 08-1233 (the siting docket)

IR 1

IR 2-3