Where were you the night of June 25, 1998?
January 13th, 2020
The June 25, 1998 blackout report needs to be on the interwebs available to the world.
June 25, 1998? That’s the night of the transmission fail that disconnected the Midwest from the Eastern Interconnect. That question was asked by Minnesota Power’s attorney of each and every witness, I think other than MP, but maybe MP witnesses too, in the Arrowhead transmission project hearing, circa 1999-2000. There were cries of “Hospitals will go dark without the Arrowhead project,” “We’re going to freeze in the dark in an incubator” which became “We’re going to freeze in the dark on a respirator without a job” — it was so histrionic.
The Arrowhead transmission project was project 13J of the WRAO Report, and the WIREs Report, which presented many transmission lines, but chose the Arrowhead transmission project as the “be all and end all” of transmission in the Midwest, that it would fix all the transmission problems:
The hearing went forward, 2 weeks in Minnesota, where MP got an exemption from Minnesota Power Plant siting law, and for TWO MONTHS in Wisconsin, for Round 1, then 2 weeks after the cost went way up, and another 3-5 days of hearing later when cost went up again. They got their permit, it’s up…
But in that first hearing, I did get to introduce the report that showed that the June 25, 1998, blackout was NOT caused by too little capacity, it was not caused by an unreliable transmission system. It was caused by corporate greed, transmission operators running the Prairie Island-Byron 345kV’s TCEX flow over the limit, disregarding operating guides, and disregarding requests and demands to ramp the power down, violating MAPP Operating Standards and NERC Operating Policies. SHAME, NSP, SHAME!!! And MP was so tacky, trying to attribute their desire for bulk power transfer to the blackout, that the Arrowhead project would save us. Yeah, right…
Here’s the report, below, it’s a gem, I’m posting this today because I’m shoveling off my desk and there are a lot of gems here, so posting them will get them out into the world in perpetuity — can’t disappear something from the internet! Scanning them in is taking a while, a royal and dusty pain in the patoot, but just for you inquiring minds, HERE IT IS:
Here are a couple snippets, starting with p. 2:
Bottom line?
OPERATE WITHIN OPERATING GUIDE LIMITS!!
DOH!
The report goes on and on with stupid human tricks – the flow was NOT reduced by NSP System Operators:
From pps 10-11:
So if the operators had been doing the job, not focused on keeping that line operating with all that power flowing through it, selling that power, the blackout may not have happened. Great…
And for some reason, NSP operators were not communicating:
300 MW above the operating guide limits:
OPERATE WITHIN OPERATING GUIDE LIMITS!! DOH!
Operator error is a too-generous way to put it — but for the efforts to NOT reduce power flows, the inadequate response of system operators and their failure to communicate the degree of the problem, the blackout may not have happened. And then utilities have the nerve to say that because of the June 25, 1998 blackout, we need the 13j Arrowhead transmission project?
Xcel wants to sell coal on market… DOH!
January 10th, 2020
How many years have I been saying that the purpose of this massive transmission build-out is to market coal elsewhere? Decades, folks, it’s been decades… And this latest from Xcel Energy, Notice of Comment period just out today, is demonstration that they plan to keep running those coal plants and selling it. Will the Public Utilities Commission care?
Here’s the newly released Xcel Energy plan, and a comment period:
The plan?
Here’s the Notice:
What to comment about? From the Commission’s Notice:
Bulk power transfer was the whole point of the transmission build-out, to be able to sell anything generated at any Point A to any Point B. And then coal generated here could be sold elsewhere, eastward via transmission, while we use generation that isn’t quite so dirty (but that’s dirty in its own way). We’re so clean here in Minnesota… NOT! We’ve been a pass through for Dakotas’ coal for a while, and now, they’re asking permission to keep burning coal here and send that energy eastward.
They built all that transmission, no Commission I’ve seen has ever found a transmission plan they didn’t like and roll over for, and now we’re paying for it. Rate increases anyone? Are you paying attention to what’s pushing those rates up?
Why ever would I say that it’s all about selling coal? Well… there’s a bit of a pattern going here. There was the Chisago project, starting in 1996 and three iterations in Minnesota and Wisconsin, not to mention the WRAO report:
WRAO laid out many transmission lines and the Arrowhead transmission project, circa 1999, was selected as the be all and end all of transmission after many hearings were held, one hearing in Minnesota and THREE before Wisconsin PSC, the price kept going UP, UP, UP!
But then on September 8, 2001, a meeting with likely intervenors to see if they could be convinced to “approve” of the SW Minnesota 345kV line, remember that, Commissioner Matt Schuerger? I pointed out all that coal lined up in the SW MN 345kV study… and from there on to the SW MN 345kV line, part of ABB plan for coal:
Don’t ya just love that name? It says it all. Why the ABB Lignite Vision 21 Transmission Study? The opening paragraph, linked above, DOH! says:
The SW MN 345kV line was the part that’s running east to west on the lower part of that yellow map, from Split Rock sub to Lakefield Junction. Some claimed it was an “It’s for WIND!” line, but that’s a lie, just read that ABB study again. The powerflows showed that it wasn’t to carry energy off of Buffalo Ridge, there was just 213-302 MVA coming off Buffalo Ridge into the over 2,000 MVA capacity line:
How stupid do they think we are? Well, money talked, and that money ruled the day. That SW MN 345kV line and the TRANSLink Settlement Agreement and 2005 Transmission Omnibus Bill from Hell (and changes to Minn. Stat. 117.189) laid the groundwork to bring us $2+ BILLION of CapX 2020:
And then the MISO MVP 17 project portfolio, now over $6 BILLION:
And then they have the audacity to suggest we need MORE transmission?
Upper Midwest utilities to study transmission grid in light of ambitious carbon reduction goals
So please explain how selling coal generated electricity on the MISO market is consistent with carbon reduction goals?
What a crock…
RUS Scoping Meetings for Cardinal-Hickory Creek xmsn
December 6th, 2016
Slow evening at Rural Utilities Service’s scoping meeting for the Environmental Impact Statement for the Cardinal – Hickory Creek transmission project. RUS is involved because Dairyland Power Cooperative (DPC) plans to hold a 9% undivided interest in the project, and are looking to RUS to provide the funding. RUS held two more meetings, following on prior meetings October 31 and November 1 & 2, because their notice for those meetings went out a day late, so another Notice went out:
Notice of Intent To Hold Public Meetings and Prepare Environmental Impact Statement (October 18, 2016
Where’s my prior post on these meetings? It’s gone! Here’s the dates and locations (click for larger version) — the last one is tomorrow in Barneveld, Wisconsin:
So to make quick work of it, this is cut and pasted from the RUS Cardinal Hickory Creek page:
Alternatives Evaluation Study (July 2016)
Notice of Intent To Hold Public Meetings and Prepare Environmental Impact Statement (October 18, 2016)
Macro-Corridor Study (September 2016)
Alternative Crossings Analysis (April 2016)
- ACA Table of Contents
- ACA Main Report Chapters 1-5
- ACA Main Report-Chapter 6-References
- ACA Appendices
SCOPING MEETINGS
I had a quick chat with Dennis Rankin who’s in charge of the environmental review on this and the Dairyland Q-1 South projects, and had a few quick things to register, particularly that ATC has announced that the project is delayed:
ATC postpones Cardinal-Hickory Creek project – The Dodgeville Chronicle -Dodgeville, WI
I had this article and a few comments to add tonight, and will file more detailed comments before the deadline — now January 6, 2017.
(don’t worry, I’ll get this looking pretty by the deadline!)
On the way in, there was new transmission marching across the countryside, so ugly:
And look how close to this house in New Vienna, right up near the garage, and not far from the house either — this line cut right through the middle of town:
But all in all, it was a beautiful day for a drive today!
Public participation? Tough in Xcel rate case
July 14th, 2016
Last night there was a hearing in Mankato on the Xcel Energy rate case (Docket E002/GR-15-826). Public participation in Public Utilities Commission dockets is supposed to be a happenin’ thang… But there were no witnesses to question yesterday at the public hearing, and the Xcel representative who was there could not answer questions. Worse, there was no commitment to have witnesses available to the public at the public hearings, and only advice that the public could attend the evidentiary hearing. ATTEND?!? When might we be able to question witnesses?
Sent this Data Practices Act Request this morning to round up the Information Requests and Responses regarding transmission, transmission riders, MISO and FERC:
Xcel Energy wants to shift its transmission rate recovery from CWIP and AFUDC to general rates, but there was no one there to talk about it. These are the MVP projects at issue, in Schedule 26A, below, which are worked into MISO tariff and FERC blessed:
And here’s the projects in Schedule 26, below, but hmmmm, no project costs shown (click for larger view):
Exhibit 1A – XcelCover_e21_Request for Planning Meeting and Dialogue – PUC Docket 14-1055
Exhibit 1B – e21_Initiative_Phase_I_Report_2014 – Xcel Filing PUC Docket 14-1055
Exhibit 2_MISO Schedule 26A Indicative Annual Charges_02262014
Exhibit 3 – FERC EL-14-12-002_ALJ Order – ROE on MISO Transmission
Next meeting I’ll have some more:
e21_MikeBull_Center for Energy and Environment
MISO Schedule 26 Indicative Annual Charges
1Q_Earnings Release Presentation_5-9-2016_1500085150
Investor Presentation – NYC-Boston_3-1-2=16_1001207698
Back to last night’s hearing…
Check the rules about public participation:
1400.6200 INTERVENTION IN PROCEEDINGS AS PARTY.
Another, the PUC practice rules:
And yet another:
And this one (though they’ll say it isn’t applicable because a rate case isn’t part o the Power Plant Siting Act):
1405.0800 PUBLIC PARTICIPATION.
At all hearings conducted pursuant to parts1405.0200 to 1405.2800, all persons will be allowed and encouraged to participate without the necessity of intervening as parties. Such participation shall include, but not be limited to:
Encourage public participation? Yeah, right…
February 10th, 2016
Here we go, thanks to Xcel Energy and Office of Administrative Hearings, based on the bias and double standards for participation and obstructions to intervention in the latest Xcel Energy rate case (PUC Docket GR-15-826).
Yes, Intervention in the rate case denied again:
And I quote:
Further, the Petition states that purposes for which No CapX 2020 was “specifically formed” (fn omitted) was to participate in dockets which are now closed, raising the question of why No CapX 2020 continues to exist.
H-E-L-L-O?!?!?! This rate case docket is all about shifting the CapX 2020 and MISO MVP 17 project portfolio transmission costs from one scheme to another. I specifically cited all the references to CapX 2020, MISO MVP, and transmission.
Intervention Petition II
Intervention Petition I
20161-117574-01_Order Denying Intervention Petition 1
No CapX 2020_Response to Xcel’s Objection
20161-116957-02_Xcel’s Objection to Intervention
NoCapX 2020 and Carol A. Overland_Intervention Petition Packet
And in a parallel track, note the double standard in pleading.
- Note that Xcel has objected only to the Overland/No CapX 2020 intervention.
- Note that Xcel has not objected to those who participated in the “e21 Initiative” which is the basis for this rate case “multi-year rate plan” and transmission shift.
- Note how little the other “intervenors” say.
- Note they do not state their interests.
- Note they do not state how their interests are different from general ratepayers.
- Note they do not state how their interests will not be represented by OAG and Commerce.
OAH has approved Interventions of “The Commercial Group,” “Suburban Rate Authority,” and “City of Mineapolis.” I’m sure the approval of “Clean Energy Organizations” will soon follow, despite the lack of specific pleading and the apparent conflict with one “attorney” representing so many organizations that either have differing positions and interests, or which are adequately represented by other organizations and don’t need to intervene… funny how this double standard works…
Read the Petitions:
Petition to Intervene of the Commercial Group
Petition to Intervene of Suburban Rate Authority
Petition to Intervene 0f City of Minneapolis
Check out each of these petitions. Look at the pleading, what’s stated, and as importantly, what is NOT stated. What are their interests? How are the “interests” different than general ratepayers in their class? How are their interests not represented by Office of Attorney General and/or MN Dept. of Commerce?
So what to do? Participating in the public hearing is not sufficient, and if that’s the limited offering, well, there’s no Discovery for a public participant. What’s next? Fight for the privilege of an unfunded intervention, as if there’s nothing else to do? The issues raised by Overland/No CapX 2020 will not be addressed otherwise. And thos overt quashing of participation is not consistent with the “public” in “Public Utilities Commission” and the Commission’s mandate.
Meanwhile, FERC just denied the 2010 Petition for Intervention too in the case regarding the cost allocation for these CapX and MISO MVP projects, yes, that took them 5 1/2 years to do, so why now? Check this out:
Odd that should come up now… naaaah, not really.