Yes, MISO is at it again, no, not the good MISO as above, but the other MISO, the Midcontinent Independent System Operator, Inc. Once again, they’re asking FERC for termination of a Generation Interconnection Agreement (GIA) for the failed and revoked Goodhue Wind Project, the part with MISO queue number H062 (it’s been assigned Docket No. ER15-254-000).
This is the docket that never ends, but keeps inching toward the cliff. For all intents and purposes it’s over, but here’s another housekeeping detail. It’s permits are revoked, the Minnesota Public Utilities Commission has closed the docket… but wait… didn’t they already do this in August?
Mastic’s H061 & H062 Interconnection Agmts TERMINATEDAugust 18th, 2014
Here’s the FERC Order in docket ER14-1684-000, about H062 from then:
20140606-3034(29458634)_OrderAcceptingNoticeOfTerminationH062
I’ve asked the MISO attorney for clarification. Will report back on any response.