Here we go again, this year’s Power Plant Siting Act Annual Hearing.

Public Utilities Commission (PUC) Docket Number: E999/M-15-785

Office of Administrative Hearings (OAH) Docket Number: 60-2500-32901

Date: Tuesday, December 1, 2015

Time: 9:30 a.m.

Location: Minnesota Public Utilities Commission, Large Hearing Room, 121 7th Place East, Suite 350, Saint Paul, MN 55101

Bad weather? Find out if a meeting is canceled. Call (toll-free) 1-855-731-6208 or 651-201-2213 or visit mn.gov/puc

 

Here are some prior dockets (to access the entire docket, individual comments, etc., go to :

2000 Summary of Proceedings

2000 Report EQB

2001 Summary of Proceedings

2001 Report EQB

2002 Summary of Proceedings

2002 Report to EQB

2003 Summary of Proceedings

2003 Report to EQB

2004 Summary of Proceedings

2004 Report to EQB

2005 Report to PUC

2006 Report to PUC – Docket 06-1733

2007 Report to PUC – Docket 07-1579

2008 Report to PUC – Docket 08-1426

2009 Report to PUC – Docket 09-1351

2010 Report to PUC – Docket 10-222

2011 Report to PUC – Docket 11-324

2012 Report to PUC – Docket 12-360

2013 Report to PUC – Docket 13-965

2014 Summary Comments– Docket 14-887

PUC

Tomorrow, the Chapter 7829 Rulemaking is going to the Commission, for approval of the FINAL rules.  This rulemaking has been going on formally for over two years now in Docket 13-24 (go to NEW SEARCH and search for this docket).

Overland 7829 Comment Nov 18 2015

PUC Staff BriefingPapers_201511-115619-01

FINAL_Rules 7829_201511-115691-01

And some history…   I’ve been concerned about this chapter for a long while, and submitted a Petition for Rulemaking over FOUR YEARS ago.  Apparently that was filed in the trash:

Overland Petition for Rulemaking-7829

And prior posts:

NSP_Stack

Notice of the Power Plant Siting and Transmission Line Routing Program Annual Hearing

Issued: November 6, 2015

In the Matter of the 2015 Power Plant Siting Act Annual Hearing

Public Utilities Commission (PUC) Docket Number: E999/M-15-785

Office of Administrative Hearings (OAH) Docket Number: 60-2500-32901

Date: Tuesday, December 1, 2015

Time: 9:30 a.m.

Location: Minnesota Public Utilities Commission, Large Hearing Room, 121 7th Place East, Suite 350, Saint Paul, MN 55101

Bad weather? Find out if a meeting is canceled. Call (toll-free) 1-855-731-6208 or 651-201-2213 or visit mn.gov/puc

Hearing Description

The annual hearing is required by Minnesota Statute § 216E.07, which provides that:

Thecommission shall hold an annual public hearing at a time and place prescribed by rule in order to afford interested persons an opportunity to be heard regarding any matters relating to the siting of large electric generating power plants and routing of high-voltage transmission lines. At the meeting, the commission shall advise the public of the permits issued by the commission in the past year….

Note – No decisions about specific projects are made at the annual hearing.

Public Hearing Information

  • Public hearings start on time.
  • Arrive a few minutes early so you have time to sign in, pick up materials, and find a seat.
  • Administrative Law Judge James LaFave will preside over the hearing.
  • Public Utilities Commission and Department of Commerce staff members are available to answer questions about the Power Plant Siting Act processes and the projects.
  • You may add verbal comments, written comments, or both into the record.
  • Learn more about participating at a public hearing at http://mn.gov/puc/resources/meetings-and-hearings.jsp
  • Judge LaFave will use information gathered at the public hearing and during the comment period to write a summary report for the Commission

Submit Comments

Topics for Public Comment:

  • Any matters related to the site permit process for large electric generating power plants and routing of high-voltage transmission lines.

Comment Period: November 6, 2015 through January 5, 2016 at 4:30pm.

  • Comments must be received by 4:30pm on the close date
  • Comments received after comment period closes may not be considered

Online Visit mn.gov/puc, select Speak Up!, find this docket (15-785), and add your comments to the discussion.

If you wish to include an exhibit, map or other attachment, please send your comments via eFiling (see below) or U.S. Mail.

Please include the Commission’s docket number in all communications.

Filing Requirements: Utilities and state agencies are required to file documents using the Commission’s electronic filing system (eFiling). All parties, participants and interested persons are encouraged to use eFiling: mn.gov/puc, select eFiling, and follow the prompts.

Important Comments will be made available to the public via the Public Utilities Commission’s website, except in limited circumstances consistent with the Minnesota Government Data Practices Act. The Commission does not edit or delete personal identifying information from submissions.

Hearing Agenda

I. Introductions
II.Overview of Programs
A. Public Utilities Commission – Facilities Permitting and Public Advisor
B. Department of Commerce – Energy Facilities Permitting Unit
C. Role of Other Agencies
III. Projects Reviewed
A. Projects Permitted in 2015
B. Pending and Anticipated Projects
C. Electric Facilities Subject to Power Plant Siting Act
1. Generating Plants
2. Transmission Lines
IV. Public Questions and Testimony
V. Adjourn

How to Learn More

Subscribe to the Docket: Subscribe to receive email notifications when new documents are filed. Note – subscribing may result in a large number of emails.

  1. mn.gov/puc
  2. Select Subscribe to a Docket
  3. Type your email address
  4. For Type of Subscription, select Docket Number
  5. For Docket Number, select 15 in the first box, type 785 in the second box
  6. Select Add to List
  7. Select Save

Full Case Record: See all documents filed in this docket via the Commission’s website – mn.gov/puc, select Search eDockets, enter the year (15) and the docket number (785), select Search.

Project Mailing Lists: Sign up to receive notices and opportunities to participate in other dockets relating to specific projects in which you are interested (meetings, comment periods, etc.). Contact docketing.puc@state.mn.us or 651-201-2234 with the docket number, your name, mailing address and email address.

Minnesota Statutes and Rules: The hearing is being conducted according to Minnesota Statute 216E.07. Minnesota Statutes are available at www.revisor.mn.gov.

Project Contacts

Public Utilities Commission Public Advisor

Tracy Smetana – consumer.puc@state.mn.us, 651-296-0406 or 1-800-657-3782

LutherpostingNOTICE!!!  Landowners need notice if their land is affected!  Local governments and residents need notice if their communities are affected!  Yes, posting something can have an impact!

Notice is something that’s been an issue in utility dockets, and transmission proceedings particularly, for a long, long time.  It’s something we’re trying to address in the Minn. R. Ch. 7850 in our rulemaking advisory committee meetings over the last TWO PLUS YEARS!

Here are the latest Comments:

NoCapX_U-CAN_ Cover_8-25-2015

NoCapX-U-CAN_Comments_8-25-2-15_20158-113514-02

Why does notice matter?  Well, there’s this thing called “Due Process.”  Notice is a fundamental Constitutional Right.  It matters because “NOTICE” often doesn’t happen.  And it ties in with eminent domain, where land may Constitutionally be taken for public purpose projects with just compensation (and what is a “public” project?  What is “just” compensation?)  If you aren’t properly informed, have no notice, what does that do to your ability to participate?

In Minnesota, it’s a matter of law, clear, simply stated law:

The commission shall adopt broad spectrum citizen participation as a principal of operation. The form of public participation shall not be limited to public hearings and advisory task forces and shall be consistent with the commission’s rules and guidelines as provided for in section 216E.16.

Looking over posts and filings where this has happened, situations I’ve been aware of where landowners have been surprised at the last minute, too late to meaningfully participate in the proceedings, have filed Motions for Reconsideration, and have been to the Appellate Court on their behalf, it is SO frustrating.  Looking at the many times I’ve tried to intervene, to have intervention deadlines extended in case landowners want to stand up,   There’s no excuse.  People should not be surprised at the last minute with a utility attempt to run transmission over their land.

It happened recently in the Great Northern Transmission Line routing docket:

ALJ Order filed, no RRANT intervention

Can you believe Commerce EERA would file this?

Commerce EERA Responds… NOT!

It happened in CapX Brookings route and on CapX Hampton- La Crosse route:

  • Cannon Falls (CapX Hampton- LaX route) example to go around county park and DOT prohibited intersection area:

Cannon Falls Beacon – CapX in the news!

Dakota County resolution about CapX 2020

CAPX APPEAL — DECISION RELEASED (includes Cannon Falls)

UPDATED Updated Minnesota Appeal Update

Initial Brief – St. Paul’s Lutheran School and Church and Cannon Falls Landowners

Reply Brief – Cannon Falls Landowners and St. Paul’s Lutheran School and Church

  • Oronoco(CapX Hampton – La X route) enters “new route” proposal without notice to its own landowners:

Oronoco Twp’s Exhibit 89

  • USDA’s Rural Utilites Service (CapX Hampton – La X) example:

RUS Reopens Comments on Hampton-LaCrosse

  • Myrick Route (CapX Brookings) example:

Myrick route withdrawn

Myrick Route & How to find things on PUC site

PUC chooses Belle Plaine crossing

  • This is important to understand the set-up, and now this notice was snuck in at the last minute due to Applicant and Commerce disregard for objections of DOT, DNR and USFWS.

That’s enough examples to get an idea of the problem… but there are more that I can trot out if necessary.  The notice provisions in Minnesota law and rule must be corrected.

DraftIt’s final… that is, the FINAL meeting notice was just issued, one more go round on these draft rules for Certificate of Need (Minn. R. Ch. 7849) and Power Plant Siting Act (siting and routing of utility infrastructure) (Minn. R. Ch. 7850).

We’ve been at this for about a year and a half, maybe more, and to some extent we’re going round and round and round.

Here are the September 2014 drafts, hot off the press:

September Draft 7849

September Draft 7850

Send your comments, meaning SPECIFIC comments, not “THIS SUCKS” but comments on the order of “because of _______, proposed language for 7950.xxxx should be amended to say_______.”  It’s a bit of work, but it’s important, for instance, the Advisory Task Force parts are important because we were just before the PUC on this last week, trying to reinforce that Task Force’s are necessary, despite Commerce efforts to eliminate and/or neuter them.  That despite ALJ orders otherwise, the Final EIS should be in the record BEFORE the Public Hearings and Evidentiary Hearings (just lost a Motion to require this last month).

How can you comment?  The best way is to fire off an email to the Commission’s staff person leading this group:

kate.kahlert@state.mn.us

If you’re up to it, sign up on the PUC’s eDockets, and file your Comment in Docket 12-1246.  If you’d like your comment filed there, and can’t figure it out, please send it to me and I’ll file it for you.  It’s important that these comments be made in a way that the Commission will SEE, in a way that they cannot ignore, when this comes up before them.