Scoping Comments on Clearbrook 115 kV
March 8th, 2016
This is the Clearbrook – Clearbrook West 115 kV transmission project proposed route.
Comments were due on the scope of environmental review for this project, and here’s what we filed yesterday:
It looks like a simple little thing, right? WRONG! What’s not readily apparent is that this transmission line is support for the Sandpiper crude oil pipeline, and is dependent on location of a tank farm and pumping station at the northwest terminus of the transmission line, and it’s way, way premature.
Couple of main points:
- This transmission line is IN ADDITION to an existing 7 pipelines and the Sandpiper pipeline and the Line 3 rebuild all in that corridor, on the northwest end running cross country through wetlands between Erie Lake and Klongerbo Lake! That’s 9 pipelines and a transmission line all right there in that narrow strip of property. How much can a family bear?!?!
- The Sandpiper pipeline is delayed, even the Enbridge proponents admit that:
Enbridge: Sandpiper Pipeline Delayed Until 2019
- Clearbrook West terminal is NOT permitted and is NOT a done deal, in fact the MPCA says it ought to be in Crookston!
So why is Minnkota Power pushing for this transmission line now? Why would they apply for it in 2014? There’s no need… not now and maybe not ever.