withdraw

Today was Deadline #1 for Comments on NDPC’s Petition for Withdrawal of the Sandpiper pipeline Certificate of Need and Route applications.  Here’s what was filed:

Sandpiper_Landowner Comments_Xmsn

Yup, that’s it.  My Sandpiper transmission clients weighed in.  I’ve been watching the docket, watching the inbox for service…. NO other comments, nothing, nada…

Just get to it.  Quick – take a few minutes and send a missive to the Public Utilities Commission encouraging them to allow Enbridge to withdraw their application for the Sandpiper pipeline WITH PREJUDICE so that they can’t refile it again.  Send to:

Daniel P. Wolf, Executive Secretary  (dan.wolf@state.mn.us)                        Minnesota Public Utilities Commission                                                           121 Seventh Place East, Suite 350                                                                    Saint Paul, MN  55101-2147

Ann O’Reilly and James La Fave, Administrative Law Judges
Office of Administrative Hearings
600 North Robert Street
P.O. Box 64620
St. Paul, MN 55164-0620

But it doesn’t end there, with zip comments… it gets weirder.  I’d saw there was no notice from the PUC about a comment period, nothing.  Here’s what they did with Hollydale, Notice, and there was a comment period and reply comments!  In that docket, Xcel Energy filed to withdraw its Hollydale applications on December 10, 2013, and this notice was issued on January 10, 2014:

20141-95340-02 Notice of Comment Period

Here’s what we got:

topics

And when I asked:

cao2puc

Here’s the response:

puc2cao

Oh my… what do I do with that?  Guess I write a post about it!!!

withdraw

 

 

 

horsesassaward

Here we go, thanks to Xcel Energy and Office of Administrative Hearings, based on the bias and double standards for participation and obstructions to intervention in the latest Xcel Energy rate case (PUC Docket GR-15-826).

Yes, Intervention in the rate case denied again:

20162-118122-01_Denial #2_Overland-NoCapX Intervention

And I quote:

Further, the Petition states that purposes for which No CapX 2020 was “specifically formed” (fn omitted) was to participate in dockets which are now closed, raising the question of why No CapX 2020 continues to exist.

aghast

H-E-L-L-O?!?!?!  This rate case docket is all about shifting the CapX 2020 and MISO MVP 17 project portfolio transmission costs from one scheme to another.   I specifically cited all the references to CapX 2020, MISO MVP, and transmission.

dohHere’s what has gone before…

Intervention Petition II

Xcel objection to second petition to intervene

Overland-NoCapX_Intervention Petition 2

Intervention Petition I

20161-117574-01_Order Denying Intervention Petition 1

No CapX 2020_Response to Xcel’s Objection

20161-116957-02_Xcel’s Objection to Intervention

NoCapX 2020 and Carol A. Overland_Intervention Petition Packet

And in a parallel track, note the double standard in pleading.

  • Note that Xcel has objected only to the Overland/No CapX 2020 intervention.
  • Note that Xcel has not objected to those who participated in the “e21 Initiative” which is the basis for this rate case “multi-year rate plan” and transmission shift.
  • Note how little the other “intervenors” say.
  • Note they do not state their interests.
  • Note they do not state how their interests are different from general ratepayers.
  • Note they do not state how their interests will not be represented by OAG and Commerce.

OAH has approved Interventions of “The Commercial Group,” “Suburban Rate Authority,” and “City of Mineapolis.”  I’m sure the approval of “Clean Energy Organizations” will soon follow, despite the lack of specific pleading and the apparent conflict with one “attorney” representing so many organizations that either have differing positions and interests, or which are adequately represented by other organizations and don’t need to intervene… funny how this double standard works…

Read the Petitions:

Petition to Intervene of the Commercial Group

Petition to Intervene of Suburban Rate Authority

Petition to Intervene 0f City of Minneapolis

Petition to Intervene 0f “Clean Energy Organizations”

Petition to Intervene of MN Chamber of Commerce

Check out each of these petitions.  Look at the pleading, what’s stated, and as importantly, what is NOT stated.  What are their interests?  How are the “interests” different than general ratepayers in their class?  How are their interests not represented by Office of Attorney General and/or MN Dept. of Commerce?

So what to do?  Participating in the public hearing is not sufficient, and if that’s the limited offering, well, there’s no Discovery for a public participant.  What’s next?  Fight for the privilege of an unfunded intervention, as if there’s nothing else to do?  The issues raised by Overland/No CapX 2020 will not be addressed otherwise.  And thos overt quashing of participation is not consistent with the “public” in “Public Utilities Commission” and the Commission’s mandate.

Meanwhile, FERC just denied the 2010 Petition for Intervention too in the case regarding the cost allocation for these CapX and MISO MVP projects, yes, that took them 5 1/2 years to do, so why now?  Check this out:

FERC Order – Docket ER09-1431 (p. 8)

Odd that should come up now… naaaah, not really.

booted-out

1000-dollar-us-bill

Released yesterday by National Institute for Science, Law, and Public Policy (NISLAPP) (never heard of it before, need to do some checking):

Green Electricity or Green Money?

Why is this a question?  We know it’s a problem. But this report focuses on things like “Smart Meters” and doesn’t dig into the the even worse toadying for coal gasification and other harebrained promotional schemes of these orgs.

Here in Minnesota, the money goes to Minnesota Center for Environmental Advocacy, Fresh Energy f/k/a ME3, Izaak Walton League and its former program now independent 501(c)(3) Wind on the Wires (conveniently separate since just after election, when Bill Grant was appointed Deputy Commissioner of Commerce in charge of all things energy)(oh, and Nancy Lange appointed to Public Utilities Commission).  And then there’s RE-AMP.  There’s so much money flying around for promotion of transmission and coal gasification.

Bill Clinton toadying for transmission

WOW’s devil we know… ummm… WOW!!!

Walton’s Bill Grant – Deputy Commissioner of Energy?

Wind up to ELPC Transmission Strategy Meeting

AAAAAAAAAAAAARGH… back to work…

pilesofiles

The Minnesota Public Utilities Commission is winding up its rulemaking on the Certificate of Need (Minn. R. Ch. 7849) and Siting/Routing (Minn. R. Ch. 7850) chapters.  My clients Goodhue Wind Truth and North Route Group have been participating all along, and their experience with the Certificate of Need and Routing/Siting process has helped inform this record and we sure hope leads to more sensible and workable rules, AND increased public participation.

Now is the time to download and make your comments on what should be included, what’s included that’s important and needs to go forward, and what needs to be reworded.

August 13 Draft 7849

7850 July 8 draft

August 13 Ch. 7850 comparison

Send Comments to:

  • kate.kahlert@state.mn.us
  • and/or post to the Rulemaking Docket.  To do that go HERE to the eDocket Filing Page, register if you’re not registered (it’s easy and almost instant), and post to Docket 12-1246.

It’s highly likely that the LAST meeting of the PUC’s Rulemaking Advisory Committee will be September 24, 2014 (9:30 a.m. at the PUC, in the basement).

A few things that need work:

  • Ch. 7849 & 7850: Need language mirroring statutory language regarding testimony by members of the public UNDER OATH (ALJs have refused to offer people opportunity to testify under oath, and PUC has stated that it makes a difference, “but were those statements made under oath” and if not, less weight.
  • Ch. 7849: Advisory Task Forces need language of statute, and membership not limited to “local units of government.”
  • Ch. 7849 & 7850: Transcripts available online — need to address this in rules and reporter contracts.
  • Ch. 7849: Scoping and Alternatives — compare with Ch. 7850.  Similar process?
  • Ch. 7849.1450: When is it Commerce EER & DER
  • Ch. 7849 & 7850 – timing should be similar for completeness review, etc.
  • Ch. 7850: Public Meeting separate from Scoping Meeting (Public Meeting is to disseminate information, Scoping Meeting is for intake).
  • Ch. 7850: Power Plant Siting Act includes “Buy the Farm.”  Need rules regarding Buy the Farm.

Now is the time to review the drafts, above, and send in Comments.  There may be, I hope there are, revisions released prior to the next meeting, but usually it happens just before, and there’s no time.  So here’s where we are now, and Comments would be helpful.

7849 Rulemaking update

July 9th, 2013

Updates on rulemaking ongoing at the PUC (not that they put anything in the PUC docket, but don’t worry, I’ll post there too):

June 26 Meting Synopsis

July 8 Draft

Is this too wonkish, or does anyone else see the irony in having to struggle so to get opportunity for public input in these Certificate of Need rules?

If you have comments on the draft rules, and BE SPECIFIC, label with rule citation (i.e., Minn. R. 7849.0100, and show how you’d change the rule, with the narrative explanation and the exact words you suggest, and send to kate.kahlert@state.mn.us and post to docket 12-1246 at the PUC site if you can, (www.puc.state.mn.us and click on “eFiling” and sign up to post if you’re not already registered).

History and background, with links to the comments thus far:

7849 Rulemaking Update – July 4th, 2013