IGCC, and Excelsior Energy’s Mesaba Project
September 6th, 2010
A couple of days ago, a little birdie sent me an uplifting article, and what I like most about it is the use of the term “boondoggle,” which is the definition of Minnesota’s “own” Mesaba Project:
If IEEE’s Spectrum is using that term, the rest of the world can’t be far behind!
We’ve been having quite a few go-rounds about Mesaba lately, since Iron Range Resources unilaterally decided to significantly and substantively alter the “contract” for the $9.5 million in funding. I’d started a post on that and can’t find it for the life of me, so here we go… Now remember, this is not including the state’s Renewable Development Fund money or the DOE’s money thrown at this project, this is “only” the state IRR’s money, $9.5 million, and the interest on that “loan” is 20%:
MCGP Exhibit 5023 – IRR & Excelsior Convertible Debenture Agreement
You’ll find that interest rate on p. 12, 20% simple interest per annum on the outstanding principal. Since they’ve paid nothing on it except the $40k that they were found to have spent improperly (with many other issues not addressed because the IRR had “destroyed” documentation… yeah, right…), 20% simple interest per annum on a “loan” from 2004 means that there’s another $8,000,000 due now. And this does NOT take into account the initial $1.5 million from IRR, it’s just the agreement above.
And as noted above, a couple of weeks ago, it seems the IRR unilaterally decided to significantly and substantively alter the “contract” … based on exactly what???
Here’s how Commissioner Sandy Layman characterized the predicament:
The principal balance owed by Excelsior Energy, Inc. to Iron Range Resources under the
existing loan documents is $9,454,962.
No mention is made of the more than $10 million in interest. Nada…
Here are two of Aaron Brown’s posts:
Excelsior Energy to seek huge break from Iron Range Resources
… and …
This Iron Range blogger is done apologizing for Iron Range cronyism
Here’s Charlotte Neigh’s editorial, published in the Grand Rapids Herald-Review and on the Citizens Against the Mesaba Project site:
IRR WRITES OFF $ MILLIONS OWED BY EXCELSIOR ENERGY
Mesaba Project appellate decision
May 18th, 2010
It’s out, and although the court rejected the arguments of Excelsior Energy saying they didn’t get enough out of the PUC, and rejected the arguments of Minnesota Power and Xcel Energy, the bottom line is that the Public Utilities Commission won, their Order stands, and so in a small way, Excelsior Energy has “won.”
There were three issues before the court:
I. Did the commission err in determining that the Mesaba project is an IEP under Minn. Stat. § 216B.1694, subd. 1?
II. Does Minn. Stat. § 216B.1694, subd. 2(a)(7), require the commission to undertake its traditional public-interest evaluation?
III. Was the commission’s application of the IEP statute to Excelsior’s PPA arbitrary and capricious or unsupported by substantial evidence?
Bottom line?
We defer to the commission’s expertise as to the definition of the technical term ―traditional technologies.‖ The commission’s decision that the Mesaba project is an IEP is supported by substantial evidence.
The commission has the statutory authority to consider the public interest in evaluating the terms and conditions of an IEP’s PPA. Its decisions in this regard are supported by substantial record evidence and are not arbitrary and capricious. Accordingly, the commission did not err in concluding that Excelsior’s proposed power-purchase agreement with Xcel is not in the public interest under Minn. Stat. § 216B.1694, subd. 2(a)(7).
Here’s the full decision, issued today at 10:00 a.m.
May 18, 2010 Excelsior Energy-Mesaba Project Appellate Decision
Excelsior Energy files Mesaba Project appeal
August 7th, 2009
Oh happy day…
Here’s the Excelsior Energy Mesaba Project appeal, hot off the “press” from a little birdie:
I’d love to weigh in, but the freight’s a little steep for recreational pleadings…
Thanks, little birdie!
Mesaba Project’s “procedural reconsideration”
November 25th, 2008
So what the hell is a “procedural reconsideration?” Today the PUC had the never-ending (until May 1, 2009) saga of Excelsior Energy’s Mesaba Project. The issue? Yet another Motion to Reconsider from Excelsior Energy, they don’t want to take NO for an answer.
The PUC staff recommended reaching the hand toward the life-support plug, but not yanking it with a final decision:
Staff acknowledges the comments of Minnesota Power requesting the clarification of whether the Commission’s approval or denial of Excelsior’s petition for reconsideration at this time constitutes a final decision for purposes of appellate review. In the alternative, the Commission will not enter a final decision until May 1, 2009, the deadline for negotiations. As such, Staff believes that the most judicially efficient course would be for the Commission to grant the petition for reconsideration for procedural reasons and hold further consideration in abeyance until after May 1, 2009.
Briefing papers, p. 13. And so they voted unanimously for alternative 1:
Grant the petition for reconsideration and rehearing for procedural reasons and hold further consideration in abeyance until after May 1, 2009.
For the whole Excelsior Energy saga, GO HERE and search for Docket 05-1993. And if that’s not enough, search also for 06-668!
So we’re still holding… zzzzzzzzzzzzzzzz
Excelsior Mesaba Project siting hearing
February 1st, 2008
Above — the mittens (approximation) the judge was wearing at the hearing, big brown leather — DURING the hearing, yes, it was indeed a cold day in hell…
The “siting” hearing for Excelsior Energy’s Mesaba Project was Tuesday and Wednesday, that’s the long dead IGCC/coal gasification plant that keeps hanging on as we beat that equine’s bloated and stinky carcass. It was bizarre, but it’s hard to tell how far back to go in detailing the bizarreness… and I’m a little cranky, having sat most of the 20 degrees below zero day in an unheated gym attached to the Hoyt Lakes Arena (they couldn’t turn the heat on because when they did, the blowers made so much noise we wouldn’t hear anything but the blowers). The first day went pretty well, we did get through a few witnesses with some good issues raised in the record, so good for our side that the second day the process was shut down. They rammed through all the witnesses through at once, before any public questioning was allowed, and it wasn’t until around 7 p.m. or later that we could get started.
How far back to go… It really started back in Big Stone II, I think, but I’ll stick to this docket for now… First large weirdness in this docket was the ALJ’s Prehearing Order granting intervenor status to Xcel, Minnesota Power, and Public Energy-Mesaba (coalition of groups actively challenging Mesaba), and then there was the Prehearing Order that those not submitting prefiled testimony would no longer be intervenors and could not participate as intervenors, only as members of the public! Really!
In that Fourth Prehearing Order, it was noted that there would be a Phase I and Phase II as provided by Minn. R. 1405.1500:
1405.1500 SEQUENCE OF PROCEEDINGS.
STAT AUTH: MS s 116C.66; 216E.16
HIST: L 1984 c 640 s 32; 17 SR 1279
Current as of 08/21/07
About this time, I saw trouble coming… So anyway, when Xcel, Minnesota Power and Public Energy-Mesaba did not submit Pre-Filed Testimony, we got the ax, we were out as Intervenors. THERE WERE NO INTERVENORS IN THE EXCELSIOR ENERGY – MESABA PROJECT DOCKET!!! That happened in Prehearing Order 5:
which said, in pertinent part:
4. Because they have failed to file testimony when due, Xcel Energy,
Minnesota Power, and Public Energy—Mesaba are denied further participation as
parties in this matter. They shall remain on the service list and may participate as
members of the public and interested persons as set forth in the First Prehearing Order
(January 19, 2007).
So let’s go back to that First Prehearing Order:
Note the foreshadowing:
3. Any person desiring to become a formal party must file a Petition to
Intervene by February 12, 2007. Any person petitioning to intervene after that date may
be restricted as to the scope of their participation. Any existing party that wishes to
object must file an objection within seven days of service of the petition. Petitions to
Intervene should comply with Minn. R. 1400.6200.
5. Members of the public need not become formal parties to participate in the
hearings. Members of the public may offer either oral or written testimony, may offer
exhibits for inclusion in the record and may question the parties’ witnesses as set forth
below.7. As suggested by Excelsior Energy, and for the greatest convenience of
the public, the two-stage hearing procedure permitted by Minn. R. 1405.1500, subp. 2,
will be used. In Stage One, the prefiled direct testimony of each party’s witnesses shall
be admitted and those witnesses shall be cross-examined by the other parties. If time
allows, limited questioning by other interested persons may be allowed. In Stage Two,
other interested persons may present testimony and may question the witnesses who
offered testimony during Stage One. Interested persons offering testimony may be
questioned by other persons at the hearing.
In the First Prehearing Order, there were to be days and days of hearings, more than two weeks worth! Given there were 20 or so witnesses, that sounds workable:
April 2-6, 2007 Stage One sessions in St. Paul, Taconite, and/or
Hoyt LakesApril 9-11, 2007 If necessary, additional Stage One sessions in
St. Paul, Taconite, and/or Hoyt LakesApril 20-24, 2007 If necessary, additional Stage One sessions in
St. Paul, Taconite, and/or Hoyt LakesApril 25-26, 2007 Stage Two sessions in Taconite and/or Hoyt
LakesApril 27, 2007 If necessary, additional Stage Two sessions in
Taconite and/or Hoyt Lakes
But all the Intervenors were eliminated and so was the public vetting and gutting of Excelsior Energy’s Mesaba Project. That got it down to two days… TWO DAYS!!!!!! Twenty witnesses in two days. Yup, great record we’ve got here. So under the rules, Minn. R. 1405.1500, Subp. 3, seems it’s time for a Motion…
Stay tuned… highlights and lowlights of the hearing to follow …