On Tuesday, Commerce is having a wind project transmission scoping meeting (MPUC Docket 17-322):

6 p.m. on December 19, 2017

Room 124

 Riverland Community College

Albert Lea, MN

The Albert Lea Tribune printed my Letter to the Editor about the Freeborn Wind Farm transmission scoping meeting:

Letter: Meeting on new wind farm is planned next week

At 6 p.m. Dec. 19 in Room 124 at Riverland Community College, the Minnesota Department of Commerce is holding a public comment and scoping meeting for the transmission line designed to serve the Freeborn Wind project. This is the opportunity for you to raise any questions and concerns about what issues should be investigated and reviewed in the Department of Commerce’s environmental review. This includes all of the things you know about the area, and any alternatives that should be in the mix.

Minnesota has a policy of non-proliferation of transmission corridors, which means that as a matter of law, transmission should be routed using existing corridors, such as transmission lines already in place or road right of way.  This line, instead, is proposed to traverse cross country.  That’s not non-proliferation.

Another problem is that Freeborn Wind developers claim they have land rights to all land needed for this transmission line, and then state that they’ll use eminent domain if they don’t. Well, which is it? And it’s troubling, because only public service corporations have the power of eminent domain, but Freeborn is a LLC, not a public service corporation. To make things more complicated, need has not been demonstrated, and there is no certificate of need. Need is a requirement for use of eminent domain. What’s their basis for saying they can use eminent domain?

This is yet another overreach by the developers — more infrastructure, which would forever change the landscape of this community.  Dec. 19 at Riverland College — now is the time to speak up!

Carol A. Overland

Attorney for Association of Freeborn County Landowners

Freeborn’s MISO info for J407

December 15th, 2017

Here’s what I’ve been able to find about MISO J407, the number provided by Xcel Energy in their 16-777 Resource Acquisition docket that included the Freeborn Wind project:

Xcel_Petition_201610-125953-02

And from Xcel’s Petition on interconnection (click for larger version):

And here’s what I could find from MISO:

miso-february-2015-initial-posting

20170117 IPTF Item 01f DPP Updates

20160714 IPTF Item 02 DPP Study Updates

GI-FeS-2014-DEC-J407-Report

GI DPP 2015 FEB West SIS PJM Addendum R2

There ya have it!

Here it is:

17-410+Comments & Draft Site Permit

Now, get to work reading and doing a thorough mark-up!

 

Ah, yes, it’s that time of year again… remember this map, way back when, connecting existing coal plants to the proposed CapX 2020 system? (note the Mid-American coal plant built in 2007 over by Council Bluffs isn’t there, it’s at the green lines on the southwest side where transmission starts.)

It’s the Power Plant Siting Act Annual Hearing!

Here’s the full notice:

2017_Docket 17-18_Notice_201711-137509-01

And going back in history:

2000 Summary of Proceedings

2000 Report EQB

2001 Summary of Proceedings

2001 Report EQB

2002 Summary of Proceedings

2002 Report to EQB

2003 Summary of Proceedings

2003 Report to EQB

2004 Summary of Proceedings

2004 Report to EQB

2005 Report to PUC

2006 Report to PUC – Docket 06-1733

2007 Report to PUC – Docket 07-1579

2008 Report to PUC – Docket 08-1426

2009 Report to PUC – Docket 09-1351

2010 Report to PUC – Docket 10-222

2011 Report to PUC – Docket 11-324

2012 Report to PUC – Docket 12-360

2013 Report to PUC – Docket 13-965

2014 Summary Report– Docket 14-887

2015 Summary Report – Docket 15-785

2016 Summary Report — Docket 16-18

Here’s the summary of what I had to say last year, from the report above:

Does this sound familiar?

Meanwhile, we’re still waiting on the rulemaking, 12-1246, which addresses PPSA siting rules, Minn. R. Ch. 7850.  To see rulemaking docket, which ostensibly is to address the changes in the 2005 Transmission Omnibus Bill from Hell, go HERE and look up rulemaking docket 12-1246.

I expect this rulemaking to reach the Public Utilities Commission before I drop dead.  But I’m starting to wonder.  The “12” in “12-1246” means the docket was opened in 2012.  This is 2017, almost 2018.  Good grief!