Susquehanna-Roseland reopened!

January 27th, 2010

open-door

The Susquehanna-Roseland hearing has been reopened.  And off we got to FERC.  It’s been quite a hectic week, with a “flurry” of filings, and here’s the update.  First, remember the NJ BPUat a special 1/15 meeting said they were NOT going to decide on PSE&G’s Susquehanna-Roseland transmission line and said they’d be asking for more information from PJM.  Well, they asked PJM to answer a few questions (though not specific enough, not the right questions):

BPU Secretary letter to PJM

Here’s what PJM had to say:

PJM Letter in response to BPU Query

Suffice it to say, the letter is … ahem… INSUFFICIENT!

And then the responses started coming in, first the Municipal Intervenors, then :

Municipal Intervenors response to PJM Letter

Environmental Intervenors – January 25, 2010

Stop The Lines! January 25, 2010

And the BPU issued an Order reopening the docket and first scheduled a hearing for February 2, 2010, and then THANKFULLY changed it to February 4, 2010:

BPU Scheduling Order Jan 25, 2010

BPU Amended Scheduling Order Jan 26, 2010

The concept is that PJM is coming in as a witness regarding the assertions of their January 21, 2010 bullshit letter, and what does that mean?  Is Steve Herling THE witness, or are there others?  Is whatever witness/es coming with a truckload of exhibits that they’ll dump on us the day of the hearing?  Is he going to be prepared in any way to back up his conclusory and unsupported statements?  So I fired off a couple missives, first Discovery to get the requests in quick and let them be on the record of ignoring or refusing to answer, and then a letter to the BPU with my view of the fine mess we’re in:

STL Discovery re: PJM Letter 1/21/10

STL Letter to BPU 1/25/10

As a sidebar, the escrow that PSE&G had to put out for the Municipal Intervenors is gone, this has been an intense case, and so they’re reasonably asking for more:

Municipal Intervenors – Motion for Escrow

Meanwhile, back at the ranch, remember that great 7th Circuit decision tossing out the cost allocation for this project?  Everything’s been up in the air since then, because if they can’t settle how they’re going to allocate the costs, this sucker won’t be built:

Illinois Commerce Commission v. FERC – August 6, 2009

It was remanded to FERC and after some wrangling, just like in the BPU case, where the utilities were saying, “It’s all there in the record, you don’t need anything more to make a separate decision” and Illinois said quite succinctly, “AHEM, WE DON”T THINK SO!” and FERC issued an Order stating that the record was not sufficient, needed more information and directed PJM to provide some information and also provided some questions for parties to mull over in their comments:

FERC Order January 21, 2010

Here’s the fun part – what they asked PJM to provide (hee hee hee hee hee hee), starting on p. 5 of the above Order:

10. PJM should provide the following information:

A. The total costs that have been approved through PJM’s Regional Transmission Expansion Plan (RTEP) process for facilities that operate at or above 500 kV (and necessary lower voltage facilities), and whose costs are assigned pursuant to Opinion No. 494. For these projects, calculate the total costs that have been assigned to each PJM zone, and estimate the total costs that would be assigned to each zone using PJM’s DFAX methodology.

B. PJM manuals require that, in planning projects, it seek to optimize projects in order to reduce the cost of addressing individual reliability criteria. Describe how the optimization process is performed. Also, explain how PJM determines the relative priorities of resolving numerous reliability issues with one project. For 500 kV and above facilities, explain whether PJM could accurately determine the beneficiaries of a project that resolves numerous reliability issues using its DFAX methodology.

C. PJM’s most recent RTEP report (2008), at P 5 states that:
Baseline thermal and voltage analysis encompasses an exhaustive analysis of all Bulk Electric System (BES) facilities for compliance with NERC Category A (TPL-001), Category B (TPL-002) and Category C (TPL-003) events. In addition, consistent with NERC standards TPL-004, a number of extreme events including those judged to be critical from an operational perspective as well as those defined in Table I of TPL-004 were evaluated for risk and consequence to the system. Describe the types of anticipated reliability requirements addressed by the PJM RTEP (i.e., voltage, thermal, stability). Explain whether and how the DFAX analysis applies to the NERC reliability analyses listed above and any other reliability requirements. Explain whether the RTEP upgrades designed to address these reliability requirements also will address other reliability concerns. In particular, explain whether the geographic location or voltage level of an RTEP upgrade makes that upgrade more likely to address broader reliability concerns.
Provide any relevant studies.

D. In this proceeding, PJM recommended the adoption of a postage-stamp rate design for new 500 kV and above facilities.

1. Describe the benefits generated by such facilities that are not captured in the DFAX methodology used by PJM to allocate costs for lower voltage facilities. Indicate whether such lines provide reliability or economic benefits to the areas producing electricity.

2. Provide engineering or other studies showing any differences in regional benefits between 500 kV and lower voltage facilities (e.g., 345 kV
and 230 kV).

E. Provide any existing engineering or other studies that indicate whether the modeling assumptions used in the RTEP analysis, such as the direction of flow,
remain consistent or vary over time.

The Municipal Intervenors sent in a Motion to FERC, PSEG objected, and then Stop the Lines sent in a Motion for Limited Intervention:

Municipal Intervenors – Motion to Intervene

PSEG Response to Munis FERC Intervention

Stop The Lines! Motion for Limited Intervention

Municipal Intervenors – Renewal of Motion to Intervene

PSEG Response to STL Intervention Motion

PSEG’s response to our Motion to Intervene… yeah… (yawn)… what-ev-er…

And just now, hot off the press, the Municipal Intervenors have filed a Motion to Depose PJM’s Steven Herling!  Oh, yes, this is much needed, so we can get an idea where they’re going and what they plan to present (I doubt they’d produce the pre-filed testimony I requested!):

Municipal Intervenors Motion to Depose PJM’s Herling

As you can see, it’s been an intense few days, and isn’t letting off anytime soon.  More to follow as it develops.

Leave a Reply