Minnesota Power’s Arrowhead-Weston Transmission Project was probably the longest and most torturous transmission project in Minnesota and Wisconsin, at least, if not worse, than CapX 2020 Hampton to La Crosse. Arrowhead_Weston ran over a less than 15 mile distance in Minnesota, crossing over the St. Louis River near Duluth, and the over into Wisconsin where it headed down to the Weston coal plant.

World Organization for Landowner Freedom (W.O.L.F.) intervened and showed up for years in the various proceedings for this transmission project. There was a two week hearing in Duluth (MEQB Docket: MP-HVTL-EA-1-99), I’d started that in a tent in a friend’s back yard, and we were officing in the garage… then off to Madison for a two month hearing (PSC Docket 05-CE-113), which after initial CPCN approval went on through 3 iterations due to cost increases and routing through Douglas County, Wisconsin. FYI,weird, the A-W EIS is HERE in the Library of Congress files, along with other Wisconsin utility EISs:

Anyway, throughout most of this fiasco, other than the very end, World Organization for Landowner Freedom intervened and participated with gusto. In Minnesota, we raised the issue of noise, which as found in the ALJ’s Findngs of Fact, would be too high (lots on noise search the pdf for more) and lack of need for this project, that the applicants were misstating need, claiming we’d all freeze in the dark in an incubator/on a respirator without a job. Over and over, the Applicants’ attorneys asked, “And where were you on June 25, 1998?”

As to noise:

And in the ultimate EQB Order regarding noise:

Regarding the initial Arrowhead-Weston applicants claim, circa 1999, that Arrowhead-Weston transmission was needed, was our finding in the “repository” the proof positive that the June 25, 1998 outage was self-inflicted, that the trip of the line and the resulting wave of outages across the Midwest, was due to the operators failing to ramp down those bulk power transfers that were far over the operating limits for the King-Eau Claire-Arpin line! Here’s that report from the Mid-Continent Area Power Pool, the “MISO” of that day:

And another report entered into the record, another issue of “high exports” that triggered disaster when system couldn’t handle an outage when all that power was being exported:

For these reasons, bulk power transfer was a concern due to utilities’ practice of overloading the system for their marketing gain. Soooooo… the other thing accomplished, other than noise, was a limitation of 800 MVA at the Arrowhead substation, which means that the line cannot be used for extreme bulk power transfer. From the EQB’s Findings of Fact and Order::

… and…

Recently, Minnesota Power has applied for permit from the Public Utilities Commission to “modernize” its AC to DC system, as the converters are ? way, way older than their expected 30 year lifetime. MP’s need statement for the project is based on the age of the DC to AC conversion equipment, that those converters are no longer made, and that parts are difficult to find. Hence, time for replacements to keep that line going.

The Commission did agree to a joint permitting process for “need” and “routing” (a very short line from the old substation to the new one. See PUC Dockets E015/CN-22-607 and E015/TL-22-611:

The purpose of this project is to facilitate use of the Center, ND to Arrowhead substation going forward. That’s a line that Minnesota Power bought a few years back, “for wind,” though I’m not really convinced. That line was built eons ago. Here’s the plan in short, from the application:

There were scoping meetings held for the Environmental “Assessment,” months ago, with comments due September 13, 2023.

Then, the comment period was extended by DOC-EERA for “residents that are farther than 1/4 mile outside of the project boundary.” R-E-S-I-D-E-N-T-S

Bit in swoops American Transmission Company, with a late filed comment with an “alternative” proposal!

READ THIS!

To which Minnesota Power had a well crafted and detailed reply, here’s the gist, but it’s SO well-written, worth a careful dissection:

Then ATC had this to say:

And based on the late ATC filing, Commerce-EERA recommended:

Then issued its Scoping Decision filed December 1, 2023:

BUT, the Commission has a meeting on November 29, 2023, and discussed this EIS Scoping and the ATC Alternative and sent it over to OAH for a contested case.

And then, AFTER the Commission’s Order and Commerce-EERA Scoping Decision is released, long after the Comment period over, ATC submits a CHANGE!

So Commerce-EERA files a REVISED scoping decision, including this new change! REALLY!

I’m recalling that offering system alternatives and routes that did not “meet the need” of the project proponent were rejected out of hand.. but this is OK?!?!?!?!

What ATC is proposing is as Minnesota Power states, a plan to circumvent the Arrowhead-Weston substation limitation of 800MVA by physically, electrically, going around the transformers in the substation!! AND it gets worse, ATC is openly wanting, planning, on EXPANSION! WHAT?!?!

ATC has intervened in these two dockets:

To further this goal, they’ve recruited FIVE (5) big buck Minnesota and Wisconsin attorneys:

And World Organization of Landowner Freedom?

W.O.L.F. is on alert!

Comments – Biennial Xmsn Report

November 11th, 2021

The Notice of Comment Period has been issued:

Here’s the plan to review:

2021 Biennial Xmsn Projects Report

Here’s the poop:

How to file comments? See below, and be sure to ask to be on the service list! If you want live links to make it easier, use link to Notice above.

AC-SL-Projects-Map

Here’s the decision:

Line 67 ruling Dec 2015

This decision is important because it is not just this pipeline — because the basis for it is the Presidential Permit, and the notion that issuance of a Presidential Permit may not be appealed applies to the Presidential Permit for the (Not-so) Great Northern Transmission Line too!

ProjectMap

Hot off the press, just filed:

Menahga_Comment of Andersen_FINAL

Overland_Andersen_Comment_FINAL

Whew, now back on the road!

Others filed today:

Comments_GRE-MP_201511-115396-01

DOT Comments_201511-115379-01

DNR Comments_201511-115391-01

Comments were due today on Minnesota Power’s request for Exemptions from the rules governing content of Applications for a Certificate of Need for a transmission line.

map01

Look at the red on that map — potentially affected areas where MP is looking to put a transmission line.  WOOOOO-EEEE, that’s a lot of land!

Minnesota Power’s proposed Great Northern Transmission Line is inching along in the Certificate of Need process.  Here’s Minnesota Power’s site:

Great Northern Transmission Line page

And to look at the full docket, go to www.puc.state.mn.us, click on “Search eDockets” and search for 12-1163.  The application is expected sometime in March or so, but I’d guess it will be later.

Here’s how they plan to let people know about the project — it was filed a while ago, Comments were due, and I tried and tried to get people to comment, oh well, here’s what was filed about the Notice Plan filed in October and the Comments filed in November:

MP Great Northern Transmission Line Notice Plan

Commerce Comments on MP’s GNTL Notice Plan

Overland Notice Plan Comments

That’s sitting at the PUC now.  So where are we?  Just starting out…  Here’s a diagram of the hoops for the PUC process, edited a bit by yours truly for handouts at the meetings a couple months ago, we’re at the very first box in the chart:

puc-process-edited1

Today, comments were due on the Minnesota Power request for Exemptions from some specific rules, Reply Comments, that is.  Here’s what’s been filed:

Minnesota Power Exemption Request

Commerce Comments – Exemptions Request

MP Exemptions Reply Comments

Overland-Legalectric Reply Comments