Live from the BPU

February 11th, 2010

Susquehanna-Roseland… surprise, surprise, they just announced that they’re going to hold off until the end of the meeting, do everything else on a long agenda first… sigh…

bpu-2-11

Here we go  ROUGH NOTES

(with a few parenthetical comments)

BPU Agenda Meeting 2/11/10

Ken Sheehan: PSEG application.  Starts in PA, crossing to NJ at DWG, through 16 municipalities, following 230kV RoW.  PSEG building in conjunction with PPL in PA.  NJSA stt, taking it before the board, prove it is reasonably necessary (blah blah)

Three outstanding issues.

  • Request for Oral Arguments – staff recommends denial.  may be useful if parties have had opportunities to make arguments.  Wouldn’t appreciable add to process.
  • Request for Depositions – for 2 PSEG attorney re editing of PJM’s Herling’s letter.   Herling admitted they had made changes, but didn’t remember, and Motion followed.  Recommend denial of request.  Review has been minor, per Herling’s statement, board does not need additional info.
  • Request for Dismissal – Internvenors requested, also recommended it be denied.

Fiordaliso:  Are we to move on all of these now?

Ken Sheehan: Move after all the discussion.

Damase Hebert:  Background.  Proposed line is about 145 miles long, 45 miles of it is in NJ, crosses over Delaware Water Gap, Picatinny Arsenal.  2 switching stations, pursuant to a deal, agreed to move the Jefferson station to Hopatcong.  East Hanover, PSEG is willing to move to Roseland.  Entire project will cost between $900 million and $1.2 billion.  Interventions of Townships, Municipal Intervenors, Gerdau Ameristeel, Willow Lake Day Camp & Fredon Bd of Ed, Exelon,  Stop the Lines, Environmental Intervenors.  Participant status to National Park Service as requested.  Fiordaliso appointed to preside over hearings.   (Commission Fox gave someone a big grin at this point)  Public hearings and many written comments.  Fiordaliso conducted site visit, 3 locations.  Fiordaliso also presided over hearings, main topics covered included need, routing, engineering and construction, and electromagnetic fields.  400 exhibits and over 1,000 pages of transcripts (BFD!).  PSEG witnesses, 4 on need, 4 on routing, 3 on engineering and construction, and 2 on EMF.  Muni Intervenors sponsored 1 on need, 1 on EMF, and STL on ability of homes to obtain FHA mortgages.  Briefs, Muni Intervenors, Env Inervenors, Exelon, PSEG, Rate Counsel.  Reply Briefs too.  During December, delays in other PJM ordered PJM lines, PATH, and MAPP.  Board requested Sec.  send letter to PJM requesting more information,Herling response 1/21, reopened for a day of hearings.

Jerry May (?) to address need.

Jerry May: Relies on PJM analyses, that there will be violations of NERC by 2012.  (background on NERC).  PJM analyses through RTEP process also determined that S-R 500kV was the most appropriate remedy for the projected recommendations.  Intervenors have questioned the bases for assumptions and recommendations, available capacity and load.  PJM has estimated over 15 year planning horizon, 13 different bulk transmission lines are asspected to be overloaded in assumed single contingency events.  In addition, 10 are assumed to be overloaded for two lines on a single structure.  Further explanation of what violations mean. (he’s presuming it’s cumulative, but those subsequent iterations replaced the ones that no longer demonstrated need!)  Overloading of lines due to single contingency events is NERC Category B, while double contingency events are Category C.  A NERC category A evaluates with NO contingencies, and PJM found no violations of category A criteria.  PJM tests for load deliverability and generator deliverability.  Load deliverability addresses defined load levels and ability of xmsn to deliver adequat power.  Generator evaluates ability of generation to be delivered to PJM system at peak load conditions.  Normal Peak Day condition assumes tha based on historical data there’s a 50% chance of being warmer or cooler.  Emergency assumes only a 10% chance that the weather will be any hotter on that day.  NERC category B requires that the system be evaluated with one system out of service, purpose is to ensure that system continues to be reliabile with instantaneous outage.  For Cagoegory B, assumes emergency peak load for area being tested, and normal for rest of system.  For Category C, requires the system be stable and within system limits, under a variety of multiple system events, i.e., lost of one system element, adjustments, and loss of second element.  Double circuit tower line contingency that are the source of the cateogyr C violations projected by PJM in this proceeding.  For thistype, no system readjustments are permitted as both are removed from system at same time, using normal load, that these are rare and not necessarily tied to weather conditions.  Category B violations, PJM projected that violations would occur on two bulk power lines by 2012, and another 3 over next three years.  Over the entire forecast period, PJM estimates 13 lines would have violations of NERC Category B criteria.  12 fail load deliverability, and 1 fails generator deliverability.  Category C, ___ violations, over entire forecast violations, 10 lines would violagte category C criteia.  All of them ae due to failing the PJM generator deliverability test.  The NERC violations reflect PJM’s 2009 retool analysis.  Earlier studies dating back to 2007 resulted in different mix, but the conclusions from each was that NERC criteria would be violated by 2012 if NERC did not take steps.

In the past month, PATH and MAPP were either withdrawn or held in abeyance due to updated analyses that the project was not necessary in the time frame.  The Board directed that an additional hearing be held to determine what impact the delay in these lines would have for need for S-R. During the hearing, Herling reconfirmed PJM’s view that the project would continue to b enecessary to avoid violating NERC criteria as early as 2012.  …  that taking into account RPM auction, would not materially alter the conclusion. (WITHOUT ANY CITES OR SUBSTANTIATION!)

While PJM considered xmsn based alternatives, it found that none were as robust or would provide the long term solution.  PJM’s position with respect to alternatives, such as adding generation, DSM, heightened efficiency, was that it had no power to order added generation or DSM.  PJM’s contention was that transmission was the only measure that it had authority over to correct the violations.

Intervenors argued that the analyses are flawed, designed with a preordained conclusion, were challenging load forecasts, DSM, energy efficiency, and challenges more generally in the conservative nature of the PJM analyses.  As an alternative to outright rejection, some suggest PSEG should hold this petition in abeyance until next RTEP report is in.  Herling would not commit as to when the next RTEP would be completed, suggesting that the typical time frame is in the fall.  Intervenors point out that the latest Retool does not reflect RPM, where significant amounts of demand response capacity cleared, and which would be included as available capacity in the 2012 year, and would also be included in the next RTEP analysis.

Staff’s review of the record leads us to conclude that PJM’s process does not result in a preordained conclusion and produces results that are reasonable.  Intervenors complained that the most recent load forecast is too high, given the load drop.  There is a great deal of uncertainty about economic recovery, and staff does not believe that PJM’s load forecast is unreasonable.  PJM’s load forecast which reflected events since the last quarter of 2008, predicted drop of 1.4%, and actual drop in 2009 was 1.9% (not addressing that peak was in 2006 and it’s been falling).  While the forecast underestimated the severity of drop, it did reflect actual recent trend.  Economic growth projections used by PJM are geared to metropolitan areas located within PJM territory, and cannot be directly compared with national projections. (and PJM historic actuals and PJM trends?)  Staff agrees that the results of the May 2009 RPM auction should be included, but witness Herling explains why even incorporating these results would not alter conclusions.  Intervenors have noted that the May RPM auction resulted in significant demand response in those areas impacted, however witness Herling pointed out that demand response could not resolve Category C violations.  Demand response is not on call during normal periods and is not sufficient time frame to offset Category C violations.  Herling points out that while there was a significant demand response, there was a marked decrease in generation availability in relevant load zones, and net increase was relatively small. (note they never deal in impacts of energy efficiency, which reduces peak overall?)  In contrast, the increases in demand response capacity where PATH amd MAPP were planned were substantial, … those were violations that MAPP and PATH were designed to address.

Intervenors have argued that PJM has failed to consider additional demand response coming, pointing to the New Jersey Energy Master Plan, however the board’s main resonsibility is to assure safe and adequate supply of electricity.  Staff does not believe that PJM excluded the Energy Master Plan from models and consideration. (EH?)  Just as PJM models do not include demand response, it also does not include generation that may or may not occur  (yes it does, as he testified in the initial hearing, with different weights put on generation with an ISA and not).

Staff concludes that PSEG has met its burden that S-R is needed to avoid violations of NERC standards as early as 2010.  The number, nature and severity of the violations all bear this out (Say what?  Decreasing number, decreasing severity, and change in nature in blatant attempt to find some sort of violation).   Realistic variations in the various key inputs would, in staff’s opinion (training, experience, they’re NOT engineers!), still point to violations as early as 2012.  The fact that the violations grow throughout the forecast period points to the need for a robust response (they start at miniscule amounts above 100%, so small that FERC asked about optimization).

Next issue is routing.

Damase Hebert: PSEG presented expert testimony that Route B was most appropriate route.  Luis Berger retained to evaluate routes.  Berger reviewed 3 alternative routes, selected Route B, which follows existing line.  Impacts least area of forested land, impacts least amount of forested wetland, fewer streams crossed, no change in existing land use, crosses Appalachian Trail on existing 230kkV RoW, least distance of Highlands area crossed, all on existing cleared RoW, likely to have the least impact compared to the other alternatives routes because existing RoW would not have to be expand.  Staff recommends approval, because it runs along existing RoW, least impact compared to other route.  Minor adjustments may be appropriate.  Montville has requested move 3 specific towers, and staff reocmmends that Board direct PSEG to relocate or report why it’s not pssible.  In relation to routing issue, STL argued that existing residential homes within a specific distance no longer eligible for FHA.  Baord staff recommends further evaluation of this issue. Switching issues, Jefferson and E hanover, and alternatives were proposed.  Staff recommends moving substations.  Staff notes that use of existing RoW reduces impacts, if approved by board, towers will either be monopole or towers based on characteristics of route.  During course of proceeding, company changed from 4 to 3 conductors, impacts charactteristics of line, change is based on engineering requirements.  Likely to reduce EMF fields. (EH?).  Intervenors have not provided sufficient evidence to prove it’s not safe.  Comapny argues EMF is not dangerous, and EMF are below limits established by any state and regularly used appliances.  Staff has analyzed EMF testimony, and has comcluded that it will be below all established standards, and electrical fields will below NJ’s standards.  Staff recommends that the board require PSEG monitor EMF levels and report results to board, to demonstrate that this meets their state EMF levels.

Cost allocation methodology.  Current PJM tarrif regionalized it across PJM.  FERC has adopted paper hearing, which has been set in response to the remand from 7th circuit decision directing FERC to explain why current methodology is sound (NO IT DOESN”T, that is NOT what remand said and it is not what FERC is requesting in its Order to PJM).  It is unknown when the board will have complete certainty of cost allocation (short paper hearing process, it’s fast tracked).  Given long construction schedule, staff recommends the board not wait until cost allocation (Fox is smiling again at this point)

Staff urges that board issue an order that local zoning does not apply.  Board attach conditions:

– Board direct PSEG to work with Montville Bd of Ed to relocate towers to address their concerns.

– Company follow with report relocating 3 towers to relocate.

– Work in good faith to determine relocation of other alignments that are practicable

– Report within 90 days about other relocations, and if can’t, proceed as proposed.

– Continue to optimize locations of access roads, tower locations and structures, with other agencies to greatest extent possible.

– Evaluate issues explored about inability to obtain FHA mortgages.

– Monitor regarding EMF levels

– Work on continuing basis with fire and safety at Hopatcong and Roseland

– Avian protection plan with guidance from USFWS

– Board require the company to report to the Board the findings of PJM’s next RTEP analysis.  If that RTEP analysis finds that the project is no logner necessary or can be delayed significantly, staff recommends the Board retainspecific authoirty to reopen the proceeding.

– Hopatcong and Roseland switching stations, should routing require modifications, get approval from board.

– This route is located with areas governed by the National Park Service, Highlands Preservation Act and the Watershed Property Review Board.  Staff recommends that the board specifically state in its order that the order shall not be construed as certificate, license, permit to construct or disturb land in these jurisdictions until the company receives the relevant approval from these governing bodies and from any other non-municipal bodies.

Fiordaliso moved, ?? (male) seconded.

Fiordaliso – Having served as hearing officer, which has taken about a year to come to judgment, I feel confident that this board has fulfilled its duty to residents of state of NJ.  Staff committed time and resources, investigating every possible angle, trying to determine whether this is needed, to maintaini electrical service, for all their hard work, I would like to point out certain individuals (thanks staff).  Speed sometimes does not substitute for trying to get it right.  I have to indicate that this was the most difficult decision that I’ve had to make since I’ve been a member of this board, to weigh all the factors involved during the evidentiary hearings.  This was a fair and open process, everyone who wanted to participate could, I wanted them to walk out of the public hearing indicating that they could be heard.  I have heard from the public and witnesses, met with staff, examined every angle of this proposal when PATH and MAPP revelation occurred.  The only thing I could do was to take notice of that, and the supplemental hearing that we had htis month.  With that, it is my contention that it hinges on reliability, increasing infrastructure is a reasonable plan, everyone wants to avoid power outages plaguing our already fragile system.  This project is one part of a wider system, remain focused on renewable, but we have to ensure safe, reliable service for the state of NJ.  PSEG will work with other stakeholders so the process will be a fair and equitable one for all parties.

Butler:  I have nothing to add, I think staff’s analysis was thorough, I’m convinced this is needed.

Fox: Lot of questions and issues.  First, I want to let you know, I reluctantly will be voting for this.  I am hoping that we will not go through this again.  This is an issue of timing, what’s in front of us now (they could choose to wait a couple weeks for additional information that’s in the works).  NERC sets reliability standards, FERC picked NERC, this is based on need, balancing out reliability for the good citizens of this state.  Based on what we have in the record.  What is in the record says there is a need, in 2012.  Timing is everything, PJM projected then, it projects that now, violations in 2012, that’s a little over 2 years away.  It’ll take 18 months or so for this to be constructed.  Our first responsibility is reasonableness of service.  We are subject to a one year time constraint.  If we don’t decide this, we are told this will go to FERC and they will take over the case.  A lot has happened, an economic downturn has taken place, federal government is promoting appliance standards, GHG has not been passed but some day will have to be, NJ will establish more extensive programs to reduce electricity use, a large part revolves about how much it is reduced, we have clean energy, efficiency, renewable energy programs, most of that is not included by PJM.  The Energy Master Plan has reduction of energy use, that is not factored in.  FERC oversees PJM, this board does not.  PJM is largest wholesale power in the world, responsible to NERC and to FERC, they do not report to us (sure, give away your authority over transmission, good idea).  PJM’s RTEP, looks at transmission, generation, customer loads.  The higher the forecast.. PJM’s RTEP, category A, B, C violations were possible, and I think that NERC set these standards and the RTO’s are responsible for following.  Fine?  (from staff: Fine of up to $1 million a day).  Differences between MAPP and PATH, staff has asked for a briefing, two, and it comes down to category C violations, this is not responsive to demand response.  Herling testified that project would still be needed, not directly impacted by load forecast, so we still have this violation, the loss of double circuit line.  The issue I want to get to is risk.  How much risk are we willing to bear, how much are we going to take, prevent that from happening.  Herling had no knowledge of what that risk might be.  Modeling, when I was at EPA we did a lot of modeling, and I am not happy with how this is being handled.  TEAC is contemplateing using sensitivity analysis on load forecast, and the only information we have in the record is from PJM, taking into account different load forecast, using state’s projections, great idea, they don’t do that now.  How much are we going to pay for not having an outage.  Asked to look at actual peak loads in NJ, and it’s quite minimal.  From 06-09, the unrestricted load has exceeded peak for 44 hours.  What is the risk that we’re willing to pay for?  We are used to having outages, when weather occurs, and I’m sure we could probably pay away, that’s a risk analysis that I’m sure had been done.  Is the risk that we’re lessening here worth the cost of a billion dollar line balanced against cost and impacts.  We need to get PJM to look at risk of outage, balanced against category C.  NERC has been modified standards, but again, timing is the issue.  NERC requires RTOs to test events, each has their own internal test, as NERC modifies, they should consider consistent standards, tests, for all future analyses.  Federal Policy Act of s005, set up two NIETC, where here is a huge need, we’re smack in the middle of it, we’re paying more because we’re congested.  The recommendations staff did I thought were good.  I ask that my fellow commissioners to ask the RTO to develop some risk and cost benefit analysis if you don’t require it in their case, why would they), category C violations, having RTOs accountable.  What PJM did was require a billion dollar transmission project.  The existing record I don’t think clearly showed the impact of these violations, that our ratepayers are paying for (and you’ll approve it?  HELLO!?).  That needs to be done for any xmsn lines (like THIS one?).  When the RTO says it exceeds rating, we need to look at the magnitude.  Load forecasting needs to be modified in PJM, direct and indirect costs and benefits, i.e. EMF, does it fit here or not, I think that we really need to look at what raetpayers would pay.  Board has been working on effective alternatives to xmsn, national and regional level.  Our NJ Master Plan deals with that, and it is not in the RTEP model.  No one seems to have jurisdiction over generation. (well duh, you deregulated!).  New generation, existing generation, we don’t have control over instate generation, what goes out of service.  We need most cost effective way to look at generation, it’s probably in Washington, maybe us working with other states.   Due to timing of this issue, and what is in the record before us, there is not any real evidence looking at load forecasting, looking at forecasting, I’m obviously gong to have to vote for this (??? that conclusion makes NO sense) and obviously having reliability issues two years from that.

Nicholas Asselta: The reliability is what strikes me as the most important, infrastructure is what NJ is about today, and in the future, has to continue to move forward to make us economically viable.  We know what our situation is, we know what the situation of the US is in the world competitive market, it is the key for us to retain power.  I bleive this project is needed reliability wise, major imporovements, I support this project.

Elizabeth Randall:  We all went to staff over and over.  The need is critical, the category C violations are important, and it is unacceptable to do nothing, it is important to have reliability.

Fiordalis0: Forgot one of his extended family (moi) in the back.

Board: Unanimous vote.

(BARF – how disgusting can it get)

Susquehanna-Roseland reopened!

January 27th, 2010

open-door

The Susquehanna-Roseland hearing has been reopened.  And off we got to FERC.  It’s been quite a hectic week, with a “flurry” of filings, and here’s the update.  First, remember the NJ BPUat a special 1/15 meeting said they were NOT going to decide on PSE&G’s Susquehanna-Roseland transmission line and said they’d be asking for more information from PJM.  Well, they asked PJM to answer a few questions (though not specific enough, not the right questions):

BPU Secretary letter to PJM

Here’s what PJM had to say:

PJM Letter in response to BPU Query

Suffice it to say, the letter is … ahem… INSUFFICIENT!

And then the responses started coming in, first the Municipal Intervenors, then :

Municipal Intervenors response to PJM Letter

Environmental Intervenors – January 25, 2010

Stop The Lines! January 25, 2010

And the BPU issued an Order reopening the docket and first scheduled a hearing for February 2, 2010, and then THANKFULLY changed it to February 4, 2010:

BPU Scheduling Order Jan 25, 2010

BPU Amended Scheduling Order Jan 26, 2010

The concept is that PJM is coming in as a witness regarding the assertions of their January 21, 2010 bullshit letter, and what does that mean?  Is Steve Herling THE witness, or are there others?  Is whatever witness/es coming with a truckload of exhibits that they’ll dump on us the day of the hearing?  Is he going to be prepared in any way to back up his conclusory and unsupported statements?  So I fired off a couple missives, first Discovery to get the requests in quick and let them be on the record of ignoring or refusing to answer, and then a letter to the BPU with my view of the fine mess we’re in:

STL Discovery re: PJM Letter 1/21/10

STL Letter to BPU 1/25/10

As a sidebar, the escrow that PSE&G had to put out for the Municipal Intervenors is gone, this has been an intense case, and so they’re reasonably asking for more:

Municipal Intervenors – Motion for Escrow

Meanwhile, back at the ranch, remember that great 7th Circuit decision tossing out the cost allocation for this project?  Everything’s been up in the air since then, because if they can’t settle how they’re going to allocate the costs, this sucker won’t be built:

Illinois Commerce Commission v. FERC – August 6, 2009

It was remanded to FERC and after some wrangling, just like in the BPU case, where the utilities were saying, “It’s all there in the record, you don’t need anything more to make a separate decision” and Illinois said quite succinctly, “AHEM, WE DON”T THINK SO!” and FERC issued an Order stating that the record was not sufficient, needed more information and directed PJM to provide some information and also provided some questions for parties to mull over in their comments:

FERC Order January 21, 2010

Here’s the fun part – what they asked PJM to provide (hee hee hee hee hee hee), starting on p. 5 of the above Order:

10. PJM should provide the following information:

A. The total costs that have been approved through PJM’s Regional Transmission Expansion Plan (RTEP) process for facilities that operate at or above 500 kV (and necessary lower voltage facilities), and whose costs are assigned pursuant to Opinion No. 494. For these projects, calculate the total costs that have been assigned to each PJM zone, and estimate the total costs that would be assigned to each zone using PJM’s DFAX methodology.

B. PJM manuals require that, in planning projects, it seek to optimize projects in order to reduce the cost of addressing individual reliability criteria. Describe how the optimization process is performed. Also, explain how PJM determines the relative priorities of resolving numerous reliability issues with one project. For 500 kV and above facilities, explain whether PJM could accurately determine the beneficiaries of a project that resolves numerous reliability issues using its DFAX methodology.

C. PJM’s most recent RTEP report (2008), at P 5 states that:
Baseline thermal and voltage analysis encompasses an exhaustive analysis of all Bulk Electric System (BES) facilities for compliance with NERC Category A (TPL-001), Category B (TPL-002) and Category C (TPL-003) events. In addition, consistent with NERC standards TPL-004, a number of extreme events including those judged to be critical from an operational perspective as well as those defined in Table I of TPL-004 were evaluated for risk and consequence to the system. Describe the types of anticipated reliability requirements addressed by the PJM RTEP (i.e., voltage, thermal, stability). Explain whether and how the DFAX analysis applies to the NERC reliability analyses listed above and any other reliability requirements. Explain whether the RTEP upgrades designed to address these reliability requirements also will address other reliability concerns. In particular, explain whether the geographic location or voltage level of an RTEP upgrade makes that upgrade more likely to address broader reliability concerns.
Provide any relevant studies.

D. In this proceeding, PJM recommended the adoption of a postage-stamp rate design for new 500 kV and above facilities.

1. Describe the benefits generated by such facilities that are not captured in the DFAX methodology used by PJM to allocate costs for lower voltage facilities. Indicate whether such lines provide reliability or economic benefits to the areas producing electricity.

2. Provide engineering or other studies showing any differences in regional benefits between 500 kV and lower voltage facilities (e.g., 345 kV
and 230 kV).

E. Provide any existing engineering or other studies that indicate whether the modeling assumptions used in the RTEP analysis, such as the direction of flow,
remain consistent or vary over time.

The Municipal Intervenors sent in a Motion to FERC, PSEG objected, and then Stop the Lines sent in a Motion for Limited Intervention:

Municipal Intervenors – Motion to Intervene

PSEG Response to Munis FERC Intervention

Stop The Lines! Motion for Limited Intervention

Municipal Intervenors – Renewal of Motion to Intervene

PSEG Response to STL Intervention Motion

PSEG’s response to our Motion to Intervene… yeah… (yawn)… what-ev-er…

And just now, hot off the press, the Municipal Intervenors have filed a Motion to Depose PJM’s Steven Herling!  Oh, yes, this is much needed, so we can get an idea where they’re going and what they plan to present (I doubt they’d produce the pre-filed testimony I requested!):

Municipal Intervenors Motion to Depose PJM’s Herling

As you can see, it’s been an intense few days, and isn’t letting off anytime soon.  More to follow as it develops.

… before they back off on these stupid infrastructure projects?

We finished up the Susquehanna-Roseland hearing today, Stop the Lines has weighed in.  Time to say goodbye to beautiful downtown Newark.

nightny

Experts at power line hearing debate safety of EMFs

For me, the best parts today were:

1) Finally… FINALLY… getting some credible testimony about the capacity of that line.  Let’s see, they’re planning to double circuit it with 500kV, getting rid of the 230kV, but when… and they’ve designed the substations for 500kV expansion.  So DUH!  Here’s the poop:

140C for a 1590 ACSR Falcon @ 500kV – PJM summer normal rating conditions = 1838 amps

4 conductors = 7,352 amps

3 conductors – 5,514 amps or 4,595 MVA

2) Clear statement on the record about the Merchant Transmission’s Firm Transmission Withdrawal Rights:

Neptune 685MW

ECP 330 MW (VFT?)

HTP 670MW

TOTAL: 1,670 MW already heading across the river

And getting those numbers in was not easy, PSEG did NOT want this in the record.  It’s confirmed in the PJM Tariff, STL-12, p. 3 of the exhibit, p. 2 of SRTT-114 (BPU Staff IR).  But there’s something else disturbing going on here.  We were supposed to question Essam Khadr about “Leakage,” which is “New Jerseyian” for the increased coal generation that will be imported if CO2 costs are assessed:

BPU’s RGGI Leakage Order December 17, 2008

That will take some time to wrap my head around.

Here’s PJM’s 3Q bad news, well… good news to me!  Because it continues to go down:

PJM 3Q STATE OF THE MARKET REPORT

And if that’s not enough, here’s the Wall Street Journal:

Weak Power Demand Dims Outlook

By REBECCA SMITH

(See Correction below)

Electricity sales remained weak in the third quarter, prompting speculation that the sluggishness could persist even after the U.S. economy rebounds. Some utilities don’t expect power sales to recover to pre-recession levels until 2012 — if at all — because so many factories have closed.

Getting a read on future demand is crucial for utilities because they require long lead times to build power plants and make other upgrades. Declining sales put pressure on utilities to raise prices, cut costs or make other adjustments to bolster profits.
[Workers last month in Charlotte, N.C., home of Duke Energy. ] Associated Press

Workers last month in Charlotte, N.C., home of Duke Energy.

The sector began to feel the recession, which started in late 2007, later than many others. Sales held up well in the first half of 2008 but then declined and have continued falling this year, though some regions are reporting an uptick. The federal Energy Information Administration expects overall electricity sales to decline 3.3% this year and grow modestly next year, but many utilities anticipate far larger declines for the year.

Duke Energy Corp. said its energy sales to the textile industry based in the Carolinas fell 20% in the third quarter, versus a drop of 13.7% for sales to all industrial users. For the first nine months of 2009, electricity sales to the textile industry were down 23.5%, from the prior year, and overall industrial sales were down 15.8%.

American Electric Power Co. of Columbus, Ohio, which owns utilities in 11 states, saw industrial electricity sales plunge 17% for the third quarter versus the year-ago period. Chief Executive Mike Morris said his company is counting on industrial demand recovering about a third of the lost ground in 2010.

Beyond that, he is wary of making predictions. “I don’t know if we’ll ever get all of it back,” he said, acknowledging that factory closings in the auto sector will have a lasting effect.

Larry Makovich of consultancy Cambridge Energy Research Associates is among the few who believe electricity sales will experience a “strong rebound” next year. “It is dangerous to misinterpret a short-run phenomenon as a structural change,” he said.

Atlanta’s Southern Co., which owns utilities in four Southeastern states, has seen year-to-date industrial demand drop 15%, including a 9.6% drop in the past quarter. Chief Executive David Ratcliffe said he sees signs of recovery, but added that it feels “fragile.”

Bill Johnson, chief executive of Progress Energy, which has utilities in Florida and the Carolinas, said he thinks homes mostly have cut use voluntarily, unlike businesses. Total sales fell 10.9% in the first nine months of the year across all customer categories, led by industrial sales that dropped 11.4% in the Carolinas and 12.9% in Florida.

“I think there’s still a high level of concern and a great deal of unease” about the economy, Mr. Johnson said, adding that he doesn’t expect a sharp recovery.

Bob Shapard, chief executive of Oncor in Dallas, said he thinks the drop in energy use in 2008 “was so quick that it wasn’t structural but was probably cyclical.” Nevertheless, he said he doesn’t expect a full recovery in total sales volumes until 2012.

Portland General Electric in Oregon saw residential sales rise 4.6% for the quarter, but the gain was offset by a 5.3% drop in industrial sales.

Utility analyst Chris Ellinghaus at Shields & Company in New York said he isn’t hopeful the sector will recover next year but thinks “2011 will look more normal.”

Just in, the New Jersey Board of Public Utilities has delayed the Evidentiary Hearings for PSE&G’s (and PJM’s!) Susquehanna-Roseland transmission line, from the week of October 19 to the week of November 16!

BPU Amended Scheduling Order 2009-09-11

Even better, the Discovery that was due right now is now not due for two more weeks! Two more weeks of figuring out how to torture those poor witnesses for PSE&G!!

For more info, see STOP THE LINES!

And that fits well with the CapX 2020 Brookings hearings, that were supposed to begin November 23 but now probably starting the week after.

fredonschool Fredon School

Dig this:

“Visual simulation” of what towers will look like compared with present strutures

The Susquehanna-Roseland transmission line through Pennsylvania and New Jersey is getting a little hairier, YEAAAAA.  Fredon PALS, a group centered around the Fredon School, which is facing transmission lines over its property(school, above), sent their first Discovery over the bow today.  It’s good stuff, I love it when this happens.

Fredon PALS – First Set of Discovery Requests to PSE&G

Until now, we’d been the only Intervenors who’d sent PSE&G any Discovery, Stop the Lines, that is, and with this filing today, Welcome to the Club, Fredon PALS!!!