RateCase_MankatoHearing

Last night there was a hearing in Mankato on the Xcel Energy rate case (Docket E002/GR-15-826).  Public participation in Public Utilities Commission dockets is supposed to be a happenin’ thang…   But there were no witnesses to question yesterday at the public hearing, and the Xcel representative who was there could not answer questions.  Worse, there was no commitment to have witnesses available to the public at the public hearings, and only advice that the public could attend the evidentiary hearing.  ATTEND?!?  When might we be able to question witnesses?

Sent this Data Practices Act Request this morning to round up the Information Requests and Responses regarding transmission, transmission riders, MISO and FERC:

Data Practices Act Request

Xcel Energy wants to shift its transmission rate recovery from CWIP and AFUDC to general rates, but there was no one there to talk about it.  These are the MVP projects at issue, in Schedule 26A, below, which are worked into MISO tariff and FERC blessed:

MVP ProjectsAnd here’s the projects in Schedule 26, below, but hmmmm, no project costs shown (click for larger view):

Sched 26I entered these exhibits:

Exhibit 1A – XcelCover_e21_Request for Planning Meeting and Dialogue – PUC Docket 14-1055

Exhibit 1B – e21_Initiative_Phase_I_Report_2014 – Xcel Filing PUC Docket 14-1055

Exhibit 2_MISO Schedule 26A Indicative Annual Charges_02262014

Exhibit 3 – FERC EL-14-12-002_ALJ Order – ROE on MISO Transmission

Next meeting I’ll have some more:

e21_MikeBull_Center for Energy and Environment

MISO Schedule 26 Indicative Annual Charges

1Q_Earnings Release Presentation_5-9-2016_1500085150

Investor Presentation – NYC-Boston_3-1-2=16_1001207698

Investor Presentation – NYInvestorMtgs_5-10-2016_1500085349

2015 10K – Xcel Energy

2015 10K – NSP

Back to last night’s hearing…

Check the rules about public participation:

1400.6200 INTERVENTION IN PROCEEDINGS AS PARTY.

Subp. 5.  Participation by public.

The judge may, in the absence of a petition to intervene, nevertheless hear the testimony and receive exhibits from any person at the hearing, or allow a person to note that person’s appearance, or allow a person to question witnesses, but no person shall become, or be deemed to have become, a party by reason of such participation. Persons offering testimony or exhibits may be questioned by parties to the proceeding.

Another, the PUC practice rules:

And yet another:

And this one (though they’ll say it isn’t applicable because a rate case isn’t part o the Power Plant Siting Act):

What about the mediation next week?  How is the public interest represented?
PublicHearingSchedule

drycasks20040405

The DOE is hosting a meeting on “consent-based” nuclear waste siting?  Who are stakeholders?  What does it take to become a “stakeholder?”  Who has legitimate authority to give consent for storing nuclear waste?  Who would agree?  And who would agree and on whose behalf, i.e., City of Red Wing, Goodhue County agreeing on behalf of those of us living here?  AAAAAAAAACK!?!?!  And given how the Minnesota legislature has dealt with nuclear waste, mandating siting “in Goodhue County.”

DOE Meeting

Thursday, July 21 from 5-9 p.m.

Hilton – 1001 Marquette

Minneapolis

From the south, hop on light rail at Ft. Snelling, and transfer or hoof it down to 10th & Marquette.

If you can’t make the meeting, check the Invitation for Public Comment in the Federal Register and email Comments to consentbasedsiting@hq.doe.gov by July 31, 2016.

Info available online at energy.gov/consentbasedsiting and the DOE’s informational booklet.

From the DOE:

The purpose of the consent-based siting public meeting is to hear from the public and interested stakeholders on what matters to you as the Department of Energy moves forward in developing a consent-based process for siting the facilities needed to manage spent nuclear fuel and high-level radioactive waste. The agenda includes a presentation from the Department of Energy’s Acting Assistant Secretary for Nuclear Energy, John Kotek. Mr. Kotek will discuss the nuclear energy activities that have brought us to this point, as well as describe the Department’s vision for an integrated waste management system and the need for a consent-based approach to siting. This presentation will be followed by a panel session with several experts providing diverse perspectives on the primary issues that need to be resolved in the design and implementation of a consent-based process. Participants will then have the opportunity to comment or ask questions to the Department and the panelists.

Following this session, there will be facilitated small group discussions on a variety of topics related to consent-based siting and integrated waste management. These small group discussions will provide the opportunity for participants to engage more closely on topics of interest to them. The Department intends for these small group discussions to be frank and open sessions on key topics that will inform the design of a consent-based process. The consent-based process will in turn serve as a framework for working with potential host communities in the future.

The agenda also includes a public comment period and two open houses with poster sessions before and after the formal meeting. The open house sessions provide participants with an opportunity to engage in less formal discussions with the Department and other meeting attendees.

wartsila-gen-set-copyWay back during the CapX 2020 proceeding, it became clear that Rochester Public Utilities planned to build gas generation just west of town, at the “Westside” site.  But this was downplayed, and ignored by the ALJ, because it would be evidence that CapX 2020 wasn’t “needed.”  And of course demand was way down, which we knew but which was also ignored, and that was one more reason CapX 2020 wasn’t needed.  The Rochester gas generation was delayed.

But recently they announced the new gas pipeline around the city, and now, the gas plant.  Today, from the MPCA:

Intent to Construct Air Emission Permit for Rochester Public Utilities Westside

MPCA requests/expects certain things to be addressed in Comments, “you must state” per the MPCA:

(1) Your interest in the permit application or the draft permit.
(2) The action you wish the MPCA to take, including specific references to the section of the draft permit you believe should be changed.
(3) The reasons supporting your position, stated with sufficient specificity as to allow the MPCA to investigate the merits of the position.

Send Comments to:

Rachel Yucuis
Industrial Division
Minnesota Pollution Control Agency
520 Lafayette Rd
St. Paul, MN 55155
Phone: 651-757-2863
Email: rachel.yucuis@state.mn.us

Graphic3

Dairyland Power Cooperative’s transmission through Onalaska and La Crosse is something to see…

Dairyland Power Cooperative and USDA’s Rural Utilities Service has released the “Q-1D South” Environmental Assessment, open for Comment until July 1, 2016:

Q1-South_Environmental Assessment (BIG FILE)

And from Dairyland’s site:

Briggs Road to La Crosse Tap (Q-1D South) – Environmental Assessment

Comments are due July 1, 2016 — send to:

USDA’s Dennis Rankin:  dennis.rankin@wdc.usda.gov

(I’d also cc DPC’s Chuck Thompson:  cat@dairynet.com)

By U.S. Mail:

Dennis Rankin

Environmental Protection Specialist

USDA Rural Utilities Service

1400 Independence Avenue S.W.

Mailstop 1571, Room 2242

Washington, DC  20250-1571

What’s to comment on?  I see two issues that should be sufficient to stop this project in its tracks — the debt load of Dairyland Power Cooperative and the physical setting of the project which too near and right over people’s homes.

Debt load — Dairyland Power Cooperative’s debt is excessive and should prohibit taking on more debt:

Dairyland Power Cooperative’s Annual Meeting was last week.  One purpose of an organization’s Annual Meeting is to discuss its financial status and approve plans going forward.

Dairyland depends on federal USDA/RUS loans to pay for its transmission expansion, such as the Q-1 transmission upgrades, including Marshland-Briggs Road and now the stretch from Briggs Road to North La Crosse south of I-90. Another USDA/RUS loan paid for Dairyland’s share of the CapX La Crosse line now blighting the bluffs. Dairyland will also be part owner of the MISO Hickory Creek to Cardinal line from Iowa to Madison. That’s a lot of transmission and loans.

Dairyland recognized this financial risk and lopsided debt/equity position, and in 2012 sought help from FERC_(DPC_Request4DeclaratoryOrder), requesting a hypothetical capital structure of 35 percent equity and 65 percent debt when its actual capital structure was 16.5 percent equity and 83.5 percent debt, and FERC did grant this relief in an Order for DPC for CapX 2020 (see FERC Docket, go HERE and plug in docket EL13-19-000).  That Order, and the 83.5/16.5% debt/equity ratio was prior to the present Q-1 D South project and the MISO MVP Hickory Creek to Cardinal transmission line.  Dairyland requested a “hypothetical” (bogus) debt/equity ratio to preserve its credit rating and enable low cost loans. The true debt level makes DPC a higher risk.

Are Dairyland members aware of the 83.5%/16.5 % debt/equity ratio and reliance on loans for major transmission projects? What’s the debt level where new projects are included? This new transmission enables increased power marketing and sales, a private purpose. Is this highly leveraged position for new transmission in the best interests of Cooperative members?

Physical setting of the project — it’s just too close!

The map way above is what the transmission system in the area looks like theoretically, according to the Wisconsin Public Service Commission, but here’s what Dairyland’s Q-1 South line looks like on the ground:

Ulman_St[1]

Really… Here’s what it looks like from a satellite with the lines drawn in, on the far south:

End of the Line

Here’s what it looks like further north — look at all those homes:

Sheet Map 3

And here’s what the Wisconsin PSC Code says about clearances in PSCW 114.234:

(2) Transmission lines over dwelling units. [Follows NESC 234C1b, p. 119] (Addition) Add the following paragraph c:
c. Transmission lines over dwelling units.
No utility may construct conductors of supply lines designed to operate at voltages in excess of 35 kV over any portion of a dwelling unit. This provision also applies to line conductors in their wind-displaced position as defined in Rule 234A2.
Note: It is the intent under s. SPS 316.225(6) that the public not construct any portion of a dwelling unit under such lines.
Note: The term “dwelling unit” has the meaning given in ch. SPS 316, which adopts by reference the definitions in NEC-2008.
Note: See s. SPS 316.225(6) Clearance Over Buildings and Other Structures, which refers to ch. PSC 114 regarding clearance of conductors over 600 volts and the prohibition of dwellings under or near overhead lines.
So look what Dairyland says about these clearance problems, first on page 3-3 of the Q1-South_Environmental Assessment in its discussion of alternatives, specifically joining with Xcel Energy, which has a similar line right through the community over homes and through yards on the other side of the highway:
p23
Though there’s no case law about this, Dairyland states, “This provision likely applies to Xcel as a public utility but not DPC as a cooperative.”  That’s pretty presumptive, with no basis for the presumption, DPC!  And they wiggle around again, claiming the code doesn’t apply to them 10 pages later:
[33_1p33_2
Do you buy that argument???  First, they don’t even cite the correct PSCW section, using “PSCW 114.234(a)(4)” rather than PSCW 114.234(a)(2).  Note they state that “public utilities may seek waivers of any rule expanding upon NESC requirements…”  But if they’re saying the code doesn’t apply to them, why would this apply to them and they can seek a waiver?  Under their argument that the PSC Code doesn’t apply to them because they’re a cooperative, then if that applied, then this would not apply to them either.  Or is it the opposite, that the Code does apply to them, they cannot rebuild the line under  and have to apply for a waiver to the PSC?  Which is it, Dairyland?  Oh, but wait, I thought part of why you’re doing it the way you are, applying to local governments, in this short segmented version of your Q-1 line, was that you don’t want to have to go to the PSC, that you’re trying to get around it…
Segments
Segmenting, particularly segmenting to avoid environmental review, is not OK, Dairyland…
Remember, comments are due July 1, 2016 — send to:

USDA’s Dennis Rankin:  dennis.rankin@wdc.usda.gov

(I’d also cc DPC’s Chuck Thompson:  cat@dairynet.com)

By U.S. Mail:

Dennis Rankin

Environmental Protection Specialist

USDA Rural Utilities Service

1400 Independence Avenue S.W.

Mailstop 1571, Room 2242

Washington, DC  20250-1571

Be there or be square — transmission open houses in eastern Iowa near Dubuque and southwestern Wisconsin near Cassville.

Monday, May 16 –
Peosta Community Center
7896 Burds Road
Peosta, IA 52068

Tuesday, May 17 –
Pioneer Lanes
1185 US (Business) 151
Platteville, WI 53818

Wednesday, May 18 –
Deer Valley Lodge
401 West Industrial Drive
Barneveld, WI 53507

Thursday, May 19 –
Deer Valley Lodge
401 West Industrial Drive
Barneveld, WI 53507

Where’s Art Hughes when you need him??

Art Hughes has died…  March 31st, 2009

Days before he died, Art Hughes was testifying in Peosta against an ITC transmission line heading east to Peosta, here’s the photo from that hearing, and the article about it is in the “Art Hughes has died…” link above.

arthughes_PeostaAnd now they’re doing another round of open houses, yesterday in Peosta, IA.  Wherefore Art thou?  Well, Art, where are you?  I guess they remember him, because this time it’s “open house” and not a meeting/hearing.  These “open houses” are held by ATC, ITC, and Dairyland about its plan for the Cardinal-Hickory Creek Transmission Project.  This project is the southern part of the “5” project on the MISO MVP project map below, from the Hickory Creek substation (near Dubuque) to the Cardinal substation (near Madison)(the northern part of 5 is the Xcel/ATC Badger Coulee line).  It’s one of the transmission lines that fills in the 345 kV transmission gaps to enable North & South Dakota to Chicago bulk power transfer.

MVP portfolio mapOnce more with feeling: Open House Schedule — each starts at 4 p.m. and goes until 7 p.m. (hello, ITC, it’s planting season, how convenient!):

Monday, May 16 –
Peosta Community Center
7896 Burds Road
Peosta, IA 52068

Tuesday, May 17 –
Pioneer Lanes
1185 US (Business) 151
Platteville, WI 53818

Wednesday, May 18 –
Deer Valley Lodge
401 West Industrial Drive
Barneveld, WI 53507

Thursday, May 19 –
Deer Valley Lodge
401 West Industrial Drive
Barneveld, WI 53507