.

jpmorgan_miso

“MISO” trademark owned by… JPMorgan Chase!

But seriously folks!  JPMorgan got caught with its hand in the cookie jar again, CAISO and MISO have filed claims of abusive practices at FERC.  Here’s the short version of what they allegedly did (it’s allegedly for now, but just you wait!) — from the second article below:

In the Midwest, the alleged manipulation involved day-ahead margin assurance payments, under which generators are compensated for situations when their real-time dispatch falls below the level set by the day-ahead dispatch schedule. As in California, traders found a flaw where they could force the market to make “inappropriate or excess” payments by placing lowball bids in the day-ahead market – as low as negative $500 per megawatt-hour – and much higher bids in the real-time market, Miso said.

Here’s the Amended CAISO Petition against JPMorgan Chase:

CAISO Petition

Still looking for the MISO Petition and FERC’s legendary Constellation Order.

In the news:

JPMorgan Chase Manipulation Scandal Raises Specter of Enron

JPMorgan probe highlights FERC power trading crackdown

JPMorgan’s Role in Power Market Comes Under Scrutiny

In the STrib:

E-mails sought in U.S. probe of JPMorgan, electricity sales

A federal judge ordered JPMorgan Chase & Co. on Thursday to explain why it shouldn’t be compelled to turn over e-mails sought by U.S. regulators in a probe of potential electricity market manipulation in the Midwest and California.

U.S. District Judge Colleen Kollar-Kotelly in Washington gave JPMorgan until the end of the day on July 13 to respond. The U.S. Federal Energy Regulatory Commission (FERC) sued JPMorgan on Monday to release 25 e-mails in an investigation of possible manipulation of power markets in the Midwest and California by J.P. Morgan Ventures Energy Corp.

FERC is examining efforts by Houston-based J.P. Morgan Ventures to extract excessive payments or above-market prices from Midwest Independent Transmission System Operator (MISO)and California ISO, Thomas Olson, a lawyer in the FERC investigating division, said in a court document. He said the probe focuses on winning inflated “make-whole” payments, which the grid operator pays when a power plant’s output isn’t needed as anticipated.

In court papers, FERC said JPMorgan’s bidding techniques in the Midwest and California resulted in at least $73 million in improper payments. FERC opened the probe in August after complaints from Midwest and California grid operators that JPMorgan’s bidding practices were abusive, according to the agency’s initial court filing.

MISO oversees the electric grid in parts of 11 midwestern states, including Minnesota and Wisconsin, and Manitoba.

“We believe we have complied in all respects with the law, as well as FERC rules and applicable tariffs, governing this market,” Jennifer Zuccarelli, a JPMorgan spokeswoman, said in an e-mail. “We stress that this investigation is ongoing and that no conclusions have been reached or findings adjudicated.”

She said “we welcome the court’s assistance in resolving this dispute over documents.”

JPMorgan’s commodities business owns or has the right to output from several electricity generating facilities. Only one power plant, an unnamed facility in Michigan, is mentioned by FERC in court papers.

It remains unclear whether utilities and power generators in the region were hurt by the bank’s alleged market manipulation. Xcel Energy, based in Minneapolis, said in a statement that it was aware of the investigation “but at this point, we don’t have information about the allegations or if we may be impacted.”

FERC has accused the bank of improperly using attorney-client privilege to withhold or redact 53 e-mails subpoenaed in April. The company has since released 28 of the e-mails.

In a three-page order, the judge said that “JPMorgan shall address why it should not be required to produce the 25 at-issue e-mails in unredacted form or to submit them to the court for in-camera review.”

Grid operators solicit bids from electricity suppliers each day to meet expected demand. Typically, 90 percent or more power consumed is secured in what is known as the day-ahead market. Any supply shortfalls because of weather or unexpected plant shutdowns are met through bids placed in real-time.

Star Tribune staff writer David Shaffer contributed to this report.

pressurecooker

First, the bad news – the Commonwealth Court of Pennsylvania has affirmed the Order of the Pennsylvania Public Utilities Commission approving the Susquehanna-Roseland transmission project:

Commonwealth Court of Pennsylvania – Affirms Pennsylvania’s S-R Order

And now, on to the pressure… The National Park Service is working to do it’s job as steward of our national park land, in this case, the federally declared Wild and Scenic Delaware River and the Delaware Water Gap.

delawarewatergap

Seems that some don’t think they should be allowed to do that job, and are pressuring them to “hurry up” so the Susquehanna-Roseland transmission line can steamroll on through.  Well, BACK OFF!

Today the pressure on NPS was overt in two venues.  First, U.S. Rep. Charlie Dent (R-PA) amends a bill to push the NPS to complete its environmental review one year ahead of schedule.  Say what?!?!?!

charliedent

Then in my inbox a sour grapes press release from FERC Commissioner Phillip Moeller whining because the newly adopted rule won’t do what he wants, it won’t address “problems” like NPS doing its proper review of transmission projects:

July 21, 2011 Press Release – Phillip Moeller Whines

Here’s the Susquehanna-Roseland specific part:

“While I offer substantial praise for today’s final rule, the Commission should have taken a different approach to several important issues.  We must recognize that all of the nation’s difficulties in building needed transmission will not be resolved by this rule.  Rather, this rule largely addresses planning for long-distance transmission lines, which is only a subset of the critical issues that are inhibiting needed investment.

This rule cannot address issues like the delays caused by other federal agencies in the siting of important projects, as this Commission lacks the legal authority to require other federal agencies to act.  For example, see the comments of PJM in this proceeding at p. 17, which state that:

[t]he PJM Board approved the Susquehanna-Roseland 500 kV line in 2007.  The Susquehanna-Roseland line was approved by the state regulatory commissions in Pennsylvania and New Jersey for 2012.  The line is currently delayed by the National Parks Service [sic] and is not expected to be in service until 2014 at the earliest.

Ohhhhhhhh, isn’t it too bad.  He’s just one Commissioner, and he’s got to put his dissent out there as an extensive and extended rulemaking proceeding closes… Why is he pushing, why does he care, and why does his care rise to the level that he sends out a dissenting press release?  Lighten up, the National Park Service has a job to do.  As the testimony in the Susquehanna-Roseland proceeding before the New Jersey Board of Public Utilities reflects, we are NOT going to freeze in the dark in an incubator without a job…

And here’s Pre. Charlie Dent’s whine:

Charlie Dent pushes expedited federal review of Susquehanna-Roseland power line proposal

Published: Thursday, July 21, 2011, 4:30 AM
By Tom Rowan Jr. | The Express-Times

U.S. Rep. Charlie Dent is pushing for the National Park Service to complete its review of the controversial Susquehanna-Roseland power line proposal sooner than planned.

And the New Jersey Sierra Club wants Dent, R-Lehigh Valley, to back off.

Dent amended a bill approved July 12 by the House Appropriations Committee to call on the park service to finish its environmental impact statement on the project by 2012 rather than 2013.

“The committee is concerned about delays,” reads Dent’s amendment to the Fiscal Year 2012 Interior and Environment Bill.

The Sierra Club this week issued a release claiming Dent added the amendment in an attempt to “handcuff the park service from doing their job in complete violation of the public trust” and “undercut the National Park Service and push an environmentally destructive and unnecessary project.”

First pitched in 2008, the Susquehanna-Roseland line has been described by the two power companies behind the plan — PPL Electric Utilities Corp. in Pennsylvania and Public Service Electric & Gas in New Jersey — as necessary to bolster the region’s power grid. The 130-mile power line is proposed to link the Berwick, Pa., area to Roseland, Essex County.

The 500-kilovolt line is being evaluated by the park service because the route, as approved by New Jersey and Pennsylvania utility regulators, crosses the Delaware Water Gap National Recreation Area and other federal lands.

“The timely completion of the impact statement is of great importance to the reliability of the regional grid and is critical to the supply of electricity to 58 million consumers in 13 states and Washington, D.C.,” the bill reads.

The National Park Service earlier this year pushed its goal to finish the impact statement back from fall 2012 to January 2013, after the utility companies asked the agency to include another alternative in their review.

“Instead of standing up for our open spaces, Dent is working for PSE&G and PPL,” Jeff Tittel, director of the New Jersey Sierra Club, is quoted as saying in the statement.

Collin Long, spokesman for Dent, responded Tuesday in an e-mail, “The congressman’s amendment does not show favor toward any of the alternatives being considered and respects the integrity of the environmental impact statement.

“It simply requires the National Park Service to follow their own timeline for completion of the review process, which already includes a six-month extension of their original deadline to October 2012.”

The appropriations bill awaits consideration by the full House of Representatives. When considered on the House floor, it will be open for modification through the amendment process.

If it passes through the House, it would be referred to the Senate.

transmissionpowerline_largempr

ILSR’s John Farrell is halfway there – he recognizes the federal part of the transmission equation, but the state part is missing, for example, Minnesota’s special eminent domain exemptions for “Public Service Corporations” (particularly where the transmission is for private profit, NOT public service), rate recovery for “Construction Work in Progress” and state regulators refusal to examine the interstate nature of transmission proposals.  And the third part of that unholy trinity — in the Midwest, bulk power transmission would not be being built but for the Settlement Agreement – ME3(Fresh Energy), Izaak Walton League (and Walton’s program Wind on the Wires), Minnesota Center for Environmental Advocacy, and North American Water Office.  This glut of transmission is their legacy.  It takes all three to build transmission.

From Grist, today:

Feds running a high-voltage gravy train for power transmission

by John Farrell
28 Jun 2011 6:00 AM

Even as distributed generation shows economical and political advantages over centralized renewable energy, the Federal Energy Regulatory Commission (FERC) is running a high voltage gravy train in support of expanded transmission. FERC’s lavish program is expanding large transmission infrastructure at the expense of ratepayers instead of looking at more economical alternatives.

Since 2007, FERC has had 45 requests for bonus incentives for transmission development — authorized under the 2005 Energy Policy Act — and has provided all or most of the requested incentives in more than 80 percent of the cases. With the bonuses, the average return on equity for utilities for their new transmission investments is nearly 13 percent. This high rate of return is a full 2.5 percentage points higher than the median utility return on equity [PDF], a value considered just and reasonable by state public service commissions in ordinary times. However, these rewards came during a time when unemployment doubled, the stock market tumbled, and most corporations were lucky to have any profit.

The ratepayer impact of these bonuses is significant. In a November 2010 criticism of FERC transmission awards, Commissioner John Norris noted that the 2 percent bonus FERC provided to the PATH high-voltage project on the Eastern seaboard would “cost [Maryland] ratepayers in PJM at least $18 million per year.” The bonus payments were also given in concert with other incentives that reduced risk, including rate recovery during construction and guarantee of payment if the facilities were abandoned for reasons outside utility control.

Read the rest of this entry »

coal-fire

The cost apportionment remand at FERC is heating up.   It’s that case where the 7th Circuit threw out the PJM cost apportionment scheme:

Illinois Commerce Commission v. FERC – August 6, 2009

It went back to FERC and so FERC issued an Order requiring PJM to produce things that… well… things that will demonstrate that there’s no need for this project, things that will demonstrate the benefactor of these transmission lines, things that PJM doesn’t really want the world to know, like how they’ve incorporated O-P-T-I-M-I-Z-A-T-I-O-N, things going directly to N-E-E-D!

FERC Order January 21, 2010

Seeing that, well, Stop the Lines had to join in, as did the Municipal Intervenors:

Stop The Lines! Motion for Limited Intervention

PJM begged for more time, an extension of 45 days!

PJM’s Motion for More Time to Answer

And for some bizarre reason, FERC gave it to them:

FERC Order Feb 22 2010

Meanwhile, Exelon wants to bring in the kitchen sink, including 345kV transmission:

Exelon Motion Feb 23 2010

And parties they are a freakin’ and filing:

Baltimore Gas & Electric Response to Exelon

Dayton Power & Light response to Exelon

And then the weirdest of all – the American Wind Energy Ass (AWEA) wants to intervene, citing “the current significance of this issue in the context of efforts to build transmission to bring location-constrained, renewable resources to load…”  Ummmm… SAY WHAT??

AWEA-SEIA Motion to Intervene Out of Time

OK, I give up… in what parallel or alternate universe is the PATH or Susquehanna-Roseland line for wind?  WHERE DO THEY GET THESE IDEAS?  I want to see the basis for that statement.  PRODUCE!

Earth to AWEA — can you spell P-R-O-J-E-C-T M-O-U-N-T-A-I-N-E-E-R?

projectmountaineermap

If you need a hint, go to FERC eLibrary and search for A05-03.  Happy reading!

Susquehanna-Roseland reopened!

January 27th, 2010

open-door

The Susquehanna-Roseland hearing has been reopened.  And off we got to FERC.  It’s been quite a hectic week, with a “flurry” of filings, and here’s the update.  First, remember the NJ BPUat a special 1/15 meeting said they were NOT going to decide on PSE&G’s Susquehanna-Roseland transmission line and said they’d be asking for more information from PJM.  Well, they asked PJM to answer a few questions (though not specific enough, not the right questions):

BPU Secretary letter to PJM

Here’s what PJM had to say:

PJM Letter in response to BPU Query

Suffice it to say, the letter is … ahem… INSUFFICIENT!

And then the responses started coming in, first the Municipal Intervenors, then :

Municipal Intervenors response to PJM Letter

Environmental Intervenors – January 25, 2010

Stop The Lines! January 25, 2010

And the BPU issued an Order reopening the docket and first scheduled a hearing for February 2, 2010, and then THANKFULLY changed it to February 4, 2010:

BPU Scheduling Order Jan 25, 2010

BPU Amended Scheduling Order Jan 26, 2010

The concept is that PJM is coming in as a witness regarding the assertions of their January 21, 2010 bullshit letter, and what does that mean?  Is Steve Herling THE witness, or are there others?  Is whatever witness/es coming with a truckload of exhibits that they’ll dump on us the day of the hearing?  Is he going to be prepared in any way to back up his conclusory and unsupported statements?  So I fired off a couple missives, first Discovery to get the requests in quick and let them be on the record of ignoring or refusing to answer, and then a letter to the BPU with my view of the fine mess we’re in:

STL Discovery re: PJM Letter 1/21/10

STL Letter to BPU 1/25/10

As a sidebar, the escrow that PSE&G had to put out for the Municipal Intervenors is gone, this has been an intense case, and so they’re reasonably asking for more:

Municipal Intervenors – Motion for Escrow

Meanwhile, back at the ranch, remember that great 7th Circuit decision tossing out the cost allocation for this project?  Everything’s been up in the air since then, because if they can’t settle how they’re going to allocate the costs, this sucker won’t be built:

Illinois Commerce Commission v. FERC – August 6, 2009

It was remanded to FERC and after some wrangling, just like in the BPU case, where the utilities were saying, “It’s all there in the record, you don’t need anything more to make a separate decision” and Illinois said quite succinctly, “AHEM, WE DON”T THINK SO!” and FERC issued an Order stating that the record was not sufficient, needed more information and directed PJM to provide some information and also provided some questions for parties to mull over in their comments:

FERC Order January 21, 2010

Here’s the fun part – what they asked PJM to provide (hee hee hee hee hee hee), starting on p. 5 of the above Order:

10. PJM should provide the following information:

A. The total costs that have been approved through PJM’s Regional Transmission Expansion Plan (RTEP) process for facilities that operate at or above 500 kV (and necessary lower voltage facilities), and whose costs are assigned pursuant to Opinion No. 494. For these projects, calculate the total costs that have been assigned to each PJM zone, and estimate the total costs that would be assigned to each zone using PJM’s DFAX methodology.

B. PJM manuals require that, in planning projects, it seek to optimize projects in order to reduce the cost of addressing individual reliability criteria. Describe how the optimization process is performed. Also, explain how PJM determines the relative priorities of resolving numerous reliability issues with one project. For 500 kV and above facilities, explain whether PJM could accurately determine the beneficiaries of a project that resolves numerous reliability issues using its DFAX methodology.

C. PJM’s most recent RTEP report (2008), at P 5 states that:
Baseline thermal and voltage analysis encompasses an exhaustive analysis of all Bulk Electric System (BES) facilities for compliance with NERC Category A (TPL-001), Category B (TPL-002) and Category C (TPL-003) events. In addition, consistent with NERC standards TPL-004, a number of extreme events including those judged to be critical from an operational perspective as well as those defined in Table I of TPL-004 were evaluated for risk and consequence to the system. Describe the types of anticipated reliability requirements addressed by the PJM RTEP (i.e., voltage, thermal, stability). Explain whether and how the DFAX analysis applies to the NERC reliability analyses listed above and any other reliability requirements. Explain whether the RTEP upgrades designed to address these reliability requirements also will address other reliability concerns. In particular, explain whether the geographic location or voltage level of an RTEP upgrade makes that upgrade more likely to address broader reliability concerns.
Provide any relevant studies.

D. In this proceeding, PJM recommended the adoption of a postage-stamp rate design for new 500 kV and above facilities.

1. Describe the benefits generated by such facilities that are not captured in the DFAX methodology used by PJM to allocate costs for lower voltage facilities. Indicate whether such lines provide reliability or economic benefits to the areas producing electricity.

2. Provide engineering or other studies showing any differences in regional benefits between 500 kV and lower voltage facilities (e.g., 345 kV
and 230 kV).

E. Provide any existing engineering or other studies that indicate whether the modeling assumptions used in the RTEP analysis, such as the direction of flow,
remain consistent or vary over time.

The Municipal Intervenors sent in a Motion to FERC, PSEG objected, and then Stop the Lines sent in a Motion for Limited Intervention:

Municipal Intervenors – Motion to Intervene

PSEG Response to Munis FERC Intervention

Stop The Lines! Motion for Limited Intervention

Municipal Intervenors – Renewal of Motion to Intervene

PSEG Response to STL Intervention Motion

PSEG’s response to our Motion to Intervene… yeah… (yawn)… what-ev-er…

And just now, hot off the press, the Municipal Intervenors have filed a Motion to Depose PJM’s Steven Herling!  Oh, yes, this is much needed, so we can get an idea where they’re going and what they plan to present (I doubt they’d produce the pre-filed testimony I requested!):

Municipal Intervenors Motion to Depose PJM’s Herling

As you can see, it’s been an intense few days, and isn’t letting off anytime soon.  More to follow as it develops.