Underground Xcel’s Hiawatha Project transmission.  That’s BIG, it’s good news, except for one thing — “Who pays?” is still a question:

ALJ Heydinger’s Recommendation for Xcel’s Hiawatha Transmission Project

Problem is, cost allocation isn’t dealt with specifically, only explained, so no recommendation regarding that.

untitled

If the PUC went ahead, would it be spread across the Metro area, the full Xcel rate base, or???

For the SE Metro, and for the Chisago Transmission Project, if they cities would have agreed to shoulder the cost, undergrounding was no problem.  But that’s not feasible for a city to pay.  So now what?  Will the PUC actually order undergrounding, with a broad rate base recovery?

pseg_logo

HA!  I love it when this happens.  Just before National Park Service public hearings (schedule below), PSEG screws up and an application gets tossed back in their face!

I’m representing Stop the Lines against PSEG”s Susquehanna-Roseland transmission project in New Jersey.

PSEG thought they’d be “smart,” and given the length and intensity of process for the federal environmental review of its proposal to cross the federally designated Wild & Scenic Delaware Water Gap with massive transmission…

delawarewatergap

… they tried to divide the line in half for its News Jersey Dept. of Environmental Protection wetlands application and other DEP applications too.

First the DEP rejected that maneuver, short and sweet, and rejected their wetlands application:

PSEG Deficiency Letter July 28, 2010

Here’s the meat of it, first the funny part:

dep-rejection-snippet1

… and then, the substantive issue…

pub-rejection-snippet2

So then, PSEG withdraws their other DEP applications:

PSEG Letter of Withdrawal July 29, 2010

I love it when that happens… and what great timing.  Bring on the National Park Service hearings!

Here’s an Alert from the New Jersey Sierra Club:

Urge the National Park Service to Select the “No Action” Alternative!

The National Park Service will be hosting 3 public meetings to present the Preliminary Alternatives for the Susquehanna-Roseland transmission line as part of its NEPA (National Environmental Policy Act) review for this project. The meetings will consist of an “open house” portion where information will be available and NPS staff can answer questions and a formal “public hearing” portion. The meetings will be held:

Tuesday, August 17
Fernwood Hotel and Resort
US 209 North
Bushkill, PA
Open House: 2:30 p.m. – 4:30 p.m.
Public Hearing: 6:00 p.m. – 9:00 p.m.

Wednesday, August 18, 2010
Stroudsmoor Country Inn – Terraview
North 4th St
Stroudsburg, PA
Open House: 2:30 p.m. – 4:30 p.m.
Public Hearing: 6:00 p.m. – 9:00 p.m.

Thursday, August 19, 2010
Farmstead Golf and Country Club
88 Lawrence Road
Lafayette, NJ
Open House: 2:30 p.m. – 4:30 p.m.
Public Hearing: 6:00 p.m. – 9:00 p.m.

The proposed alternative routes can be viewed here.  Click on the “Preliminary Alternatives Newsletter” for details and mapping of the 6 proposed routes.

Please come to these meetings and voice your support for the “No Build Alternative”!  If you are unable to attend the hearings, comments can be submitted online here.  NPS will accept comments on these alternatives August 8- September 7.

++++++++++++++++++++++++++

And word is getting out:

Opponents of powerline upgrade are happy that project is delayed

BY COLLEEN O’DEA • STAFF WRITER • August 5, 2010

Opponents are cheering the news that Public Service Electric and Gas Co.’s transmission line upgrade will be delayed by three years because of problems with environmental permits.

But they are still urging people to comment on the National Park Service’s proposed alternatives to the line, which would span 47 miles in New Jersey. Some of those options would bring the line south into areas of Morris County that are more congested.

The utility had hoped to begin work this summer to add 500-kilovolt lines on towers as high as 195 feet, along its existing 230-kilovolt Susquehanna-Roseland line. It received approval from the state Board of Public Utilities and was awaiting OKs from the state Department of Environmental Protection and NPS.

Last week, PSE&G’s second quarter earnings statement disclosed that the utility would not complete work on the eastern half of the line, from Hopatcong through portions of Morris County to Roseland, until 2014 and on the western section to the Delaware Water Gap until 2015.
Read the rest of this entry »

crowd_cheering_med

YEAAAAAAAA!  The East Coast Governors are mad as hell and letting the Senate know just what they think of this Midwest plan to build billions and billions of dollars of transmission from here to the East Coast and make them pay for it, oh yes, it’s about time the Midwest schemers start listening.

The Des Moines Register is paying attention — why not Minnesota papers?

Eastern governors protest Midwest wind transmission line

And here’s the letter itself, pretty much the same spirit as the last one, although I don’t see the directly stated link to coal in this one:

East Coast Governors’ Letter 7/10/2010

Here’s  a pithy snippet:

The build-out of the national transmission corridor implicit in S. 1462 is estimated to cost at least $160 billion, the majority of which would be paid for by East Coast states, costing our ratepayers hundreds of dollars per year. In its current form, this legislation would harm regional efforts to promote local renewable energy generation, require our ratepayers to bear an unfair economic burden, unnecessarily usurp states’ current authority on resource planning and transmission line certification and siting, and hamper efforts to create clean energy jobs in our states.

This comes not too far on the heels of some promotional announcements about those transmission plans, the “not so” SMARTransmission study — I though I’d posted this before, but don’t see it, so here it is:

SMARTransmission Phase I Study

How’s this for a vision/nightmare — it’s one of their chosen three:

alternative5

midtown-greenway2001

Xcel Energy, or Northern States Power, whichever, has filed its brief in the Routing docket for the Hiawatha Transmission Project.

Xcel/NSP Post-Hearing Brief

Xcel/NSP Proposed Findings of Fact, Conclusions

Also filed is Notice that the transcripts are now available at local libraries, a big help because the cost is prohibitive, they’re not free here as they are in WI or available via FOIA as they are in New Jersey (called OPRA there):

Notice – Transcripts are in the libraries

Which states:

I write to advise that the transcripts for the evidentiary hearings held in the Hiawatha Transmission Project routing proceeding on April 12 – 21 and April 26 – 30, 2010, have been placed in the following libraries: East Lake Library, Hosmer Library, Franklin Library, Central Library, and Roosevelt Library. We have also provided an extra copy to the Central Library with a request that it forward it to the Nokomis Branch once renovations are complete. The transmittal documents are enclosed.

So those of you writing briefs now know where to go!!!!

STL in the news!

June 12th, 2010

stopthelines_sign3

Stop The Lines! has appealed the New Jersey Board of Public Utilities’ determination on the Susquehanna-Roseland transmission line, I’ve been representing them in this fracas, and from the news reports below, it looks like we’ve hit all the bases!

The Susquehanna-Roseland transmission line is absurd — they’re tearing down an existing low capacity line and putting up towers twice as high with … well… imagine this, QUAD bundled 500 kV line.  Really… that is what they applied for, but midway through the hearing, they admitted that the structures couldn’t handle that and reduced it to TRI-bundled 500kV.  ACSR at that, could it be more primitive?  It’s absurd, if they 190 foot towers fell, with a 75 foot Right of Way, that’s 115 feet that it could extend beyond the Right of Way.  It’s beyond absurd — it’s insane, and earth to mars, there are people right there, RIGHT THERE, don’t they care?

susquehanna-roseland

Plus it’s not needed, the Marketing Analytics report says it all:

Marketing Analytics – PJM 2009 State of the Market Report

Here’s the BPU order that we’ve challenged:

NJ BPU Order – April 21, 2010

This is from the Pocono Record — be sure to click on the linkedarticle below to get to the Pocono Record comment section:

Power line fight heads to NJ court

By Wayne Witkowski

For the Pocono Record
June 11, 2010

New Jersey activists fighting proposed increases in the voltage and tower height of the Roseland-to-Susquehanna power lines are taking their battle to appeals court.

Four environmental groups and one onf the two private organizations made up of concerned homeowners filed court papers this week against the state’s Board of Public Utilities and utility company PSE&G. The papers charge that BPU, which approved the plan unanimously without comment in February, did not exercise due diligence in properly reviewing the proposal.

Stop the Lines, based in Fredon, N.J., has filed suit. It is one of two active private organizaitions in New Jersey opposing the project, along with the recently established Save the Park group in Hardwick Township, N.J., which has a sign advertising its cause on Hollow Road in Smithfield Township.

The suit contends the review lacked a proper analysis of the need for the project, failed to consider the environmental impacts of construction or weigh the secondary impacts of importing coal energy from Pennsylvania.

The existing 47-mile link of the 145-mile route, which extends through the Delaware Water Gap National Recreation Area and specifically through Saw Creek Estates in Lehman Township, would add 500,000 kilovolts and raise towers to 195 feet. It is under the auspices of the PJM Interconnection, which includes PPL on the Pennsylvania side and PSE&G, which is looking to recoup $3 billion in costs stemming from the deregulation of the energy sector in New Jersey.

The project still awaits approval by the National Park Service. New Jersey Sen. Bob Menendez recently sent a letter to park Superintendent John Donahue asking him and the National Park Service to exercise due diligence in its decision, which is due in 2012.

PSE&G spokesman Karen Johnson defended BPU’s decision, saying PSE&G is aware of the appeal and believes there is “ample evidence” to support its decision.

And from the Daily Record:

Morris area citizens group sues over power line plan


BY COLLEEN O’DEA • STAFF WRITER • June 10, 2010

The citizens group Stop The Lines has filed an appeal challenging the state Board of Public Utilities’ approval of Public Service Electric and Gas Co.’s transmission line expansion through Morris, Sussex and Warren counties.

Stop The Lines’ appeal of the BPU’s January decision permitting the upgrade on PSE&G’s Susquehanna-Roseland power line is the second filed in appellate court in the last week. Four environmental groups that like Stop The Lines also had intervened in the proceedings filed an appeal last Friday.

The Stop the Lines appeal will focus on the lack of need for the expanded transmission line, which would add 500-kilovolt lines to towers as high as 195 feet along the 47 miles in New Jersey. The group also faults the BPU’s refusal to consider information on a possible decreased demand, health and safety impacts on landowners, residents and the environment and economic impacts ranging from loss of property value and tax revenue to inability of homeowners to obtain mortgages.

“Building 195-foot high towers within a 150-foot wide right-of-way is simply unreasonable,” said David Slaperud, a Stop The Lines trustee.

“We believe the ample evidence in the case fully supports the BPU decision that this line is needed for reliability,” said PSE&G spokeswoman Karen Johnson.

PSE&G is awaiting final environmental permits to begin working on the eastern half of the $750 million project, from Hopatcong to Roseland. It hopes to begin work this summer. The western portion, from Hopatcong to the Delaware River, has to await the completion of a National Park Service review because the line runs through the Delaware Water Gap National Recreation Area. That is expected to take until 2012.

The project was challenged in the BPU by citizen and environmental groups, several municipalities and the Montville School District. Ratepayers would foot the bill.

The line crosses from Pennsylvania at the Delaware Water Gap and proceeds through Warren and Sussex Counties. More than half the line would traverse Morris County, through Jefferson, Rockaway Township, Kinnelon, Boonton Township, Montville, Parsippany and East Hanover before ending in Roseland.

And in the New Jersey Herald:

Activists appeal state’s power line approval


FREDON — The most outspoken local opponent of the Susquehanna-Roseland power line is appealing its state approval in the court system.

Stop the Lines, the activist group that has been the most vocal and omnipresent adversary to the PSE&G line since its proposal in 2008, is appealing the Board of Public Utilities approval issued in February.

The appeal focuses on the need of the 500kV line, running 146 miles from the Poconos across northwestern New Jersey and into the heart of the Garden State. They will also question the economic impacts to property owners and municipalities along the line — which will double the height and triple the power of the existing 1920s-era transmission towers.

“Building 195-foot-high towers within a 150-foot wide right-of-way is simply unreasonable,” said David Slaperud, a Stop the Lines Trustee.

Four state environmental groups also appealed the BPU decision by the June 7
deadline.

PSE&G has maintained brownouts could roll down the line as early as 2012 if the upgrade is not complete. However, the National Park Service blessing to cross the Delaware Water Gap will not be available until that year — and PSE&G put off seeking final environmental permits for the 20-mile Sussex County stretch of the line last month.