RateCase_MankatoHearing

Last night there was a hearing in Mankato on the Xcel Energy rate case (Docket E002/GR-15-826).  Public participation in Public Utilities Commission dockets is supposed to be a happenin’ thang…   But there were no witnesses to question yesterday at the public hearing, and the Xcel representative who was there could not answer questions.  Worse, there was no commitment to have witnesses available to the public at the public hearings, and only advice that the public could attend the evidentiary hearing.  ATTEND?!?  When might we be able to question witnesses?

Sent this Data Practices Act Request this morning to round up the Information Requests and Responses regarding transmission, transmission riders, MISO and FERC:

Data Practices Act Request

Xcel Energy wants to shift its transmission rate recovery from CWIP and AFUDC to general rates, but there was no one there to talk about it.  These are the MVP projects at issue, in Schedule 26A, below, which are worked into MISO tariff and FERC blessed:

MVP ProjectsAnd here’s the projects in Schedule 26, below, but hmmmm, no project costs shown (click for larger view):

Sched 26I entered these exhibits:

Exhibit 1A – XcelCover_e21_Request for Planning Meeting and Dialogue – PUC Docket 14-1055

Exhibit 1B – e21_Initiative_Phase_I_Report_2014 – Xcel Filing PUC Docket 14-1055

Exhibit 2_MISO Schedule 26A Indicative Annual Charges_02262014

Exhibit 3 – FERC EL-14-12-002_ALJ Order – ROE on MISO Transmission

Next meeting I’ll have some more:

e21_MikeBull_Center for Energy and Environment

MISO Schedule 26 Indicative Annual Charges

1Q_Earnings Release Presentation_5-9-2016_1500085150

Investor Presentation – NYC-Boston_3-1-2=16_1001207698

Investor Presentation – NYInvestorMtgs_5-10-2016_1500085349

2015 10K – Xcel Energy

2015 10K – NSP

Back to last night’s hearing…

Check the rules about public participation:

1400.6200 INTERVENTION IN PROCEEDINGS AS PARTY.

Subp. 5.  Participation by public.

The judge may, in the absence of a petition to intervene, nevertheless hear the testimony and receive exhibits from any person at the hearing, or allow a person to note that person’s appearance, or allow a person to question witnesses, but no person shall become, or be deemed to have become, a party by reason of such participation. Persons offering testimony or exhibits may be questioned by parties to the proceeding.

Another, the PUC practice rules:

And yet another:

And this one (though they’ll say it isn’t applicable because a rate case isn’t part o the Power Plant Siting Act):

What about the mediation next week?  How is the public interest represented?
PublicHearingSchedule