Hot off the press from the Federal Appellate Court — Missouri Western District

Western-District-Appeal-Results

From the Order:

ATXI is an Illinois corporation authorized to do business in Missouri and engaged in the construction, ownership, and operation of interstate transmission lines that transmit electricity for the public use. It does not generate, distribute, or sell electricity to the general public or serve any retail service territory.

And the law is clear:

“If any of the items required under this rule are unavailable at the time the application is filed, they shall be furnished prior to the granting of the authority sought.”  4 CSR 240-3.105(2) (emphasis added).

And interpretation of the law:

The general language of section 393.170.3 authorizes the PSC to impose “reasonable and necessary” conditions on a CCN. However, the specific language of section 393.170.2 states that evidence of the county commission consents “shall” be on file before the PSC grants a CCN.  “Where one provision of a statute contains general language and another provision in the same statute contains more specific language, the general language should give way to the specific.” Id.

And bottom line?

The PSC’s Report and Order is vacated as it was entered in excess of the PSC’s statutory authority.

Love it when this happens!

Xcel Energy has released its 2016 SEC 10-K, and here is the number I care most about, the peak demand, incorporated into the chart above:

“Peak Demand” is the number they use to attempt to justify “need” for all sorts of abhorrent and expensive infrastructure, particularly infrastructure of the transmission variety.  Here are the specifics in megawatts (MW):

As Xcel Energy’s Ben Fowkes says, this is the “new normal.”  From the Seeking Alpha transcript of the XEL Earnings Call, January 31, 2013. 

So I think the economies are in decent shape across all our jurisdictions. Doesn’t necessarily mean it translates to high sales growth. And that’s consistent with our forecast. I mean, we’re not anticipating that we’re going to see a tremendous rebound in sales, even as the economies start to improve. I mean, I think, that’s our new normal, frankly.

Hence, they’re looking for other ways to make money, which they found in transmission, specifically CapX 2020 transmission, which was justified with this chart from MN Dept. of Commerce’s Steve Rakow, in his bar napkin depiction of the ups and down of peak demand:

Compare this drunken-dream drawing with the actual peak demand above — doesn’t look at all similar, does it.  Nevertheless, we’ve been stuck with over $2 billion in transmission infrastructure build-out which we’re just starting to pay for, and just starting to see show up in rate cases.  People are just now starting to get a feel for the economic impact, as if the environmental and quality-of-life impact isn’t bad enough…

Meanwhile, after going through years and years over CapX 2020, followed by the MISO MVP 17 project portfolio, now under construction, MISO wants to spring another bunch of projects on us. Their “Transmission Overlay.”  Yeah, right…

Here’s the list, in a spreadsheet:

20170131 EPUG Preliminary Overlay Ideas List

This is the MN, WI, SD, ND and some IA wish list weeded out from that spreadsheet (click for a larger version):

They want to add all of this, nevermind that Xcel is whining in its e21_Initiative that only 55% of the grid is not utilized:

(N) Identify and develop opportunities to reduce customer costs by improving overall grid efficiency.  In Minnesota, the total electric system utilization is approximately 55 percent (average demand divided by peak demand), thus providing an opportunity to reduce system costs by better utilizing existing system assets (e.g., generation, wires, etc.). (e21_Initiative_Phase_I_Report, p. 11).

And they want to build more?  MORE?!?!

And they want to ram it through even though it’s not needed, just like CapX 2020 transmission?  As if Obama’s RRTT wasn’t enough, pushing CapX 2020 Hampton-La Crosse transmission line:

Obama “fast tracks” CapX Hampton-LaCrosse?!?!?!

… check out tRump’s Executive Order 13766:

Expediting Environmental Reviews and Approvals for High Priority Infrastructure Projects

GRRRRRRRRRRRR!  As if there’s not enough work to do these days… but you know, the work never ends for us “paid protesters.”  And a woman’s work is never done either.

LTE in Dodgeville Chronicle

December 8th, 2016

mvp345

See the lower 1/2 of MISO’s MVP project 5, running from near Dubuque, IA to the northeast to the “Cardinal” substation near Madison?  That’s the Cardinal – Hickory Creek transmission line.

The Dodgeville Chronicle ran my Letter to the Editor, just in time for the meeting last night, held by Rural Utilities Service, about the Cardinal – Hickory Creek transmission project:

From 4-7 p.m. on Wednesday, December 7th, the Rural Utilities Service (RUS) is hosting a scoping meeting at the Deer Valley Lodge in Barneveld. RUS will again collect scoping comments for its Environmental Impact Study as it decides on a loan to Dairyland Power Cooperative for a share of project costs. RUS held scoping meetings October 31-November 3, 2016 – why more scoping meetings now?

The Cardinal-Hickory Creek transmission project stretches from a substation near Peosta, across the Mississippi River and Wisconsin, near Dodgeville, to a substation near Madison. Last April, as reported in this paper, American Transmission Company’s Jon Callaway reported that the project schedule had been pushed out to 2018 or beyond. The reasons weren’t clear, and should be specified and made part of the RUS record.

Cardinal-Hickory Creek and the under-construction Badger-Coulee transmission lines are MISO’s (Midcontinent Independent System Operator, Inc.) MVP project “five” revealed five years ago in MISO’s MTEEP 11 report. That was 2011, and it was “postponed” in 2016. Why the delay? MISO’s 12.38% rate of return for construction has been successfully challenged in federal court. There’s a glut of electricity where even marketing electricity cross country is not alleviating the industry’s overproduction. MISO’s MVP economic modeling no longer hold under current scenarios. And maybe the delay is that and more!

Now’s the time to tell RUS to consider the economics, need and causes of delay in its financing decision. If delay is right for the project developers, RUS should also delay, and put financing on hold.

Carol A. Overland, Esq.
Red Wing, MN

20161206_1655071

Slow evening at Rural Utilities Service’s scoping meeting for the Environmental Impact Statement for the Cardinal – Hickory Creek transmission project.  RUS is involved because Dairyland Power Cooperative (DPC) plans to hold a 9% undivided interest in the project, and are looking to RUS to provide the funding.  RUS held two more meetings, following on prior meetings October 31 and November 1 & 2, because their notice for those meetings went out a day late, so another Notice went out:

Notice of Intent To Hold Public Meetings and Prepare Environmental Impact Statement (October 18, 2016

Second Notice_2016-27988-2

Where’s my prior post on these meetings?  It’s gone! Here’s the dates and locations (click for larger version) — the last one is tomorrow in Barneveld, Wisconsin:

noice12-6-7-2016

So to make quick work of it, this is cut and pasted from the RUS Cardinal Hickory Creek page:

I had a quick chat with Dennis Rankin who’s in charge of the environmental review on this and the Dairyland Q-1 South projects, and had a few quick things to register, particularly that ATC has announced that the project is delayed:

ATC postpones Cardinal-Hickory Creek project – The Dodgeville Chronicle -Dodgeville, WI

I had this article and a few comments to add tonight, and will file more detailed comments before the deadline — now January 6, 2017.

Overland-Legalectric Preliminary Comments Cardinal-Hickory Creek(don’t worry, I’ll get this looking pretty by the deadline!)

20161206_1654551

On the way in, there was new transmission marching across the countryside, so ugly:

xmsn-mvp

And look how close to this house in New Vienna, right up near the garage, and not far from the house either — this line cut right through the middle of town:

20161206_1550331

20161206_1551041

newvienna1

But all in all, it was a beautiful day for a drive today!

20161206_1543442

applicationroute
It’s DONE!  With the Order released today by the Minnesota Public Utilities Commission, the Clearbrook – Clearbrook West 115 kV transmission line is officially over, AGAIN!  The PUC’s Order was issued earlier this month, and now another today from the Executive Secretary:

PUC Order_withdrawal_201611-126419-01

PUC Executive Secretary Notice and Order 201611-126818-01

Why this second one?  Perhaps because it’s the Executive Secretary who has power to permit withdrawal of the application, not the full Commission that issued that previous order?  Who knows… but hey, that reinforcement can’t hurt@