keystone-pipeline_SuppliedtoCBCPhoto from CBC(“supplied”)

There’s a big pipeline eruption underground, to the point that it’s bubbling up out of the ground, discovered by a passerby/landowner, near, but not at, a pumping station.

Why do I say big?  Well, for a pipeline to spring a leak, and for it to reach the surface, it must be a lot of oil.  And it will be a major effort to find the problem, fix it, and clean up the damage.  I won’t use the words “spill” or “leak” to describe it, because those sound so pesky and innocent, and will stick to “eruption” or “disgorge” or some such, to convey the impact and damage expected from something like this.

TransCanada_NationalObserverTransCanada’s Russ Girling

Try finding news articles about this!  Try, I dare ya!  There’s not more than a handful.

Keystone pipeline shut down after crude leak in South Dakota

Keystone pipeline springs leak in South Dakota

TransCanada shuts down Keystone pipeline after oil spill in South Dakota

TransCanada shuts down Keystone pipeline after oil seeps to surface

This isn’t going to just go away.  Cindy Myers has been posting some great photos, maybe those “supplied” to the CBC are hers?  I’ve asked for permission to post… waiting for response.

Map

Today it’s a meeting or two about a pipeline, but that’s not all… it’s also about a gas plant at the beginning of this pipeline route!

First the pipeline — Minnesota Energy Resources Corporation is the applicant, and it’s PUC Docket 15-8858, a docket for a pipeline route on the west and southern edges of Rochester, Minnesota, starting at the “Westside” substation on the west side of town, along the big gas transmission pipeline that runs parallel with Hwy. 14.  From there it goes a section west, and then south and around to the east.

mtg

Meeting Presentation

And lo and behold, last week, Rochester Public Utilities announced its long planned natural gas generating plant for that same location as this pipeline starts, at 19th St. NW and 60th Ave. N. W.  This proposed plant was at issue during the CapX 2020 Transmission Certificate of Need docket, where RPU discussed building a natural gas plant in its RPU_34945_Report_June_2005.  Here’s the 2015_update_rpu_infrastructure_study.  During the CapX 2020 CoN hearing, that notion was pooh-poohed, but we knew better.  And voila, here it is!

First they brought it up at RPU Board meetings over the summer:

PUB- Resolution 4315 – Resolution: West Side Energy Station

Westside Energy Station Epc – Bids in Minnesota

And finally, last week, RPU made it’s plans to add new natural gas generation VERY public:

A New Generating Station for Rochester

Back in that CapX 2020 Certificate of Need proceeding (PUC Docket 06-1115) it was an issue because the “need” used to justify CapX 2020 transmission to Rochester was so very small that it could be met with this RPU planned natural gas plant.  Here’s what I wrote in the 2008 No CapX 2020 Initial Brief:

Most importantly, the need is overstated. In addition to modeling performed with all local generation off line, infrastructure planned was not considered. For example, in Rochester, there are FOUR 161kV lines planned that were not taken into consideration, and which could well serve Rochester’s needs. In addition, RPU, the Rochester utility, has planned for new generation at the West Side substation (Ex. 100, lower left corner), where two of those four lines will be connection to serve Rochester. Ex. 157, Report on the Electric Utility Baseline Strategy for 2005-2030 Electric Infrastructure, June 2005, Summary p. S-21-S-22. Specifically, this report recommends actions that have been taken by RPU, resulting in the Westside Substation and transmission from it to serve the city:

Consider taking options on approximately 100 acres of land within the RPU service territory near a high pressure gas line and transmission facilities under RPU control for installation of future combustion turbine capacity.

…Around 2014, assuming that new generation is required in accordance with the long range plan and that generation has not been installed in connection with the transmission issue, begin the process for installation of approximately 50-100MW of natural gas-fired generation for an inservice date of 2018. The generation should be low capital cost with as low an operating cost as is consistent with expected operating capacity factors.

Id.

Local load as a reason for CapX is not supported by the evidence. The need, even if assumed, can be met in other ways, and these small amounts, if assumed in its entirety, cannot justify a project of this size.

And here we are, deja vu all over again.  Guess we need to make sure that phased and connected actions are considered in this pipeline environmental review.

And another thing, this pipeline environmental review — the PUC, despite that Sandpiper case, ordered a “comparative environmental analysis.”

PUC_Order – February 3, 2016, PUC eDockets #20162-117966-01

Nope, that “environmental review lite” is NOT sufficient…

11924293_10204793438938937_3891610473493333103_n

Yes, it’s TOMORROW!  Great River Energy and Minnesota Power want to build a transmission line to solve a distribution problem (age and overloads) and power up pipeline pumping stations for the MinnCan MPL Line 4 and for another “potential” project, oh, maybe, perhaps, the Sandpiper pipeline?

6:00 p.m.

Monday, October 19, 2015

Menahga Senior Center

19 Cedar Avenue

Menahga, MN  56464

For more information, check this Legalectric post:

A transmission project with a pipeline driver

You can see everything in the Public Utilities Commission docket, just go to DOCUMENT SEARCH HERE and search for either Certificate of Need docket 14-787 or Route Permit docket 14-797.

TOMORROW!

Dog_shocked

WHAT!?!?!  Yes… Really… after the delightful decision from the Appellate Court requiring an Environmental Impact Statement, telling the Public Utilities Commission that an EIS must be completed before a Certificate of Need can be issue, the Applicants dropped  Petition.  Read this whale-eye inducing filing from North Dakota Pipeline Company, LLC (a/k/a Enbridge) hot off the press:

North Dakota Pipeline Company _ Petition for Rejoinder and Comment Period 20159-114150-03

Here’s the short version:

Untitled

Once more with feeling, here’s the Appellate Court’s decision:

OPa150016-091415

And the bottom line:

BottomLine

So from this order of the Appellate Court “to complete an EIS” the Applicant now asks for the “need” docket and “routing” docket to be brought back together and to use the “Comparative Environmental Analysis” that the Appellate Court says isn’t sufficient.  Yes, that what they’re saying:

Untitled

What planet is North Dakota Pipeline Company living on?  Earth to Mars!!!!!  A “CEA” is not sufficient.  MEPA requires an EIS.  The court told the Public Utilities Commission to complete an EIS.  The Court did NOT say to go ahead with a “CEA.”

Not too long ago, Lisa Agrimonti sent around notice that she had moved over to Fredrickson & Byron.  $50 says that she’ll be filing Notice of Appearance for this docket!

 

 

 

DSC00141Putting MinnCan pipeline through the Nietes field

Today the Minnesota Court of Appeals finally determined that under the Minnesota Environmental Policy Act, a full Environmental Impact Statement, not the abbreviated “Environmental Report,” is required.  I’ve been before the Appellate Court, the Public Utilities Commission, the Administrative Law Judge, in Comments to the Dept. of Commerce, and at the Rulemaking Advisory Committee for Minn. R. ch. 7849 how many times on this?!?!? … sigh… OK, whatever…

Sent this to the PUC’s rulemaking staff because we’ve got to make sure the Certificate of Need rules are in line with this decision:

Letter_AppellateCourt_Sept142015

So back to today’s Appellate decision — I’m glad they’re finally acknowledging this problem.  Very, very glad to see this order to remand to the Public Utilities Commission for a full Environmental Impact Statement, as required by the Minnesota Environmental Policy Act.

Here is the decision:

OPa150016-091415

Here’s the meat of it — it’s so simple — why did it take so long?

Here the MPUC deviated from its usual practice and chose to conduct the certificate of need proceedings prior to the routing permit proceedings. As a result, the MEPA-compliant environmental review associated with the routing permit would not occur until after a decision was made on the certificate of need. Neither party challenges the underlying decision to bifurcate the proceedings, but FOH argues that making a decision on the certificate of need in the absence of an EIS violates MEPA. The MPUC and NDPC contend that requiring an EIS at the certificate of need stage is inconsistent with the EQB’s longstanding determination that the alternative environmental review conducted as part of the routing permit proceedings satisfies MEPA. We agree with FOH, and see this as a simple question of statutory interpretation that requires us to examine the plain meaning of two MEPA provisions.

Relying on subdivision 2b, FOH contends that the issuance of a certificate of need constitutes a “final governmental decision” to grant a permit, and as such is prohibited until an EIS has been completed. We agree. For purposes of MEPA, the definition of permit includes a “certificate, or other entitlement for use or permission to act that may be granted or issued by a governmental unit.” Minn. R. 4410.0200, subp. 58 (2013) (emphasis added). This unambiguous definition encompasses a certificate of need. All parties also agree that once the MPUC decides to grant a certificate of need, its decision regarding the issuance of that specific permit is final. Therefore, based on the plain language of subdivision 2b, the MPUC’s issuance of a certificate of need constitutes a final governmental decision that is prohibited until the required environmental review is completed.

We are also not convinced that an EIS is not required before a certificate of need may be issued simply because the EQB has approved the environmental assessment associated with the routing permit process as an adequate alternative to a formal EIS. While the substance of this alternative review process may be equivalent to an EIS, its approval as an alternative by the EQB says nothing about when a final governmental decision to grant a permit may or may not be made in the absence of an EIS, which is specifically addressed by subdivisions 2a and 2b. Minn. Stat. § 116D.04, subds. 2a, 2b. We also note that the legislature could have clearly stated that a certificate of need for a large oil pipeline was excluded from the environmental review requirements of MEPA, but it declined to do so. See Minn. Stat. § 116D.04, subd. 2a(a) (authorizing EQB to establish categories of action for which an EIS is mandatory and identifying certain actions for which an environmental assessment worksheet or EIS shall not be required). As a result, in the absence of a statutory exclusion or an explicit statement by the EQB that the approved routing permit application process supplants the need for environmental review at the certificate of need stage, subdivisions 2a and 2b must control our determination of whether environmental review is required. The unambiguous language of those provisions mandates that in a situation such as this, when the MEPA-compliant environmental review would not occur until after a certificate of need was issued, an EIS must be completed as part of the certificate of need proceedings.

Finally, we point out that requiring an EIS during the initial certificate of need proceedings affirms the emphasis MEPA places on conducting environmental review early on in the decision-making process. Specifically, MEPA states that, “[t]o ensure its use in the decision-making process, the environmental impact statement shall be prepared as early as practical in the formulation of an action.” Id., subd. 2a. This emphasis on timing is also consistent with the way federal courts have applied the National Environmental Policy Act (NEPA), which we may look to for guidance when interpreting MEPA. See Minn. Ctr. for Envtl. Advocacy v. Minn. Pollution Control Agency, 644 N.W.2d 457, 468 (Minn. 2002). The United States Supreme Court has explained that the early-stage environmental review similarly required by NEPA is critical because it “ensures that that important [environmental] effects will not be overlooked or underestimated only to be discovered after resources have been committed or the die otherwise cast.” Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 349, 109 S. Ct. 1835, 1845 (1989)

In this case, the completion of an EIS at the certificate of need stage satisfies the imperative identified above by ensuring decision-makers are fully informed regarding the environmental consequences of the pipeline, before determining whether there is a need for it. Moreover, completion of an EIS at the initial certificate of need stage seems particularly critical here because once a need is determined, the focus will inevitably turn to where the pipeline should go, as opposed to whether it should be built at all. We acknowledge that the MPUC did order a high level environmental review to be considered during the certificate of need proceedings. But as the MPUC noted, this review was not meant to serve as a substitute for the more rigorous and detailed review needed to satisfy MEPA, and it cannot take the place of a formal EIS now. Accordingly, we conclude the MPUC erred by not completing an EIS at the certificate of need stage as MEPA requires.