For years, for decades, I’ve been going on and on about the inefficiency of transmission, the electric system, and line losses ad nauseum.  Y’all know that, if you’ve been paying attention.  And here we are, back to discussing inefficiency in the electric system.

The SW MN 345 kV Transmission Lines (PUC Docket 01-1958) turned on line losses.  After that close call, line losses were calculated and considered on a very different model, framing it as a percentage of THE ENTIRE EASTERN INTERCONNECT.  So what’s a little loss of 0.1%, who cares… well, as a part of THE ENTIRE EASTERN INTERCONNECT, it adds up fast.  Let me make this perfectly clear, transmission line loss is substantial.  It’s particularly substantial when you’re talking about using transmission to ship lower capacity energy, like wind and solar.  If you have long, hundreds of miles long, transmission lines, there’s not much, if any, of that energy that would find its way to its destination.

This is not news.  My engineer, Art Hughes, PhD EE, taught me so much about power engineering.  It was a struggle to keep up with him, but the knowledge I gained working with him opened doors in challenging utility infrastructure projects.  Here he is at a public hearing in Peosta, Iowa,  telling people a thing or two about transmission:
Art Hughes filed testimony in the SW MN 345 kV Transmission Lines case, PUC Docket 01-1958) — search the testimony for “losses” upon which this case turned, and was erroneously granted a Certificate of Need, and later a Routing Permit:
Oh well.   It’s long done, this transmission project and many others, the horse is out of the barn, dead, and beaten to a pulp.  There’s been a massive transmission build-out, and now they want to build yet another “transmission overlay.”  Great idea, MISO, Xcel, and all of you dreaming of this revenue generation via capital investment and ROI scheme.
Anyway, back to today’s email.

There’s a “Stakeholder Meeting” coming up:

Register here

Those words, “Stakeholder Meeting” get my attention, because just who is a stakeholder, who decides.  I don’t recall getting this email, but thankfully a client who is regarded as a “Stakeholder” did, so I’ve signed up and will spend the time to show up and raise a few points.

Minnesota Department of Commerce Division of Energy Resources Header


Upcoming Stakeholder Meeting: Opportunities and Barriers to Utility Infrastructure Efficiency

Friday, July 28th from 8:30 a.m. – 12:30  p.m.

Wilder Center – 451 Lexington Pkwy. N, Saint Paul, MN 55104

Register for this free public meeting

Meeting Details

An estimated 12-15% of the nation’s electricity production is consumed by generation auxiliary loads, transmission and distribution losses, and substation consumption. As such, there is significant potential to increase utility infrastructure efficiency by decreasing conversion losses, improving plant operations, and mitigating transmission and distribution losses throughout Minnesota’s electric grid.

The Minnesota Department of Commerce invites you to participate in a stakeholder meeting to explore opportunities and barriers to utility infrastructure efficiency projects, and to begin developing a framework to improve the overall generation, transmission, and distribution efficiency of Minnesota’s electric system.

Meeting attendees will hear from national and local experts and gain insight into how existing, new, and on-the-horizon utility infrastructure technologies can increase system efficiency, including:

  • A presentation by the Electric Power Research Institute, highlighting innovative utility infrastructure efficiency projects and approaches from around the country.
  • A presentation from Minnkota Power Cooperative, discussing lessons learned from implementing infrastructure efficiency projects in Minnesota.
  • Information about next steps in the stakeholder engagement process, including a deeper-dive examination of supply-side efficiency policy issues.

Register here

Leave a Reply