Let Mesaba go…

December 19th, 2009

liar

Jorgensen’s got to get over it — Mesaba is done, ain’t happening, dead, dead dead, yet she’s spinning those tales and hype about Excelsior Energy’s Mesaba IGCC Project.  From the first words in the title, it’s lies, lies and more lies, oh, and misrepresentations and falsehoods and exaggerations and utter bullshit too!  Why does the St. Paul Pioneer Press give her space forthis advertising of the nonsensical kind?

Here’s what Citizens Against the Mesaba Projet’s Charlotte Neigh had to say about it:

Julie Jorgensen is using the opportune hook of the Copenhagen conference to repeat Excelsior Energy’s same old, self-serving promotional claims about the “clean coal” technology of its Mesaba Energy Project. One must wonder why the Press unquestioningly allots opinion space to the promoter of a precarious for-profit venture, financed almost exclusively by $40 million in public funds, which have been benefiting the author and her co-founder husband, Tom Micheletti.

What Jorgensen didn’t say:

• The U.N. negotiators in Copenhagen decided to leave carbon capture and storage, the prime objective of the IGCC technology touted by Excelsior Energy, off the list of clean-energy projects eligible for the Clean Development Mechanism; the 12/17/09 Wall Street Journal reported that “clean coal seems to be getting the cold shoulder at the climate summit”, and  “. . .  clean coal is anything but viable right now”.

• Mesaba’s Unit I would emit 5 million tons of carbon dioxide per year and the Department of Energy has acknowledged that capturing and sequestering the CO2 from the proposed Taconite plant is not feasible.

• The claimed economic benefit has been rejected by the Minnesota Public Utilities Commission, which found the project too expensive and risky and not in the public interest.

• The need for this Project has never been proven; no utility is willing to buy its output; Xcel Energy successfully resisted efforts to force it into a power purchase agreement; and the MPUC has declined to require other utilities in the state to include Mesaba’s output in their resource plans.

• The environmental claims are yet to be adjudicated as the MPUC considers the route and siting permits and other government agencies pursue their concerns related to air, water and waste permits.

Is Jorgensen’s piece really that bad?  See for yourself:

Julie Jorgensen: We need baseload power. Coal’s plentiful. Let’s clean it up

By Julie Jorgensen
Updated: 12/17/2009 05:54:25 PM CST

As heads of government gather in my ancestral home of Denmark, the world considers its energy options.

The challenge for Copenhagen is that commitments to cut greenhouse gas emissions are at odds with the plans of developing nations to rely on inexpensive fossil energy to fuel economic growth and improve their standard of living. Developed nations, meanwhile, fear that mandated greenhouse gas reductions will tax economic recovery and prolong global recession. Diplomacy is the art of the achievable, and these realities will be balanced against concerns about the effect of man-made carbon dioxide and other greenhouse gases on Earth’s climate.

On the home front, there are plenty of competing concerns to consider as we address our energy needs. But there are two things our local energy experts agree on: Minnesota has an impending need for more baseload power, and renewables can’t do the job alone.

For baseload — that is, the steady supply of electricity for everything from factories to home outlets — Minnesotans must take a long, hard look at the most abundant resource in our own backyard: coal. Not old-fashioned, dirty, polluting coal, but coal used to fuel a new technology called IGCC, which stands for Integrated Gasification Combined Cycle. In addition to producing clean, affordable energy, such plants would allow us to transform America’s 250-year supply of coal into ultra-clean fuels like synthetic natural gas, transportation fuels, and hydrogen.

I’m the co-founder of Excelsior Energy, which is developing the Mesaba Energy Project, an IGCC power plant near the town of Taconite on Minnesota’s Iron Range. From my point of view, IGCC offers economic and environmental benefits to Minnesota. The Midwest is poised be a leader in the delivery of this technology. Gov. Tim Pawlenty and the Minnesota Legislature have supported the development of Minnesota’s IGCC plant, the Mesaba Energy Project, since 2003, and the project has been exempted from a statewide prohibition against new coal plants. Eleven Midwest governors established a collective goal to spur construction of at least five commercial-scale IGCC plants by 2015, and President Obama announced a goal to build five such “first-of-a-kind” clean coal plants. The U.S. Department of Energy (DOE) has provided significant funding and incentives to the Mesaba Project to offset the costs of needed innovation.

Adoption of IGCC technology is essential to cleaning up coal and mitigating climate change.

IGCC plants use less water, use less land, create less waste, and emit two-thirds less air pollution than the cleanest of the traditional coal plants that currently deliver most of our electricity. In addition, IGCC plants clean a volume of gas that is a mere 1/100th of the stream pouring out of the smokestacks at the Sherco coal plant in Becker and the Boswell coal plant in Cohasset. This makes it easier and cheaper to prevent the release of carbon dioxide, which is essential in the face of potential climate change regulation.

As fears mount about global warming, environmental advocates like the Clean Air Task Force and the Natural Resources Defense Council support the timely and widespread commercialization of IGCC technology. From a global perspective, the importance of commercializing a cleaner way to use coal cannot be understated: both India and China have vast coal reserves, which they will inevitably use in the cheapest and easiest possible ways to fuel their growing economies.

Nuclear power faces major obstacles. Plans for a federal nuclear waste repository have been scrapped. The Obama Administration stopped the DOE’s development of the Yucca Mountain repository, originally slated to begin accepting waste in 1998, without providing an alternative storage plan. As a result, we will store nuclear waste on the banks of the Mississippi River for the foreseeable future.

Additionally, the costs of new nuclear facilities may put them out of reach.

Even if the Legislature lifts Minnesota’s ban on new nuclear plants, it will be at least 20 years before a new plant could be licensed and built in Minnesota, given the long and costly lead-times. Simply put, new nuclear capacity cannot meet our current needs.

While the eyes of the world are on Copenhagen, it’s appropriate for Minnesotans to ponder our own impending energy crisis. Since renewables and conservation can’t meet all of our new energy needs, we must make some difficult choices that ultimately will involve coal-fired, natural gas-fired, and nuclear energy sources. Marrying new IGCC technology with the abundance of U.S. coal makes clean coal the most rational choice for our state.

Julie Jorgensen is the former CEO of CogenAmerica, a publicly traded independent power company, and a former executive of NRG Energy, a global energy development company. She’s a co-founder of Excelsior Energy Inc., which is developing a coal gasification plant near Taconite on Minnesota’s Iron Range. Her e-mail address is JulieJorgensen@ExcelsiorEnergy.com.

excelsior-yahoos

mesabaone

The joint DOE and MN Dept. of Commerce EIS for Excelsior Energy’s Mesaba Project has been released.  WTF?  This is SUCH a waste of time.  And I am at a lost to explain how it is that this even was released, why we have to bother with it, when it’s the vampire-vaporware project from hell that is dead but … but…

Excelsior Energy Mesaba Project Environmental Impact Statement

Comments on the “adequacy of the Final EIS or its impact upon the issues” are due on December 2, 2009.  Send Comments to:

steve.mihalchick [at] oah.state.mn.us

or by mail to:

Steve Mihalchick, ALJ

Office of Administrative Hearings

P.O. Box 64620

St. Paul, MN  55164-0620

Here’s the Order establishing that deadline:

4-17-08 Order – Final EIS Comment Deadline Established

Is this weird language or what:

b. Such comments on the “adequacy” of the Final EIS or its “impact” upon the issues in this matter shall be filed with the Administrative Law Judge within ten business days after filing of the Final EIS.

So get cracking on “such comments” and send them in!

And just in, breaking news…

Just last Friday, a MCGPer and his son were out deer hunting on the preferred Excelsior site, guns in hand, on the alert, and what should come bursting through the trees but… BOB EVANS!  Bob Evans and two other Excelsior boys, they were out viewing the site during deer hunting!  That just doesn’t seem to bright.

Give it up!!!   Get a job, Bob!!!

And have they forgotten that other encounter in the woods, almost exactly three years ago?

boysinthetreesgrhrnov182006

Meanwhile … the sun is coming up over New York right now…

sunriseovernewyork

dealwithdevil

Wind on the Wires” and AWEA are whining and crying in the press about unfair treatment to wind generators.   They do a deal with the devil to promote transmission and now are getting screwed — sorry, I won’t be hosting a pity party here!

AWEA PRESS RELEASE HERE.

AWEA and WOW’s FERC filing to protest MISO cost allocation proposal

To look at the full FERC docket, GO HERE TO FERC SEARCH PAGE, and search for docket ER09-1431.

“Wind on the Wires” is a subset of the Izaak Walton League – Midwest, not a separate organization.  Some background here:

Years ago, the Midwest Izaak Walton League, together with MCEA, ME3 (Fresh Energy) and North American Water Office, did a deal with Xcel, and a massive “Wind on the Wires” grant was announced a couple of days later.  The deal was to support a massive transmission buildout, specifically, to work to change state and federal law; to support transmission projects; to usher them through the legislature, state and federal administrative venues, to support at industry transmission planning groups; to support changes in rate recovery; to support changes in transmission need and siting criteria; and to allow transmission-only companies, all the things that Xcel wanted to roll out CapX 2020, JCSP, and whatever else is in their dreams.

Really… it’s all here:

Settlement Agreement – ME3, Waltons, MCEA, NAWO

$8.1 Million Wind on Wires grant from McKnight/Energy Foundation

Waltons 2007 Form 990, shows Beth Soholt, WOW Director & Matt Schuerger, Energy Systems Consulting, p. 19

This 2003 Settlement Agreement was in the Minnesota PUC’s TRANSLink docket, where Xcel wanted a transmission only company, not yet allowed in Minnesota.  For the docket, go to www.puc.state.mn.us and then click on “eDockets” and search for docket 02-2152.  F”or the resulting legislation, some of it, see 2005 Transmission Omnibus Bill from Hell.

So they jump through all those hoops and where are they?  What happens?

gettingscrewed

Back to Cost Allocation of Transmission.

Let’s see… there was one cost allocation scheme,  50-50 split between owner utilities and generators connecting.  Otter Tail Power objected and so the utilities changed it to a 90-10 split, and now “Wind on the Wires” and AWEA are screaming, whining and crying saying it has to go back.  This has to do with how the utilities characterize the purpose of the line, be it for “Reliability” or “Generation Interconnection” and how costs are apportioned are different.  In the CapX proceeding, the “Brookings line” was not declared, and the Fargo and LaCrosse lines were deemed “Reliability” but that’s absurd…

CapX’s Grover – Direct Testimony

CapX Application- Appendix D-5 – Cost Allocation

For “Baseline Reliability” projects here’s the cost allocation scheme:

baselinereliability

For “Generation Interconnection” here’s the cost allocation scheme:

generationinterconnectioncostallocation

Ummmmm…  a little more background here now that we’re talking about interconnection… does anyone remember the name of that coal plant that Otter Tail Power just got permitted to build?  Oh, yeah, right, it’s BIG STONE II.   And what was the name of that big honkin’ coal plant that “suddenly decided” to produce electricity rather than syngas?  South Heart, yeah, that’s it.   See “South Heart coal gasification — Coal on the Wires.” Both plants strategically placed to use CapX 2020 transmission.  So what is the impact of this shift to Otter Tail Power and their Big Stone II project?

Here’s the Big Stone electrical link to CapX — it’s all connected:

sw-mn-its-not-for-wind-map

Here’s new connector ND transmission announced April 3 — it’s all connected:

capxphaseii-map-corridorupgrade-res-projects-2-246x300

And of course, the big picture of CapX 2020 – click on it for a bigger picture to really appreciate those lines starting in the Dakotas:

capx2020-powerpoint-p-7-big-picture-map.jpg

Here’s an article from last week about their objections:

Wind industry protesting plan to pay for new lines

Cost-sharing proposal decried as threat to renewable energy goals


By Leslie Brooks Suzukamo
lsuzukamo@pioneerpress.com
Updated: 08/14/2009 12:01:26 PM CDT

The emerging wind industry in Minnesota and the Upper Midwest could be shut down by the cost of connecting to high-voltage transmission lines if a proposal by the organization that controls the Midwest’s power grid goes through, wind advocates say.

The grid operator and some utilities say the wind industry is overstating the effect, but the long-simmering dispute over who should pay for new transmission lines boiled over Thursday.

If the matter can’t be resolved, the wind industry insists, Minnesota’s renewable energy goals would be at risk.

The Midwest Independent Transmission System Operator, which covers 13 states and Manitoba, Canada, last month proposed changing the way costs are shared for new transmission lines. It wants to put 90 percent of the cost on energy generators, including the wind farms springing up across the Dakotas and southwestern Minnesota.

Previously, the cost has been split 50-50 between energy generators and transmission-line owners, typically utilities.

However, Otter Tail Power of Fergus Falls told the grid operator, known as MISO, recently that unless the sharing agreement is changed, Otter Tail would pull out of the system.

Wind farms in the Dakotas representing a total of 10,000 megawatts of electricity — a significant chunk of the power waiting to be added to the grid — wanted to connect to Otter Tail’s grid to reach Minnesota and the rest of the transmission system operator’s territory, said JoAnn Thompson,

Otter Tail’s manager of federal regulatory compliance and policy. Otter Tail consumers were going to have to pay half the cost of the new transmission, even though they would use almost none of that power, as it would be transmitted onward, she said.

“We support developing renewable energy but not at a substantially disproportionate impact to consumers,” she said.

The new cost-sharing proposal, which was submitted to the Federal Energy Regulatory Commission for approval, would increase the cost of developing wind energy projects so much they would no longer be economical, wind energy advocates said Thursday.

The American Wind Energy Association in Washington, D.C., and Wind on the Wires, a St. Paul-based industry association, filed a protest Thursday with the energy regulatory commission opposing the proposal.

“If (the transmission system operator) loads up the cost (of new transmission) on the generators, we won’t get new transmission built,” said Beth Soholt, executive director of Wind on the Wires.

“So unless we get the cost of new transmission spread out more evenly in the MISO footprint, wind-energy development is going to come to a screeching halt.”

The changes also could throttle efforts to export wind energy from the Upper Midwest to the rest of the country, the American Wind Energy Association added.

The Upper Midwest has been dubbed “the Saudi Arabia of wind” because of the region’s gusty conditions, but unless big and expensive transmission lines are built, there is no way to get that power from the scores of wind-energy projects proposed for the isolated prairie to energy-hungry metro areas like the Twin Cities, Chicago and points east, American Wind Energy Association analyst Michael Groggin said.

But Xcel Energy, which must generate 30 percent of its electricity from renewable energy by 2025, says the impact will be temporary. Xcel on Thursday asked the Federal Energy Regulatory Commission to require MISO to propose an alternative plan by April 1 next year, to be effective July 1, said Kent Larson, Xcel’s vice president of transmission.

MISO said it requested the shift in cost sharing to keep Otter Tail from bolting from the organization, which is voluntary. If Otter Tail pulled out, the wind farms in the Dakotas would have to pay higher rates to use Otter Tail’s lines as a bridge to the big cities anyway, said Clair Moeller, MISO vice president of transmission asset management.

A proposal by American Wind Energy Association and Wind on the Wires to spread the cost of new transmission to all MISO members would have caused utilities in the eastern part of the territory with no renewable-energy requirements to leave, Moeller added.

If members left MISO, the system of using the organization as a market to buy the cheapest electricity on the system would fall apart and rates would go up, Moeller said.

“So we were on the horns of a dilemma,” he said.

So if “Wind on the Wires” and AWEA object to “generator pays” transmission, where it’s the generator causing the need, then they’re now in essence advocating for a different scheme for Big Stone II and South Heart coal plants too.  Oh, good idea…

Here’s another one that turned up — WOW and AWEA sent out a raft of press releasees

Wind Industry Fights Midwest Transmission Proposal to Stay Alive

by Stacy Feldman – Aug 17th, 2009

The burgeoning wind industry in America’s Upper Midwest could be at risk of shutting down if a new transmission policy by a local grid operator goes through, according to a pair of wind advocacy groups.

Even worse — the plan could put the nation’s renewable energy goals in jeopardy.

The American Wind Energy Association (AWEA) and Wind on the Wires (WOW) have filed a protest with the Federal Energy Regulatory Commission (FERC) to stop a proposal by the Midwest Independent Transmission System Operator (MISO) — one that would dramatically change the way costs are distributed for new transmission lines.

Specifically, the plan would force energy generators to bear a 90 percent share of new transmission costs in the region, wind farm developers included.

Currently, generators and utilities split the price paid, 50-50.

For the wind industry, that would be seen as a shame. Current plans for regional wind are grand. Developers want to build a wave of utility-scale wind farms, and get the ones that have already sprouted plugged in. In fact, a decent chunk of the power waiting to be added to the grid in the Midwest is wind.

But if FERC approves the proposal by MISO, which covers 13 states, those megawatts may have to keep on waiting. Here’s why:

“The proposed change would nearly double the cost for a wind plant to connect to the power system in the Upper Midwest, potentially forcing many wind plant developers to pull the plug on tens of billions of dollars of investment they have planned for the region,” said AWEA in a statement.

Simply put, wind would no longer be economical under the MISO scheme, and some projects that are waiting in the wings would be killed.

Without the planned turbines, states in the Upper Midwest, which include Minnesota, Wisconsin, Illinois, Indiana, and the Dakotas, may struggle to meet their renewable energy goals and mandates, the AWEA says. America as a whole would be hard-pressed to reach the White House ambition of doubling the nation’s supply of renewable energy in the next three years sans the Upper Midwest, known as the “Saudi Arabia of wind.”

As AWEA and WOW see it, the MISO policy is “unworkable” for the wind sector because of this fact. It assigns nearly all of the costs of upgrading the grid to the next wind plant waiting in line to connect to it. It’s akin to

“requiring the next car entering a congested highway to pay the full cost of adding a new lane,” said WOW Director Beth Soholt.

The Upper Midwest isn’t alone on this issue. Transmission has become the major tripwire to America’s green-powered future.

One of the biggest hang-ups is over a cross-country transmission superhighway that would zap electricity from America’s midsection to the urban areas that need it. The plan carries a massive, multi-billion dollar price tag. Those in favor say it would move the nation toward a clean renewable energy future. Those against see it as a total waste of cash, a covert attempt to serve some of the dirtiest coal plants, giving them access to new markets through transmission.

And then there’s the big issue of cost: Who would pay for it?

The MISO proposal is a local version of that long-simmering cost dispute.

What’s clear is that loading up the costs on generators could price many wind farm plans out of existence. There’s also the issue of costs to electricity consumers. The price hike to generators that a shift to MISO’s cost sharing would bring would be passed onto certain Midwestern consumers. They’ll end up paying more for the transmission of wind, and may not even benefit, if it gets sent to neighboring states. That could stymie public support for new wind energy.

AWEA and WOW have an alternative vision — to more broadly distribute transmission-line investments “in a way that matches the broadly distributed benefits of building a stronger grid, such as improved reliability and reduced power prices.”

But MISO’s rationale for its policy suggests something else entirely — that wind shouldn’t be the only game in town in the Upper Midwest.

“We continue to focus on addressing the challenges of integrating large quantities of wind through ongoing work with our stakeholders and state officials. This work includes developing long-term transmission plans, cost allocation strategies and other market solutions that preserve and enhance the ability of all resources, including wind, to integrate and operate efficiently.”

FERC has not indicated whether it favors MISO’s proposal or would recommend changes.

In a ruling in June on the Southwest Power Pool (SPP), the agency sided with the wind industry, deciding to more broadly and fairly spread the cost of building new transmission to all users of the SPP electric grid.

SPP serves Kansas, and parts of New Mexico, Texas, Oklahoma, Arkansas, and Louisiana, Missouri and Nebraska. In response to the decision, AWEA was hopeful for future transmission rulings:

“We hope other regions and the federal government will follow their lead and institute similar reforms so that we can begin to put the world-class wind resources that are currently stranded in rural parts of this country to use.”

800lbgorilla

The South Heart North Dakota coal gasification is now going to be an ELECTRIC GENERATION plant.  DUH!  The 800 pound gorilla has just started jumping around the room.  This IGCC plant will be up and ready just in time to use CapX 2020 transmission — DUH!  And if you’re surprised, you’re in the wrong business.

Published August 01 2009

A change in plant plans

What was slated to be a coal gasification plant near South Heart will now produce electricity, a company spokesman said Friday.

By: Jennifer McBride and Beth Wischmeyer, The Dickinson Press

What was slated to be a coal gasification plant near South Heart will now produce electricity, a company spokesman said Friday.

Members of the Industrial Commission of North Dakota continue to support Great Northern Project Development/Allied Syngas Corp.’s ongoing development of the South Heart project. The commissioners prepared a letter of support to Chairman Charles Kerr of GNPD, after discussing the project at their Friday meeting in Bismarck. Commissioners have supported the project and $10 million has been committed to it, along with legislative and technical support, according to the letter.

“The site is ideally located to take advantage of the existing transmission infrastructure and GNPD’s unique access to extensive, low-cost coal reserves,” according to the letter.

The plant will be located four miles south and two miles west of South Heart and will be a

coal-to-hydrogen electrical generation plant.

Rich Voss, Great Northern vice president, said the company asked the commission for support because it is applying for U.S. Department of Energy funding for its plant. Voss said this plant will be more marketable and is a very clean project carbon-wise. He hopes plant construction will begin in 2011 and said permits for the 2 million ton-per-year coal mine are likely to be filed late this year or early next year.

“They originally were going to be a power plant, then a gasification plant then a coal-drying plant, so the next logical attempt will be electricity,” said Mary Hodell, a member of Neighbors United, a citizen-awareness group based out of South Heart. “I don’t know what is left.”

Voss said Great Northern and GTL Energy, a company seeking to operate a coal beneficiation plant also near South Heart, are independent companies.

“We are not working together,” Voss said. “We will use their technology in our plant when they build it and prove that it works, but we won’t use their equipment.”

The cost to build Great Northern’s plant is estimated at $1 billion.

“The county does have a comprehensive plan that is in place to protect the livelihood of the people and it would be nice if that was followed,” Hodell said.

Are we going to let them get away with this?  I love it when my hunches are right, but I hate it when anyone has the audacity to propose something so utterly stupid as this.  It will be hard for them to get it up and running… except who has a power plant application ready to rock (except that it’s a joke, but it takes some time to prove that to the PUC)?  Drat… and here I thought Tom would be down in Honduras trying to build Mesaba down there…

800lbgorilla2

Excelsior Energy’s Mesaba Project has been delayed… AGAIN… until June… and when we get closer to June, well, we know what will happen… delay again!

DOE chart showing Mesaba FEIS delay March 13 2009

Thanks to Charlotte Neigh and CAMP for keeping on this!