Bent Tree Order filed by PUC
June 5th, 2018
The settlement agreements for Minnesota’s first landowner buyouts were approved by the Public Utilities Commission at its agenda meeting on May 17, 2018. Today, it’s REAL, the written order has been filed.
Thanks to Alliant/Wisconsin Power & Light for their work in getting this done. Now, time for a couple of closings!
And at the same time, let’s whip this wind siting process into shape!
It’s been a busy week. First the release of the ALJ Recommendation for the Freeborn Wind Proect:
OAH+80-2500-34633+Findings of Fact, Conclusions of Law, and Recommendation
In the STrib today, on both Freeborn Wind and the Bent Tree project!:
Administrative Law Judge says PUC should reject Freeborn County wind project
A couple of choice snippets from STrib article:
and:
Methinks they’re getting the message that wind projects can no longer steamroll communities. It’s time for rulemaking, it’s time for revision of “standards” to something people can live with, it’s time to use proper, applicable, siting criteria, DOH!.
And today was yet another big day, because the Public Utilities Commission approved settlement agreements for two families who have been living under the Bent Tree wind project. This is the first time in Minnesota that landowners within a wind project have been bought out.
It’s real.
Here are the Staff Briefing Papers:
The room was packed, and I hope that the this “first” wasn’t lost on the audience. Wind has shifted direction. Are you paying attention?
Bent Tree – Motion for Order to Show Cause filed today!
February 19th, 2018
Here ’tis:
It’s been years and years, and we’re getting to where administrative remedies are almost exhausted! What more does the Public Utilities Commission need to act?
There’s two studies now showing noise levels above what’s allowed under MPCA rule and the Bent Tree permit.
But wait… there was post-construction monitoring showing the same way back in 2011!
How long does it take to enforce noise regulations? Too long, so far.